Monthly Local Let Maintenance Report For Yoakum District As Of Mar 13, 2024 Page 3 Of 4

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND CALHOUN COUNITES
To.
CSJ6433-18-001
Proj IDMMC - 643318001
Work TypeHYDRAULIC CEMENT
 
0.01018900.005880.0031.1
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged274
Percent Time Used76
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231310
Totals18900.005880.005880.0031.1

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND CALHOUN COUNITES
To.
CSJ6433-20-001
Proj IDMMC - 643320001
Work TypeLIME
 
0.01020475.000.000.0
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged274
Percent Time Used76
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231311
Totals20475.000.000.000.0

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND CALHOUN COUNITES
To.
CSJ6433-22-001
Proj IDMMC - 643322001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010123987.507456.496.0
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged274
Percent Time Used76
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231312
Totals123987.500.007456.496.0

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND CALHOUN COUNITES
To.
CSJ6433-24-001
Proj IDMMC - 643324001
Work TypeAGGREGATE
 
0.010280800.00123080.4643.8
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged274
Percent Time Used76
Contractor(s)
QUALITY HOT MIX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231313
Totals280800.000.00123080.4643.8

CountyCOLORADO
HighwayIH0010
FromDISTRICT WIDE
To.
CSJ6433-42-001
Proj IDRMC - 643342001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010274550.00206780.5575.3
Work Order00-00-00
Work Began08-31-23
Work Completed
Time Computed09-05-23
Contract Working Days365
Addl Days Granted0
Working Days Charged174
Percent Time Used47
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6433-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231302
Totals274550.000.00206780.5575.3

CountyJACKSON
HighwaySH0111
FromJACKSON COUNTY
To.
CSJ6437-29-001
Proj IDRMC - 643729001
Work TypeJANITORIAL MAINTENANCE
 
0.01010100.006760.0066.9
Work Order00-00-00
Work Began05-31-23
Work Completed
Time Computed05-31-23
Contract Working Days365
Addl Days Granted365
Working Days Charged271
Percent Time Used37
Contractor(s)
RWCS JANITORIAL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6437-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231325
Totals10100.00730.006760.0066.9

CountyVICTORIA
HighwayUS0059
FromVICTORIA MAINT OFFICE
To.
CSJ6437-75-001
Proj IDRMC - 643775001
Work TypeJANITORIAL MAINTENANCE
 
0.01014774.5210371.5570.1
Work Order00-00-00
Work Began05-24-23
Work Completed
Time Computed06-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged270
Percent Time Used73
Contractor(s)
ACE GLOBAL
SUBCONTRACTOR(S) FOR CCSJ: 6437-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231326
Totals14774.521245.0710371.5570.1

CountyVICTORIA
HighwayUS0059
FromVICTORIA COUNTY
To.
CSJ6442-46-001
Proj IDRMC - 644246001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010129650.85155500.8599.9
Work Order00-00-00
Work Began07-03-23
Work Completed
Time Computed07-05-23
Contract Working Days365
Addl Days Granted0
Working Days Charged236
Percent Time Used64
Contractor(s)
TREC SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231301
Totals129650.8532842.60155500.8599.9

CountyFAYETTE
HighwayIH0010
FromFAYETTE, GONZALES, COLORADO, AND
ToAUSTIN COUNTIES
CSJ6445-02-001
Proj IDSUP - 644502001
Work TypeSTATE USE CONTRACT
 
0.010752122.00475052.6063.1
Work Order00-00-00
Work Began07-20-23
Work Completed
Time Computed07-20-23
Contract Working Days365
Addl Days Granted0
Working Days Charged221
Percent Time Used60
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-02-001
RUCON, INC. (0.00)
Contract #06231301
Totals752122.0049773.33475052.6063.1

CountyCALHOUN
HighwaySH0035
FromCALHOUN COUNTY
To.
CSJ6445-45-001
Proj IDSUP - 644545001
Work TypeJANITORIAL MAINTENANCE
 
0.01036132.7610422.2228.8
Work Order00-00-00
Work Began07-05-23
Work Completed
Time Computed08-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged209
Percent Time Used28
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-45-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #06231302
Totals36132.762957.1010422.2228.8

CountyGONZALES
HighwayIH0010
FromGONZALES, COLORADO, AND
ToCALDWELL COUNTIES
CSJ6451-41-001
Proj IDRMC - 645141001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.01049515.030.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed07-24-24
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREC SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231310
Totals49515.030.000.000.0

