Monthly State Let Maintenance Report For Fort Worth District As Of Jul 14, 2017 Page 2 Of 4

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT & JOHNSON COUNTY
CSJ6272-53-001
Proj IDRMC - 627253001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.0101427188.621147593.5283.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-04-15
Work Began05-11-15
Work Completed
Time Computed05-11-15
Contract Working Days98
Addl Days Granted0
Working Days Charged166
Percent Time Used169
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08144001
Totals1427188.620.001147593.5283.6

CountyERATH
HighwayUS0281
FromVARIOUS ROADWAYS WITHIN
ToHOOD/SOMMERVELL ERATH COUNTIES
CSJ6273-55-001
Proj IDRMC - 627355001
Work TypeCLEANING & SEALING JOINTS & CRACKS
 
0.010603719.00748436.8099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-10-15
Work Began02-11-15
Work Completed
Time Computed02-17-15
Contract Working Days57
Addl Days Granted14
Working Days Charged25
Percent Time Used35
Contractor(s)
BICK'S CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12144006
Totals603719.000.00748436.8099.9

CountyJOHNSON
HighwaySH0171
FromVARIOUS ROADWAYS IN
ToJOHNSON COUNTY
CSJ6281-09-001
Proj IDRMC - 628109001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010639283.203119697.3099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-25-15
Work Began00-00-00
Work Completed
Time Computed04-01-15
Contract Working Days25
Addl Days Granted25
Working Days Charged50
Percent Time Used100
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12144011
Totals639283.200.003119697.3099.9

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6281-24-001
Proj IDRMC - 628124001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010659900.001550104.14100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-03-15
Work Completed08-11-15
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged23
Percent Time Used92
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6281-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12144211
Totals659900.000.001550104.14100.0

CountyTARRANT
HighwayIH0035W
FromVARIOUS BRIDGES IN
ToTHE FORT WORTH DISTRICT
CSJ6283-26-001
Proj IDBPM - 628326001
Work TypeBRIDGE REPAIR
 
0.010689452.00464761.7367.4
Work Order01-17-17
Work Began01-17-17
Work Completed
Time Computed01-17-17
Contract Working Days184
Addl Days Granted0
Working Days Charged112
Percent Time Used60
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164003
Totals689452.0018986.85464761.7367.4

CountyTARRANT
HighwayUS0377
FromVARIOUS LOCATIONS IN TARRANT, JOHNSON,
ToAND PARKER COUNTIES
CSJ6284-11-001
Proj IDRMC - 628411001
Work TypeTARFFIC SIGNAL MAINTENANCE
 
0.020580600.0053549.609.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-16
Work Began00-00-00
Work Completed
Time Computed07-25-16
Contract Working Days302
Addl Days Granted1
Working Days Charged69
Percent Time Used22
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154007
Totals580600.000.0053549.609.2

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6287-56-001
Proj IDRMC - 628756001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010738774.11632495.5190.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-08-16
Work Began02-08-16
Work Completed
Time Computed02-16-16
Contract Working Days365
Addl Days Granted46
Working Days Charged410
Percent Time Used99
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6287-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154002
Totals738774.110.00632495.5190.2

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6287-57-001
Proj IDRMC - 628757001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.010421504.75391777.4992.9
Work Order03-01-16
Work Began03-02-16
Work Completed
Time Computed03-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged350
Percent Time Used95
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6287-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154214
Totals421504.7530629.32391777.4992.9

CountyTARRANT
HighwaySH0360
FromSH 360 FRONTAGE ROADS
ToIN SOUTH TARRANT COUNTY
CSJ6287-71-001
Proj IDRMC - 628771001
Work TypeMILL & OVERLAY, MISC ROADWAY WORK
 
2.1111855641.581814228.6297.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-08-15
Work Began09-22-15
Work Completed
Time Computed09-15-15
Contract Working Days70
Addl Days Granted0
Working Days Charged55
Percent Time Used78
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 6287-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154202
Totals1855641.580.001814228.6297.7

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6288-08-001
Proj IDRMC - 628808001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010899300.00908187.3499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-28-15
Work Began09-30-15
Work Completed
Time Computed10-05-15
Contract Working Days60
Addl Days Granted0
Working Days Charged70
Percent Time Used116
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154201
Totals899300.000.00908187.3499.9

