Monthly State Let Maintenance Report For San Antonio District As Of Mar 13, 2024 Page 2 Of 3

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6411-43-001
Proj IDRMC - 641143001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0101270873.501822689.0299.9
Work Order04-10-23
Work Began04-16-23
Work Completed
Time Computed11-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged320
Percent Time Used87
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6411-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224218
Totals1270873.502000.001822689.0299.9

CountyCOMAL
HighwayIH0035
FromIH 35 IN COMAL AND
ToGUADALUPE COUNTIES
CSJ6411-87-001
Proj IDRMC - 641187001
Work TypeBUNDLED BID
 
0.0105782081.002216167.4338.3
Work Order03-25-23
Work Began04-01-23
Work Completed
Time Computed04-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged335
Percent Time Used45
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6411-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234011
Totals5782081.00346589.882216167.4338.3

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN GUADALUPE,
ToBEXAR, AND CALDWELL COUNTIES
CSJ6423-28-001
Proj IDRMC - 642328001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010987882.80326669.6033.0
Work Order05-08-23
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged274
Percent Time Used37
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6423-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234211
Totals987882.800.00326669.6033.0

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN KERR
ToAND GILLESPIE COUNTIES
CSJ6423-30-001
Proj IDRMC - 642330001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010850556.10281869.1133.1
Work Order00-00-00
Work Began05-10-23
Work Completed
Time Computed05-10-23
Contract Working Days730
Addl Days Granted0
Working Days Charged296
Percent Time Used40
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-30-001
JCW CONSTRUCTION, LLC (0.00)
Contract #01234012
Totals850556.100.00281869.1133.1

CountyMEDINA
HighwayUS0090
FromVARIOUS LOCATIONS
ToIN MEDINA, ATASCOSA AND FRIO COUNTIES
CSJ6423-32-001
Proj IDRMC - 642332001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010771863.30255037.6233.0
Work Order04-24-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged305
Percent Time Used41
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-32-001
JCW CONSTRUCTION, LLC (1.14)
Contract #01234212
Totals771863.30127518.81255037.6233.0

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS IN KENDALL
ToBEXAR, AND COMAL COUNTIES
CSJ6423-34-001
Proj IDRMC - 642334001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010790344.50265578.0233.6
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed05-30-23
Contract Working Days730
Addl Days Granted0
Working Days Charged276
Percent Time Used37
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234013
Totals790344.500.00265578.0233.6

CountyBANDERA
HighwaySH0016
FromVARIOUS LOCATIONS
ToIN BANDERA COUNTY
CSJ6423-38-001
Proj IDRMC - 642338001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010398370.50170079.0342.6
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged274
Percent Time Used37
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234213
Totals398370.500.00170079.0342.6

CountyCOMAL
HighwaySH0046
FromVARIOUS LOCATIONS IN COMAL
ToAND GUADALUPE COUNTIES
CSJ6423-40-001
Proj IDRMC - 642340001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010693048.50228516.0132.9
Work Order06-14-23
Work Began06-26-23
Work Completed
Time Computed06-26-23
Contract Working Days730
Addl Days Granted0
Working Days Charged249
Percent Time Used34
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234014
Totals693048.505685.50228516.0132.9

CountyUVALDE
HighwayUS0090
FromVARIOUS LOCATIONS
ToIN UVALDE COUNTY
CSJ6423-42-001
Proj IDRMC - 642342001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010635540.30263818.8341.5
Work Order00-00-00
Work Began06-19-23
Work Completed
Time Computed06-19-23
Contract Working Days730
Addl Days Granted0
Working Days Charged256
Percent Time Used35
Contractor(s)
USA DT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234214
Totals635540.3070286.70263818.8341.5

CountyWILSON
HighwayUS0181
FromVARIOUS LOCATIONS IN WILSON
ToAND ATASCOSA COUNTIES
CSJ6423-44-001
Proj IDRMC - 642344001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010573644.00179579.0031.3
Work Order06-20-23
Work Began06-26-23
Work Completed
Time Computed06-26-23
Contract Working Days730
Addl Days Granted0
Working Days Charged249
Percent Time Used34
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6423-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234015
Totals573644.000.00179579.0031.3

