Item No Description Units July 31, 2016 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
700 6001 POTHOLE REPAIR (STANDARD) SY     300.000 49.89000 1
700 6009 EMERGENCY MOBILIZATION EA     20.000 365.54000 1
712 2005 JT / CRCK SEAL (RUBBER - ASPHALT) LMI     368.360 466.07992 2
712 6004 JT / CRCK SEAL (POLY MOD ASPH EMULSION LMI     203.770 603.74996 1
712 6008 JT / CRCK SEAL (RUBBER - ASPHALT) LMI 1,003.890 592.00000 2,556.510 605.86946 4
730 2002 FULL - WIDTH MOWING AC     5,269.940 27.00000 1
730 6002 FULL - WIDTH MOWING AC     30,561.500 25.13286 4
731 6007 PAVEMENT EDGES, STRUCTURES & FIXTURES MI     1,096.300 84.15000 1
731 6011 BROADCAST APPLICATION AC     8,695.910 29.70000 1
734 6001 LITTER REMOVAL AC     8,644.800 8.99349 3
735 2001 DEBRIS REMOVAL (CNTR MEDIANS / MAINLANES CYC     76.000 2,000.00000 1
735 2003 DEBRIS REMOVAL (FRONTAGE ROADS) CYC     12.000 1,000.00000 1
735 2005 DEBRIS REMOVAL (ENTRANCE / EXIT RAMPS) CYC     12.000 1,000.00000 1
735 2007 DEBRIS REMOVAL (SPOT DEBRIS) MI     6.000 200.00000 1
735 6001 DEBRIS REMOVAL (CNTR MEDIANS / MAINLANES CYC     130.000 1,229.29000 1
735 6003 DEBRIS REMOVAL (FRONTAGE ROADS) CYC     12.000 954.29000 1
735 6005 DEBRIS REMOVAL (ENTRANCE / EXIT RAMPS) CYC     12.000 954.29000 1
735 6007 DEBRIS REMOVAL (SPOT DEBRIS) MI     18.000 402.37000 1
735 6068 DEBRIS - CNTR MEDIANS / MAINLANES - AREA (1) CYC     52.000 973.87000 1
738 2001 CLEANING / SWEEPING (CENTER MEDIAN) CYC     5.000 9,500.00000 1
738 2003 CLEANING / SWEEPING (OUTSIDE MAIN LANE) CYC     5.000 9,500.00000 1
738 2013 CLEANING / SWEEPING (DIRECT CONNECTOR) CYC     5.000 3,000.00000 1
738 6001 CLEANING / SWEEPING (CENTER MEDIAN) CYC     5.000 9,025.86000 1
738 6003 CLEANING / SWEEPING (OUTSIDE MAIN LANE CYC     5.000 9,025.86000 1
738 6114 CLEAN / SWEEP - OUTSIDE MAIN LANE - AREA (1 CYC     12.000 9,025.86000 1
738 6174 CLEAN / SWEEPING - DIRECT CONNECT - AREA (1) CYC     5.000 4,512.93000 1
740 2001 GRAFFITI REMOVAL (BLAST CLEANING) SF     60.000 20.00000 1
740 2002 GRAFFITI REMOVAL (PAINTING) SF     1,200.000 3.00000 1
740 2003 GRAFFITI REMOVAL (CHEMICAL CLEANING) SF     30.000 30.00000 1
740 6001 GRAFFITI REMOVAL (BLAST CLEANING) SF     20.000 19.80000 1
740 6002 GRAFFITI REMOVAL (PAINTING) SF     94.000 2.97000 1
740 6003 GRAFFITI REMOVAL (CHEMICAL CLEANING) SF     30.000 29.70000 1
752 2022 TREE REMOVAL (4" - 12" DIA) EA     600.000 40.00000 1
752 2023 TREE REMOVAL (12" - 18" DIA) EA     450.000 60.00000 1
752 2024 TREE REMOVAL (18" - 24" DIA) EA     75.000 100.00000 1
752 2025 TREE REMOVAL (24" - 30" DIA) EA     75.000 150.00000 1
752 2026 TREE REMOVAL (30" - 36" DIA) EA     18.000 200.00000 1