CountyDEWITT
HighwayUS0183
FromDEWITT COUNTY
To.
CSJ6451-43-001
Proj IDMMC - 645143001
Work TypeHOT-MIX COLD-LAID
 
0.010292500.0092345.4031.5
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days180
Addl Days Granted0
Working Days Charged121
Percent Time Used67
Contractor(s)
BRAUNTEX MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6451-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231301
Totals292500.000.0092345.4031.5

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND WHARTON COUNTIES
To.
CSJ6452-23-001
Proj IDSUP - 645223001
Work TypeDEBRIS REMOVAL
 
0.010595403.04152654.9225.6
Work Order00-00-00
Work Began10-11-23
Work Completed
Time Computed11-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged117
Percent Time Used32
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6452-23-001
RUCON, INC. (0.00)
Contract #10231301
Totals595403.0440001.58152654.9225.6

CountyMATAGORDA
HighwayBS0035H
FromMATAGORDA COUNTY
To.
CSJ6455-47-001
Proj IDRMC - 645547001
Work TypeJANITORIAL MAINTENANCE
 
0.0107267.002159.0029.7
Work Order00-00-00
Work Began11-07-23
Work Completed
Time Computed11-07-23
Contract Working Days365
Addl Days Granted0
Working Days Charged111
Percent Time Used30
Contractor(s)
MAXPRO ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6455-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231302
Totals7267.00626.002159.0029.7

CountyGONZALES
HighwayUA0090
FromGONZALES COUNTY
To.
CSJ6455-49-001
Proj IDRMC - 645549001
Work TypeJANITORIAL MAINTENANCE
 
0.0107160.002325.0032.4
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged117
Percent Time Used32
Contractor(s)
RWCS JANITORIAL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6455-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231303
Totals7160.00550.002325.0032.4

CountyDEWITT
HighwayUS0183
FromDEWITT COUNTY
To.
CSJ6455-51-001
Proj IDRMC - 645551001
Work TypeJANITORIAL MAINTENANCE
 
0.0108020.002410.0030.0
Work Order00-00-00
Work Began10-31-23
Work Completed
Time Computed11-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged117
Percent Time Used32
Contractor(s)
RWCS JANITORIAL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6455-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231304
Totals8020.00700.002410.0030.0

CountyFAYETTE
HighwaySH0071
FromFAYETTE COUNTY
To.
CSJ6455-53-001
Proj IDRMC - 645553001
Work TypeJANITORIAL MAINTENANCE
 
0.0109030.002920.0032.3
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed11-02-23
Contract Working Days365
Addl Days Granted0
Working Days Charged116
Percent Time Used31
Contractor(s)
RWCS JANITORIAL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6455-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231305
Totals9030.00850.002920.0032.3

CountyLAVACA
HighwayUA0090
FromLAVACA COUNTY
To.
CSJ6455-55-001
Proj IDRMC - 645555001
Work TypeJANITORIAL MAINTENANCE
 
0.0108020.002310.0028.8
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed11-03-23
Contract Working Days365
Addl Days Granted0
Working Days Charged115
Percent Time Used31
Contractor(s)
RWCS JANITORIAL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6455-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231306
Totals8020.00650.002310.0028.8

CountyDEWITT
HighwayBU0077Q
FromDISTRICT OFFICE COMPLEX
To.
CSJ6455-83-001
Proj IDRMC - 645583001
Work TypeJANITORIAL MAINTENANCE
 
0.01077592.0111147.7214.3
Work Order00-00-00
Work Began01-03-24
Work Completed
Time Computed01-03-24
Contract Working Days365
Addl Days Granted0
Working Days Charged54
Percent Time Used14
Contractor(s)
JANI-KING OF AUSTIN
SUBCONTRACTOR(S) FOR CCSJ: 6455-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231305
Totals77592.016289.7211147.7214.3

CountyCALHOUN
HighwaySH0035
FromVICTORIA BARGE CANAL - CALHOUN COUNTY
To.
CSJ6456-55-001
Proj IDEMC - 645655001
Work TypeFENDER SYSTEM REPAIR
 
0.010488516.50445776.5191.2
Work Order00-00-00
Work Began11-30-23
Work Completed
Time Computed12-07-23
Contract Working Days15
Addl Days Granted0
Working Days Charged11
Percent Time Used73
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6456-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231309
Totals488516.504835.70445776.5191.2

page 1 | page 2 | page 3 | page 4