CountyATASCOSA
HighwayIH0037
FromIH 37
ToAT VARIOUS LOCATIONS
CSJ6424-98-001
Proj IDRMC - 642498001
Work TypeMETAL BEAM GUARD FENCE UPGRADE
 
0.010649999.00133531.2520.5
Work Order00-00-00
Work Began02-12-24
Work Completed
Time Computed02-12-24
Contract Working Days84
Addl Days Granted0
Working Days Charged12
Percent Time Used14
Contractor(s)
DIAMOND R CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6424-98-001
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.00)
Contract #12234041
Totals649999.00133531.25133531.2520.5

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS THROUGHOUT
ToSAN ANTONIO DISTRICT
CSJ6428-56-001
Proj IDMMC - 642856001
Work TypeEMULSION
 
0.010707100.00636842.9090.0
Work Order02-17-23
Work Began02-23-23
Work Completed
Time Computed02-21-23
Contract Working Days365
Addl Days Granted366
Working Days Charged374
Percent Time Used51
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6428-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234215
Totals707100.0074171.32636842.9090.0

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN SEGUIN
ToMAINTENANCE SECTION
CSJ6428-58-001
Proj IDMMC - 642858001
Work TypeHOT MIX
 
0.010325250.001299085.4699.9
Work Order00-00-00
Work Began03-06-23
Work Completed
Time Computed02-27-23
Contract Working Days365
Addl Days Granted366
Working Days Charged368
Percent Time Used50
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6428-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234016
Totals325250.0098137.961299085.4699.9

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS IN BOERNE
ToMAINTENANCE SECTION
CSJ6428-60-001
Proj IDMMC - 642860001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010606041.20816628.0499.9
Work Order00-00-00
Work Began03-22-23
Work Completed
Time Computed03-07-23
Contract Working Days365
Addl Days Granted0
Working Days Charged360
Percent Time Used98
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6428-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234216
Totals606041.200.00816628.0499.9

CountyWILSON
HighwayUS0181
FromVARIOUS LOCATIONS IN FLORESVILLE
ToMAINTENANCE SECTION
CSJ6428-62-001
Proj IDMMC - 642862001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010783436.001103097.2199.9
Work Order00-00-00
Work Began03-23-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged366
Percent Time Used50
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6428-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234017
Totals783436.00185477.941103097.2199.9

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN KERRVILLE
ToMAINTENANCE SECTION
CSJ6428-64-001
Proj IDMMC - 642864001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010620100.00564970.0091.1
Work Order00-00-00
Work Began03-27-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged366
Percent Time Used50
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6428-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234217
Totals620100.000.00564970.0091.1

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN PEARSALL AND TILDEN
ToMAINTENANCE SECTIONS
CSJ6428-66-001
Proj IDMMC - 642866001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010630200.001388960.5999.9
Work Order02-22-23
Work Began03-30-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged366
Percent Time Used50
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6428-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234018
Totals630200.00104015.261388960.5999.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS THROUGHOUT
ToSAN ANTONIO DISTRICT
CSJ6444-96-001
Proj IDRMC - 644496001
Work TypePAVEMENT MARKINGS
 
0.0101122677.501352252.9799.9
Work Order00-00-00
Work Began10-02-23
Work Completed
Time Computed10-02-23
Contract Working Days365
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234036
Totals1122677.50184498.101352252.9799.9

CountyATASCOSA
HighwayFM0478
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6449-73-001
Proj IDRMC - 644973001
Work TypeSEAL COAT
 
0.0102429817.6915500.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-30-23
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6449-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234025
Totals2429817.690.0015500.000.6

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6450-04-001
Proj IDRMC - 645004001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101131650.0062460.005.5
Work Order00-00-00
Work Began01-02-23
Work Completed
Time Computed01-02-23
Contract Working Days365
Addl Days Granted0
Working Days Charged59
Percent Time Used16
Contractor(s)
AWP SAFETY
SUBCONTRACTOR(S) FOR CCSJ: 6450-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234026
Totals1131650.0056647.0062460.005.5

page 1 | page 2 | page 3