752 2027 TREE REMOVAL (36" - 42" DIA) EA     15.000 300.00000 1
752 2028 TREE REMOVAL (42" - 48" DIA) EA     6.000 400.00000 1
752 2029 TREE REMOVAL (48" - 60" DIA) EA     3.000 500.00000 1
752 2030 TREE REMOVAL (60" - 72" DIA) EA     3.000 500.00000 1
752 6003 TREE TRIMMING / BRUSH REMOVAL MI     730.700 1,321.98001 10
752 6004 TREE TRIMMING / BRUSH REMOVAL (CHANNELS AC     100.000 1,155.00000 1
752 6005 TREE REMOVAL (4" - 12" DIA) EA 7,400.000 24.00000 12,455.000 33.69691 7
752 6006 TREE REMOVAL (12" - 18" DIA) EA 1,164.000 48.00000 3,848.000 55.32471 8
752 6007 TREE REMOVAL (18" - 24" DIA) EA 400.000 83.00000 1,964.000 84.27189 6
752 6008 TREE REMOVAL (24" - 30" DIA) EA 165.000 165.00000 1,022.000 130.33757 6
752 6009 TREE REMOVAL (30" - 36" DIA) EA 20.000 750.00000 490.000 177.04286 6
752 6010 TREE REMOVAL (36" - 42" DIA) EA 20.000 750.00000 118.000 340.86441 6
752 6011 TREE REMOVAL (42" - 48" DIA) EA 7.000 600.00000 59.000 329.83051 5
752 6012 TREE REMOVAL (48" - 60" DIA) EA 5.000 1.00000 40.000 388.55000 5
752 6013 TREE REMOVAL (60" - 72" DIA) EA 4.000 1.00000 24.000 480.37500 5
760 6001 DITCH CLEANING AND RESHAPING (FOOT) LF     1,472,726.000 1.30754 9
770 2001 REPAIR RAIL ELEMENT (W - BEAM) LF     4,000.000 20.00000 1
770 2002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF     50.000 30.00000 1
770 2003 REP RAIL ELMNT (THRIE - BM TRANS TO W - BM) LF     50.000 30.00000 1
770 2004 REM / REPL TIMBER / STL POST W / O CONC FND EA     50.000 15.00000 1
770 2005 REM / REPL TIMBER / STL POST W / CONC FND EA     15.000 50.00000 1
770 2006 REALIGN POSTS EA     350.000 70.00000 1
770 2008 REPLACE TERMINAL ANCHOR POSTS EA     1.000 100.00000 1
770 2009 REMOVE GDRAIL END TRT / REPL WITH SGT EA     15.000 1,800.00000 1
770 2010 REPL SINGLE GDRAIL TERM IMPACT HEAD EA     12.000 1,000.00000 1
770 2011 REPLACE SINGLE GDRAIL TERMINAL RAIL LF     1,500.000 30.00000 1
770 2012 REPLACE SINGLE GDRAIL TERMINAL POST EA     100.000 60.00000 1
770 2014 REPAIR STEEL POST WITH BASE PLATE EA     12.000 100.00000 1
770 2018 REM / REPL TIMBER POST W / O CONC FND EA     350.000 40.00000 1
770 2022 REM & RESET SGT IMPACT HEAD EA     15.000 700.00000 1
770 2023 REPLACE SGT OBJECT MARKER EA     15.000 20.00000 1
770 2024 REPLACE SGT CABLE ANCHOR EA     4.990 200.00000 1
770 2025 REPLACE SGT CABLE ASSEMBLY EA     12.000 100.00000 1
770 2026 REPLACE SGT STRUT EA     1.990 100.00000 1
770 2027 REMOVE & REPLACE BLOCKOUT EA     30.000 30.00000 1
770 2031 INSTALL BLOCKOUT EA     25.000 30.00000 1
770 6001 REPAIR RAIL ELEMENT (W - BEAM) LF     5,280.000 22.79242 5
770 6002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF     110.000 29.90455 4