CountyERATH
HighwayFM2156
FromVARIOUS ROADWAYS IN ERATH, HOOD, WISE,
ToSOMERVELL, PARKER, & PALO PINTO CONTIES
CSJ6288-80-001
Proj IDRMC - 628880001
Work TypeSEAL COAT
 
0.0101589066.921477632.2792.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-15-16
Work Began06-15-16
Work Completed
Time Computed06-22-16
Contract Working Days30
Addl Days Granted0
Working Days Charged29
Percent Time Used96
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-80-001
BARRICADES PLUS, LLC (1.88)
FLAT LINE, INC. (15.08)
BRYDL CONTRACTING, INC. (0.83)
Contract #10154216
Totals1589066.920.001477632.2792.9

CountyTARRANT
HighwayIH0035W
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6289-08-001
Proj IDRMC - 628908001
Work TypeGUARDRAIL INSTALLATION/REPAIR
 
0.0104024750.003843207.0095.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-16
Work Began01-07-16
Work Completed
Time Computed01-14-16
Contract Working Days365
Addl Days Granted81
Working Days Charged444
Percent Time Used99
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154210
Totals4024750.000.003843207.0095.4

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6291-02-001
Proj IDRMC - 629102001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.0101301700.00998844.8476.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-16
Work Began10-03-16
Work Completed
Time Computed10-07-16
Contract Working Days75
Addl Days Granted0
Working Days Charged75
Percent Time Used100
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6291-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154016
Totals1301700.000.00998844.8476.6

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6291-15-001
Proj IDRMC - 629115001
Work TypeFULL-DEPTH CONCRETE PAEVMENT REPAIR
 
0.010385403.19389779.6399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-16
Work Began00-00-00
Work Completed
Time Computed12-01-16
Contract Working Days52
Addl Days Granted0
Working Days Charged35
Percent Time Used67
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164202
Totals385403.190.00389779.6399.9

CountyJOHNSON
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6293-58-001
Proj IDRMC - 629358001
Work TypeVEGETATION MGMT RURAL
 
0.0101029409.00382822.0037.1
Work Order04-07-16
Work Began05-04-16
Work Completed
Time Computed04-14-16
Contract Working Days214
Addl Days Granted0
Working Days Charged90
Percent Time Used42
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154213
Totals1029409.000.00382822.0037.1

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6296-04-001
Proj IDRMC - 629604001
Work TypeFULL-WIDTH MOWING
 
0.010690320.00370336.0054.7
Work Order05-19-16
Work Began05-23-16
Work Completed
Time Computed05-26-16
Contract Working Days120
Addl Days Granted0
Working Days Charged79
Percent Time Used65
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154014
Totals690320.0036019.00370336.0054.7

CountyTARRANT
HighwaySH0114
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6296-23-001
Proj IDRMC - 629623001
Work TypeROADSIDE MOWING
 
0.010857304.00309345.0036.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-12-17
Work Began05-17-16
Work Completed
Time Computed05-19-17
Contract Working Days184
Addl Days Granted0
Working Days Charged53
Percent Time Used28
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154015
Totals857304.000.00309345.0036.0

CountyPALO PINTO
HighwayUS0281
FromVARIOUS ROADWAYS IN PALO PINTO
ToAND ERATH COUNTIES
CSJ6296-64-001
Proj IDRMC - 629664001
Work TypeMOWING AND HERBICIDE
 
0.010604371.40329565.5054.5
Work Order06-16-16
Work Began05-10-16
Work Completed
Time Computed06-20-16
Contract Working Days140
Addl Days Granted0
Working Days Charged45
Percent Time Used32
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154201
Totals604371.400.00329565.5054.5

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToPARKER COUNTY
CSJ6296-65-001
Proj IDRMC - 629665001
Work TypeMOWING AND HERBICIDE
 
0.010663779.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-05-16
Work Began00-00-00
Work Completed
Time Computed05-13-16
Contract Working Days144
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154202
Totals663779.480.000.000.0

CountyERATH
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN HOOD, ERATH,
ToAND SOMERVELL COUNTIES
CSJ6296-90-001
Proj IDRMC - 629690001
Work TypeHES FLEX PVMT REPAIR
 
0.0101180000.001186131.7499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-16
Work Began09-06-16
Work Completed
Time Computed09-12-16
Contract Working Days50
Addl Days Granted0
Working Days Charged26
Percent Time Used52
Contractor(s)
BICK'S CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164201
Totals1180000.000.001186131.7499.9

page 1 | page 2 | page 3 | page 4