Monthly State Let Maintenance Report For Waco District As Of Jul 11, 2014 Page 1 Of 1

Last Update: Friday, July 11, 2014
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMCLENNAN
Highway IH0035
From WILLIAMSON/BELL COUNTY LINE TO
To HILL/JOHNSON COUNTY LINE
CSJ 6202-14-001
Proj ID RMC - 620214001
Work Type ROUTINE MAINTENANCE OF IH 35
 
115.258 19631784.00 380588.18 25858981.09 99.9
Work Order 09-13-10
Work Began 09-15-10
Work Completed  
Time Computed 09-22-10
Contract Working Days 1,825
Addl Days Granted 0
Working Days Charged 1,378
Percent Time Used 75
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6202-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08104020
Totals 19631784.00 380588.18 25858981.09 99.9

CountyMCLENNAN
Highway US0084
From VARIOUS ROADWAYS IN BOSQUE, HAMILTON,
To HILL AND MCLENNAN COUNTIES
CSJ 6253-96-001
Proj ID RMC - 625396001
Work Type MULTI - COUNTY PAVEMENT MARKINGS
 
0.010 996713.00 3497.34 788603.08 79.1
Work Order 08-26-13
Work Began 08-30-13
Work Completed  
Time Computed 09-06-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 298
Percent Time Used 81
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06134004
Totals 996713.00 3497.34 788603.08 79.1

CountyBELL
Highway US0190
From VARIOUS LOCATIONS IN BELL, CORYELL,
To FALLS AND LIMESTONE COUNTIES
CSJ 6253-97-001
Proj ID RMC - 625397001
Work Type DISTRICT WIDE PAVEMENT MARKINGS
 
0.010 984989.12 131482.42 483344.62 49.0
Work Order 10-24-13
Work Began 10-31-13
Work Completed  
Time Computed 10-31-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 66
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06134019
Totals 984989.12 131482.42 483344.62 49.0

CountyMCLENNAN
Highway US0084
From VARIOUS ROADWAYS IN
To THE WACO DISTRICT
CSJ 6257-35-001
Proj ID RMC - 625735001
Work Type NON - SITE SPECIFIC SIGNAL INSTALL & MAINT
 
0.010 395648.00 0.00 129039.04 32.6
Work Order 11-08-13
Work Began 05-23-14
Work Completed  
Time Computed 11-18-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 225
Percent Time Used 30
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08134003
Totals 395648.00 0.00 129039.04 32.6

CountyHILL
Highway SH0022
From BELL, BOSQUE, CORYELL, FALLS, HAMILTON,
To HILL, LIMESTONE AND MCLENNAN CO.
CSJ 6260-12-001
Proj ID RMC - 626012001
Work Type DISTRICT WIDE DRIFT / DEBRIS REMOVAL
 
0.100 350900.00 20820.00 94570.00 26.9
Work Order 10-04-13
Work Began 10-14-13
Work Completed  
Time Computed 10-14-13
Contract Working Days 156
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 17
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6260-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08134012
Totals 350900.00 20820.00 94570.00 26.9

CountyMCLENNAN
Highway IH0035
From VARIOUS LOCATIONS
To ON IH 35
CSJ 6262-46-001
Proj ID RMC - 626246001
Work Type OVERLAY AND MILL AND INLAY
 
0.010 1019908.28 0.00 695248.23 68.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-18-14
Work Began 04-22-14
Work Completed  
Time Computed 04-29-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 25
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6262-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09134016
Totals 1019908.28 0.00 695248.23 68.1

CountyBELL
Highway FM2904
From VARIOUS ROADWAYS IN BELL, CORYELL,
To FALLS, HAMILTON, LIMESTONE & MCLENNAN
CSJ 6264-65-001
Proj ID RMC - 626465001
Work Type SEAL COAT
 
0.010 3611729.81 0.00 212291.28 5.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-09-14
Work Began 00-00-00
Work Completed  
Time Computed 07-21-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-65-001
BATTERSON,LLP( 13.19%)
Contract # 01144028
Totals 3611729.81 0.00 212291.28 5.8

CountyMCLENNAN
Highway US0084
From VARIOUS LOCATIONS IN BOSQUE, HAMILTON,
To HILL AND MCLENNAN COUNTIES
CSJ 6266-98-001
Proj ID RMC - 626698001
Work Type MULTI - COUNTY PAVEMENT MARKINGS
 
0.010 815887.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144007
Totals 815887.00 0.00 0.00 0.0

CountyBELL
Highway US0190
From VARIOUS ROADWAYS IN BELL, CORYELL, FALLS
To AND LIMESTONE COUNTIES
CSJ 6266-99-001
Proj ID RMC - 626699001
Work Type DISTRICT WIDE PAVEMENT MARKINGS
 
0.100 814468.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144018
Totals 814468.00 0.00 0.00 0.0

CountyCORYELL
Highway FM0116
From VARIOUS ROADWAYS IN CORYELL, MCLENNAN,
To BELL, AND HAMILTON COUNTIES
CSJ 6270-56-001
Proj ID RMC - 627056001
Work Type MISCELLANEOUS CONCRETE REPAIRS
 
0.100 487533.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144003
Totals 487533.00 0.00 0.00 0.0

CountyHILL
Highway SH0081
From VARIOUS ROADWAYS IN HILL, LIMESTONE AND
To FALLS COUNTIES
CSJ 6270-57-001
Proj ID RMC - 627057001
Work Type MISCELLANEOUS CONCRETE REPAIR
 
0.100 555359.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144004
Totals 555359.50 0.00 0.00 0.0

CountyBELL
Highway SP0290
From VARIOUS ROADWAYS IN
To BELL COUNTY
CSJ 6270-58-001
Proj ID RMC - 627058001
Work Type PLANING AND ACP OVERLAY
 
0.100 837162.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-07-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144035
Totals 837162.40 0.00 0.00 0.0

CountyCORYELL
Highway US0190
From VARIOUS ROADWAYS IN CORYELL AND
To HAMILTON COUNTIES
CSJ 6270-60-001
Proj ID RMC - 627060001
Work Type BASE REPAIR, UNDERDRAIN AND ACP OVERLAY
 
0.100 1887222.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144202
Totals 1887222.25 0.00 0.00 0.0

CountyFALLS
Highway SH0014
From VARIOUS ROADWAYS IN
To FALLS COUNTY
CSJ 6270-61-001
Proj ID RMC - 627061001
Work Type BASE FAILURE PAVEMENT REPAIR
 
0.010 670190.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144002
Totals 670190.00 0.00 0.00 0.0

CountyHILL
Highway FM3050
From VARIOUS ROADWAYS IN
To HILL COUNTY
CSJ 6270-63-001
Proj ID RMC - 627063001
Work Type BASE FAILURE PAVEMENT REPAIR
 
0.100 317805.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144203
Totals 317805.00 0.00 0.00 0.0

CountyLIMESTONE
Highway SH0007
From VARIOUS ROADWAYS IN
To LIMESTONE COUNTY
CSJ 6270-64-001
Proj ID RMC - 627064001
Work Type BASE FAILURE PVMNT REPAIR AND ACP O / L
 
0.010 571952.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144204
Totals 571952.00 0.00 0.00 0.0

CountyMCLENNAN
Highway US0084
From VARIOUS ROADWAYS IN
To MCLENNAN COUNTY
CSJ 6270-65-001
Proj ID RMC - 627065001
Work Type BASE REPAIR
 
0.010 1210040.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-14
Work Began 00-00-00
Work Completed  
Time Computed 07-08-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144001
Totals 1210040.50 0.00 0.00 0.0

page 1