770 6003 REP RAIL ELMNT (THRIE - BM TRANS TO W - BM LF     55.000 27.99091 3
770 6010 REM / REPL TIMBER / STL POST W / O CONC FN EA     329.000 48.58328 4
770 6011 REM / REPL TIMBER / STL POST W / CONC FN EA     37.000 85.35135 3
770 6012 REM / REPL TIMBER POST W / O CONC FND EA     50.000 19.80000 1
770 6016 REPAIR STEEL POST WITH BASE PLATE EA     7.000 29.00000 2
770 6017 REALIGN POSTS EA     350.000 23.83571 4
770 6018 INSTALL BLOCKOUT (TYPE SPECIFIED) EA     52.000 14.54615 2
770 6019 REMOVE & REPLACE BLOCKOUT EA     112.000 12.11071 2
770 6021 REPLACE SINGLE GDRAIL TERMINAL RAIL LF     1,205.000 21.65021 2
770 6022 REPLACE SINGLE GDRAIL TERMINAL POST EA     212.000 55.38113 4
770 6024 REPLACE TERMINAL ANCHOR POSTS EA     4.000 74.75000 3
770 6027 REMOVE GDRAIL END TRT / REPL WITH SGT EA     27.000 2,291.11111 5
770 6028 REPL SINGLE GDRAIL TERM IMPACT HEAD EA     21.000 954.71429 4
770 6029 REM & RESET SGT IMPACT HEAD EA     16.000 269.62500 3
770 6030 REPLACE SGT CABLE ASSEMBLY EA     8.000 131.67500 2
770 6031 REPLACE SGT CABLE ANCHOR EA     8.000 198.50000 2
770 6032 REPLACE SGT STRUT EA     7.000 113.42857 2
770 6033 REPLACE SGT OBJECT MARKER EA     7.000 6.37143 2
770 6034 REPAIR RAIL ELEMENT (W - BEAM FURNISHED LF     500.000 7.50000 2
774 2006 REPAIR (TRACC) EA     1.000 3,000.00000 1
774 2015 REPAIR (NARROW QUAD) EA     1.000 3,000.00000 1
774 2028 REPAIR (QUAD) (N) (BAY) EA     10.000 800.00000 1
774 2038 REMOVE AND REPLACE (FASTRACC) EA     1.990 2,000.00000 1
774 2052 REPAIR (FASTRACC) LF     50.000 100.00000 1
774 2055 REPAIR (FASTRACC) (BAY) EA     12.000 400.00000 1
774 6001 REMOVE AND REPLACE (TRACC) EA     3.000 3,333.33333 3
774 6006 REPAIR (TRACC) EA     4.000 2,360.00000 3
774 6008 REPAIR (WIDE TRACC) EA     2.000 750.00000 2
774 6015 REPAIR (NARROW QUAD) EA     4.000 1,810.00000 3
774 6028 REPAIR (QUAD) (N) (BAY) EA     4.000 596.00000 2
774 6038 REMOVE AND REPLACE (FASTRACC) EA     4.000 2,240.00000 3
774 6052 REPAIR (FASTRACC) LF     20.000 99.00000 1
774 6055 REPAIR (FASTRACC) (BAY) EA     6.000 365.33333 3
776 2001 REPAIR (STEEL POST W / W - BEAM - T101) LF     50.000 60.00000 1
776 2004 REPAIR (STL POST W / DOUBLED W - BEAMS - T6) LF     50.000 20.00000 1
776 2032 REPAIR (STEEL POST W / CHANNEL IRON RAIL LF     100.000 20.00000 1
776 6001 REPAIR (STEEL POST W / W - BEAM - T101) LF     55.000 69.61818 3
776 6004 REPAIR (STL POST W / DOUBLED W - BEAMS - T6 LF     45.000 24.28889 3
776 6021 REPAIR (TY T1 - 101R) LF     160.000 135.00000 1
776 6032 REPAIR (STEEL POST W / CHANNEL IRON RAIL LF     95.000 13.61053 2
778 6011 CONCRETE RAIL REPAIR (TYPE 501) LF     22.000 350.00000 1
780 6001 CNC CRACK REPAIR (DISCRETE) (GRAVITY) LF     280.000 21.96429 2