Monthly State Let Maintenance Report For Paris District As Of Jul 14, 2017 Page 1 Of 2

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLAMAR
HighwayUS0082
FromUS 82 W
ToUS 271 N
CSJ6203-38-001
Proj IDRMC - 620338001
Work TypeSEAL COAT SHOULDERS/CLEAN & SEAL JOINTS
 
3.560372768.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6203-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05104002
Totals372768.260.000.000.0

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6259-31-001
Proj IDRMC - 625931001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.001605150.00654829.0099.9
Work Order04-01-14
Work Began04-01-14
Work Completed
Time Computed04-08-14
Contract Working Days250
Addl Days Granted240
Working Days Charged432
Percent Time Used88
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6259-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12134025
Totals605150.007987.00654829.0099.9

CountyGRAYSON
HighwayUS0075
FromVARIOUS ROADWAYS IN GRAYSON, FANNIN,
ToLAMAR, DELTA, AND RED RIVER COUNTY
CSJ6269-45-001
Proj IDRMC - 626945001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.0011167978.751072263.8591.8
Work Order01-13-16
Work Began01-19-16
Work Completed
Time Computed01-19-16
Contract Working Days365
Addl Days Granted365
Working Days Charged528
Percent Time Used72
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6269-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154002
Totals1167978.750.001072263.8591.8

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN HUNT, RAINS,
ToHOPKINS AND FRANKLIN COUNTIES
CSJ6283-76-001
Proj IDRMC - 628376001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.001772192.15772662.5499.9
Work Order01-13-16
Work Began00-00-00
Work Completed
Time Computed01-19-16
Contract Working Days365
Addl Days Granted365
Working Days Charged528
Percent Time Used72
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6283-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154003
Totals772192.156672.51772662.5499.9

CountyGRAYSON
HighwaySH0091
FromVARIOUS LOCATIONS IN GRAYSON, FANNIN,
ToRED RIVER AND RAINS COUNTIES
CSJ6291-12-001
Proj IDBPM - 629112001
Work TypeENCASEMENT AND WINGWALL REPAIR/REPLACE
 
0.001476292.00355057.9277.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-16
Work Began04-25-16
Work Completed
Time Computed04-25-16
Contract Working Days75
Addl Days Granted10
Working Days Charged105
Percent Time Used123
Contractor(s)
REVEGETATION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6291-12-001
ROSS TREE SERVICE (1.07)
S&S BRIDGE PAINTING (4.22)
Contract #01164201
Totals476292.000.00355057.9277.0

CountyLAMAR
HighwayUS0082
FromLAMAR, DELTA, RED RIVER
ToGRAYSON, FANNIN COUNTIES
CSJ6292-43-001
Proj IDRMC - 629243001
Work TypeON CALL STRIPING
 
0.001633100.00297953.1547.0
Work Order01-13-16
Work Began00-00-00
Work Completed
Time Computed01-19-16
Contract Working Days365
Addl Days Granted365
Working Days Charged528
Percent Time Used72
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6292-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154201
Totals633100.0036539.80297953.1547.0

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN HUNT, RAINS,
ToHOPKINS AND FRANKLIN COUNTIES
CSJ6292-44-001
Proj IDRMC - 629244001
Work TypeON CALL TY II STRIPING
 
0.001427700.00233908.6354.6
Work Order01-13-16
Work Began01-15-16
Work Completed
Time Computed01-15-16
Contract Working Days365
Addl Days Granted365
Working Days Charged533
Percent Time Used73
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154001
Totals427700.0084174.72233908.6354.6

CountyLAMAR
HighwayUS0082
FromPARIS DISTRICT
ToALL LOCATIONS
CSJ6292-45-001
Proj IDRMC - 629245001
Work TypeON CALL RPM'S
 
0.001294594.00335818.7299.9
Work Order01-07-16
Work Began01-15-16
Work Completed
Time Computed01-15-16
Contract Working Days365
Addl Days Granted365
Working Days Charged532
Percent Time Used72
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154202
Totals294594.000.00335818.7299.9

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN HOPKINS, FRANKLIN,
ToLAMAR, DELAT, AND RED RIVER COUNTIES
CSJ6300-57-001
Proj IDRMC - 630057001
Work TypeON CALL FULL DEPTH CONCRETE REPAIR
 
