Monthly State Let Maintenance Report For Wichita Falls District As Of Jul 14, 2017 Page 1 Of 1

Last Update: Monday, July 17, 2017
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyARCHER
HighwayFM2846
FromUS 82
ToFM 1180
CSJ6294-73-001
Proj IDRMC - 629473001
Work TypeREPLACE CULVERTS
 
0.001390263.40501776.2599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-05-16
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged59
Percent Time Used88
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-73-001
WOLFE CONSTRUCTION GROUP, INC. (1.35)
DALLAS LITE AND BARRICADE INC. (2.95)
Contract #09164002
Totals390263.400.00501776.2599.9

CountyWICHITA
HighwayIH0044
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6300-25-001
Proj IDRMC - 630025001
Work TypeONCALL GUARDRAIL REPAIR
 
0.001731750.00829779.9999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted60
Working Days Charged363
Percent Time Used85
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164002
Totals731750.00226555.99829779.9999.9

CountyWICHITA
HighwayUS0082
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6304-00-001
Proj IDRMC - 630400001
Work TypeDW ONCALL PAVEMENT MARKINGS & RPM
 
0.001853660.00630969.7173.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-26-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged275
Percent Time Used75
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6304-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164013
Totals853660.00110732.79630969.7173.9

CountyWICHITA
HighwayUS0082
FromVARIOUSE BRIDGES IN COOKE
ToWICHITA & YOUNG COUNTY
CSJ6304-34-001
Proj IDBPM - 630434001
Work TypeBRIDGE MAINTENANCE
 
0.001589293.70170838.1928.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged38
Percent Time Used50
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174201
Totals589293.7055532.52170838.1928.9

CountyCOOKE
HighwayIH0035
FromVARIOUS ROADWAYS IN
ToCOOKE AND MONTAGUE COUNTY
CSJ6308-65-001
Proj IDRMC - 630865001
Work TypeROUTINE STREET SWEEPING
 
0.001288904.0068476.0023.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-28-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6308-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164202
Totals288904.000.0068476.0023.7

CountyWICHITA
HighwayIH0044
FromVARIOUS ROADWAYS IN
ToWICHITA & WILBARGER COUNTY
CSJ6308-66-001
Proj IDRMC - 630866001
Work TypeROUTINE STREET SWEEPING & DEBRIS REMOVAL
 
0.001376742.00183292.8048.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-13-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged163
Percent Time Used44
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6308-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164002
Totals376742.000.00183292.8048.6

CountyYOUNG
HighwaySH0016
FromVARIOUS ROADWAYS IN ARCHER BAYLOR
ToCLAY MONTAGUE & WICHITA COUNTY
CSJ6309-82-001
Proj IDRMC - 630982001
Work TypeCULVERT REPLACEMENT
 
0.001956061.00793332.2882.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted30
Working Days Charged47
Percent Time Used44
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174202
Totals956061.0024840.25793332.2882.9

CountyARCHER
HighwaySH0079
FromVARIOUS ROADWAYS IN
ToARCHER COUNTY
CSJ6309-86-001
Proj IDRMC - 630986001
Work TypeGUARDRAIL UPGRADE
 
0.001632007.50196423.0031.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged12
Percent Time Used16
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174002
Totals632007.50196423.00196423.0031.0

CountyWICHITA
HighwayUS0082
FromVARIOUS ROADWAYS IN COOKE CLAY
ToMONTAGUE WICHITA & WILBARGER CO
CSJ6311-23-001
Proj IDRMC - 631123001
Work TypeDEBRIS ROMOVAL
 
0.001519787.00212940.0040.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-17
Work Completed
Time Computed00-00-00
Contract Working Days275
Addl Days Granted0
Working Days Charged123
Percent Time Used44
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6311-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174203
Totals519787.0071460.00212940.0040.9

CountyMONTAGUE
HighwayUS0287
FromFM 174
ToWISE COUNTY LINE IN MONTAGUE CO
CSJ6315-46-001
Proj IDRMC - 631546001
Work TypeMETAL BEAM GUARD FENCE UPGRADE
 
0.001518214.00163832.8531.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-15-17
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged8
Percent Time Used14
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6315-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174005
Totals518214.0053130.00163832.8531.6

CountyWICHITA
HighwayIH0044
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6318-41-001
Proj IDRMC - 631841001
Work TypeDW ONCALL GRDRAIL/CABLE BARRIER REPAIR
 
0.0011038100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174011
Totals1038100.000.000.000.0

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6318-68-001
Proj IDRMC - 631868001
Work TypeTRUCK MOUNTED ATTENUATORS (TMA)
 
0.001384890.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6318-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174203
Totals384890.000.000.000.0

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6318-84-001
Proj IDRMC - 631884001
Work TypeONCALL STRIPING & RPM
 
0.0011010918.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6318-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174002
Totals1010918.000.000.000.0

page 1