Monthly Local Let Maintenance Report For Waco District As Of Sep 21, 2017 Page 3 Of 6

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBELL
HighwaySL0121
FromLAWN AND GROUNDS MAINTENANCE
ToFOR BELL COUNTY COMPLEX
CSJ6307-01-001
Proj IDSUP - 630701001
Work TypeLAWN AND GROUNDS MAINTENANCE
 
0.01014405.0013430.0093.2
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160932
Totals14405.000.0013430.0093.2

CountyCORYELL
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6307-02-001
Proj IDSUP - 630702001
Work TypeLAWN AND GROUNDS
 
0.01015545.009860.0063.4
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160933
Totals15545.001370.009860.0063.4

CountyHAMILTON
HighwayFM0218
FromVARIOUS
ToVARIOUS
CSJ6307-03-001
Proj IDSUP - 630703001
Work TypeLAWN AND GROUNDS
 
0.0106280.005865.0093.3
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160934
Totals6280.00830.005865.0093.3

CountyHILL
HighwaySH0081
FromVARIOUS
ToVARIOUS
CSJ6307-04-001
Proj IDSUP - 630704001
Work TypeLAWN AND GROUNDS MAINTENANCE
 
0.0109890.006150.0062.1
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160935
Totals9890.00740.006150.0062.1

CountyFALLS
HighwaySH0007
FromLAWN AND GROUNDS MAINTENANCE
ToAT THE FALLS COUNTY COMPLEX
CSJ6307-05-001
Proj IDSUP - 630705001
Work TypeLAWN AND GROUNDS MAINTENANCE
 
0.01010145.003615.00100.0
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged359
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160936
Totals10145.00380.003615.00100.0

CountyBOSQUE
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6307-06-001
Proj IDSUP - 630706001
Work TypePICNIC AREA MAINTENANCE
 
0.01052300.0040030.00100.0
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160937
Totals52300.004985.0040030.00100.0

CountyLIMESTONE
HighwaySH0014
FromVARIOUS
ToVARIOUS
CSJ6307-07-001
Proj IDSUP - 630707001
Work TypeLAWN AND GROUNDS
 
0.01010740.004550.00100.0
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160938
Totals10740.00590.004550.00100.0

CountyMCLENNAN
HighwaySS0299
FromVARIOUS
ToVARIOUS
CSJ6307-08-001
Proj IDSUP - 630708001
Work TypeJANITORIAL SERVICES
 
0.01076645.3261580.52100.0
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160939
Totals76645.324762.4161580.52100.0

CountyMCLENNAN
HighwayFM3476
FromVARIOUS
ToVARIOUS
CSJ6307-09-001
Proj IDSUP - 630709001
Work TypeLAWN AND GROUNDS MAINTENANCE
 
0.01023490.0015100.00100.0
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160940
Totals23490.001315.0015100.00100.0

CountyMCLENNAN
HighwayFM0933
FromJANITORIAL SERVICE FOR SPECIAL CREWS
To(GHOLSON)
CSJ6307-10-001
Proj IDSUP - 630710001
Work TypeJANITORIAL SERVICE
 
0.01010316.729471.60100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-30-16
Work Began08-01-16
Work Completed07-31-17
Time Computed08-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160930
Totals10316.720.009471.60100.0

CountyCORYELL
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6307-12-001
Proj IDSUP - 630712001
Work TypePICNIC AREA MAINTENANCE
 
0.01047770.0039845.0083.4
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160942
Totals47770.003500.0039845.0083.4

CountyHAMILTON
HighwayUS0281
FromVARIOUS
ToVARIOUS
CSJ6307-13-001
Proj IDSUP - 630713001
Work TypePICNIC AREA MAINTENANCE
 
0.01044370.0031410.0070.7
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160943
Totals44370.003265.0031410.0070.7

CountyHILL
HighwaySH0081
FromVARIOUS
ToVARIOUS
CSJ6307-14-001
Proj IDSUP - 630714001
Work TypePICNIC AREA MAINTENANCE
 
0.01044300.0035905.0081.0
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160944
Totals44300.004375.0035905.0081.0

CountyFALLS
HighwaySH0007
FromVARIOUS
ToVARIOUS
CSJ6307-15-001
Proj IDSUP - 630715001
Work TypePICNIC AREA MAINTENANCE
 
0.01034100.0026045.00100.0
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged359
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160945
Totals34100.002895.0026045.00100.0

CountyMCLENNAN
HighwayFM3476
FromVARIOUS ROADWAYS IN
ToMCLENNAN COUNTY
CSJ6307-16-001
Proj IDSUP - 630716001
Work TypeLITTER PICK UP AND DISPOSAL
 
0.01062824.5452596.12100.0
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160946
Totals62824.549729.4152596.12100.0

CountyLIMESTONE
HighwaySH0014
FromVARIOUS
ToVARIOUS
CSJ6307-17-001
Proj IDSUP - 630717001
Work TypePICNIC AREA MAINTENANCE
 
0.01039300.0030355.00100.0
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160947
Totals39300.003765.0030355.00100.0

CountyLIMESTONE
HighwaySH0014
FromVARIOUS
ToVARIOUS
CSJ6307-18-001
Proj IDSUP - 630718001
Work TypeJANITORIAL SERVICES
 
0.0106980.005580.00100.0
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6307-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160948
Totals6980.00465.005580.00100.0

CountyBELL
HighwaySL0121
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6307-19-001
Proj IDSUP - 630719001
Work TypeLITTER PICK UP AND DISPOSAL
 
0.01094581.0488125.0593.1
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160949
Totals94581.048829.5788125.0593.1

CountyBELL
HighwaySL0121
FromVARIOUS
ToVARIOUS
CSJ6307-20-001
Proj IDSUP - 630720001
Work TypePICNIC AREA MAINTENANCE
 
0.01016550.0012320.0074.4
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160950
Totals16550.001045.0012320.0074.4

CountyBELL
HighwaySL0121
FromVARIOUS
ToVARIOUS
CSJ6307-85-001
Proj IDSUP - 630785001
Work TypeJANITORIAL SERVIES
 
0.01028871.9627007.6693.5
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160951
Totals28871.962095.2827007.6693.5