0.0011571293.00691934.4744.0
Work Order10-20-16
Work Began00-00-00
Work Completed
Time Computed11-08-16
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-57-001
W.O.E. CONSTRUCTION (0.00)
DUSTROL, INC. (0.55)
Contract #07164201
Totals1571293.0020293.88691934.4744.0

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT ENTIRE
ToPARIS DISTRICT
CSJ6301-86-001
Proj IDRMC - 630186001
Work TypeON CALL TRAFFIC CONTROL SERVICES
 
0.0012302678.751404059.1660.9
Work Order10-10-16
Work Began00-00-00
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged241
Percent Time Used33
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6301-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164201
Totals2302678.75200946.101404059.1660.9

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN GRAYSON, FANNIN,
ToHUNT COUNTIES
CSJ6302-68-001
Proj IDRMC - 630268001
Work TypeON CALL FULL DEPTH CONCRETE REPAIR
 
0.0011369980.001505464.8099.9
Work Order09-19-16
Work Began00-00-00
Work Completed
Time Computed09-23-16
Contract Working Days365
Addl Days Granted0
Working Days Charged274
Percent Time Used75
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164001
Totals1369980.00373400.441505464.8099.9

CountyFANNIN
HighwaySH0056
FromAT BOIS D'ARC CREEK
ToRELIEF BRIDGE IN FANNIN COUNTY
CSJ6307-25-001
Proj IDBPM - 630725001
Work TypeBPM - ABUTMENT EROSION REPAIR
 
0.001587380.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174201
Totals587380.000.000.000.0

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT
ToPARIS DISTRICT
CSJ6308-45-001
Proj IDRMC - 630845001
Work TypeON CALL MILL AND INLAY
 
0.0014370668.543558450.7681.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-22-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged129
Percent Time Used35
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164001
Totals4370668.54680181.283558450.7681.4

CountyLAMAR
HighwayFM0079
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6311-57-001
Proj IDRMC - 631157001
Work TypeTYPE I STRIPING
 
0.0011026957.87231193.0122.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged14
Percent Time Used23
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6311-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174001
Totals1026957.87231193.01231193.0122.5

CountyRED RIVER
HighwayFM0114
FromVARIOUS ROADWAYS IN LAMAR, DELTA,
ToAND RED RIVER COUNTY
CSJ6311-78-001
Proj IDRMC - 631178001
Work TypeCROSS DRAINAGE STRUCTURE REPAIR
 
0.001478007.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174002
Totals478007.800.000.000.0

CountyHUNT
HighwayIH0030
FromIH 30 THROUGH HUNT, HOPKINS,
ToFRANKLIN COUNTIES
CSJ6313-72-001
Proj IDRMC - 631372001
Work TypeDEBRIS REMOVAL
 
0.001328038.0065125.0019.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged44
Percent Time Used17
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174001
Totals328038.0031356.0065125.0019.8

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT
ToENTIRE PARIS DISTRICT
CSJ6314-23-001
Proj IDRMC - 631423001
Work TypeILLUMINATION MAINTENANCE
 
0.001387411.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days261
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6314-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174003
Totals387411.000.000.000.0

CountyFANNIN
HighwayFM0100
FromVARIOUS LOCATIONS IN
ToFANNIN COUNTY
CSJ6314-29-001
Proj IDRMC - 631429001
Work TypeCULVERT REPAIR
 
0.001620554.0075330.0012.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-20-17
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged6
Percent Time Used13
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-29-001
HIGHWAY 19 CONSTRUCTION, LLC (93.25)
TOTAL HIGHWAY MAINTENANCE, LLC (1.60)
Contract #04174201
Totals620554.0075330.0075330.0012.1

CountyLAMAR
HighwayUS0082
FromVARIOUS ROADWAYS IN LAMAR, DELTA,
ToAND RED RIVER COUNTIES
CSJ6314-93-001
Proj IDRMC - 631493001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.001642955.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-08-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged23
Percent Time Used6
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6314-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174202
Totals642955.000.000.000.0

CountyGRAYSON
HighwayUS0075
FromVARIOUS ROADWAYS IN GRAYSON AND
ToFANNIN COUNTIES
CSJ6314-95-001
Proj IDRMC - 631495001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.001667264.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-22-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged9
Percent Time Used2
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6314-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174004
Totals667264.000.000.000.0

page 1 | page 2