Item No Description Units August 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 2001 PREPARING ROW AC     9.806 10,708.68856 11
100 2002 PREPARING ROW STA 2.500 2,000.00000 1,281.250 386.85044 32
100 2003 PREPARING ROW (TREE) (5" TO 12" DIA) EA     64.000 328.12500 2
100 2004 PREPARING ROW (TREE) (12" TO 24" DIA) EA     1.000 1,000.00000 1
100 2008 PREPARING ROW (TREE) (0" TO 6" DIA) EA     13.000 203.84615 4
100 2009 PREPARING ROW (TREE) (6" TO 24" DIA) EA     1.000 2,400.00000 1
100 2017 PREP ROW (TREE) (GREATER THAN 8 IN DIA) EA     3.000 2,000.00000 1
100 2020 PREPARING ROW (DENSITY A) STA     75.040 4,800.00000 1
100 2021 PREPARING ROW (DENSITY B) STA     15.030 4,800.00000 1
100 2022 PREPARING ROW (DENSITY C) STA     96.290 4,800.00000 1
104 2001 REMOVING CONC (PAV) SY     4,263.000 27.81362 6
104 2009 REMOVING CONC (RIPRAP) SY 10.000 20.00000 6,201.750 28.77247 40
104 2010 REMOVING CONC (RIPRAP) CY 1.000 20.00000 339.500 51.81944 7
104 2011 REMOVING CONC (MEDIANS) SY 10.000 150.00000 249.000 30.56454 3
104 2012 REMOVING CONC (MEDIANS) CY     130.000 57.67000 1
104 2013 REMOVING CONC (FOUNDATIONS) SY     13.000 200.74000 1
104 2014 REMOVING CONC (FOUNDATIONS) CY     74.000 375.27027 3
104 2015 REMOVING CONC (SIDEWALKS) SY     1,595.000 21.41436 17
104 2017 REMOVING CONC (DRIVEWAYS) SY     724.900 22.97489 7
104 2020 REMOVING CONC (OTHER APPURTENANCES) CY     100.000 43.87000 1
104 2021 REMOVING CONC (CURB) LF     12,938.000 13.86307 29
104 2022 REMOVING CONC (CURB AND GUTTER) LF     3,757.000 13.15283 12
104 2023 REMOVING CONC (CTB) LF     2,313.000 28.53696 5
104 2025 REMOVE CONC (WINGWALL) CY     95.800 454.07098 4
104 2027 REMOVING CONC (APPR SLAB) SY     763.000 53.58322 4
104 2028 REMOVING CONC (MISC) SY     1,192.600 38.43158 9
104 2029 REMOVING CONC (CURB OR CURB & GUTTER) LF     265.000 9.00000 1
104 2032 REMOVING CONC (WHEELCHAIR RAMP) SY     148.000 22.39865 3
104 2036 REMOVING CONC (SIDEWALK OR RAMP) SY     112.000 29.93750 2
104 2037 REMOVE CONC (RAIL) LF     837.500 56.03785 7
104 2040 REMOVING CONC (PAVERS) SY     400.000 13.75000 2
104 2044 REMOVING CONC (FLUME) SY     485.000 44.92784 3
104 2045 REMOVE CONC (MISC) EA     28.000 953.57143 3
104 2048 REMOVING CONC (SIDEWALKS) (RMA) SY     550.000 10.00000 1
104 2054 REMOVING CONCRETE (MOW STRIP) LF     50.000 20.00000 1
105 2002 REMOVING STAB BASE AND ASPH PAV (2") SY     4,554.000 5.00000 1
105 2005 REMOVING STAB BASE AND ASPH PAV (3") SY     340.000 12.40000 1
105 2008 REMOVING STAB BASE AND ASPH PAV (6") SY     17.000 100.00000 1
105 2014 REMOVING STAB BASE & ASPH PAV (7" - 12") SY     40.000 21.00000 2
105 2016 REMOVING STAB BASE & ASPH PAV (16") SY     820.000 43.00000 2
105 2018 REMOVING STAB BASE AND ASPH PAV (7") SY     2,440.000 6.00000 1
105 2019 REMOVING STAB BASE & ASPH PAV (14") SY     1,591.040 12.25000 1
105 2020 REMOVING STAB BASE & ASPH PAV (12") SY     969.000 15.00000 1
105 2026 REMOVE STAB BASE & ASPH PAV (13" - 18") SY     4,500.000 10.00000 1
105 2041 REMOVING STAB BASE AND ASPH PAV (8") SY     1,062.000 14.25288 2
105 2050 REMOV STAB BASE AND ASPH PAV (24") SY     419.000 9.99000 1
105 2058 REMOVING STAB BASE & ASPH PAV (10" - 12" SY     1,498.000 25.00000 1
105 2069 REMOVING STAB BASE & ASPH PAV (4" - 6" SY     197.000 12.00000 1
105 2074 REMOVING STAB BASE AND ASPH PAV (4") SY     825.330 10.00000 1
105 2079 REMOVING STAB BASE & ASPH PAV (4" - 12") SY     1,826.000 11.00000 1
110 2001 EXCAVATION (ROADWAY) CY     49,865.400 10.48865 33
110 2002 EXCAVATION (CHANNEL) CY     10,519.000 14.83359 13
110 2003 EXCAVATION (SPECIAL) CY 2,693.000 12.00000 9,742.400 17.92825 13
112 2001 SUBGRADE WIDENING (ORD COMP) STA     4,572.790 249.81450 27
112 2002 SUBGRADE WIDENING (DENS CONT) STA     1,544.670 197.71914 8
132 2001 EMBANKMENT (FINAL) (ORD COMP) (TY A) CY     4,846.500 22.04304 13
132 2002 EMBANKMENT (FINAL) (DENS CONT) (TY A) CY     1,660.000 20.00000 1
132 2003 EMBANKMENT (FINAL) (ORD COMP) (TY B) CY     10,285.700 12.75199 17
132 2004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY 3,571.000 14.00000 23,869.000 15.32610 9
132 2005 EMBANKMENT (FINAL) (ORD COMP) (TY C) CY     9,514.700 18.59885 12
132 2006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY     645.000 26.47287 3
132 2007 EMBANKMENT (FINAL) (ORD COMP) (TY D) CY     3,044.000 31.54599 7
132 2008 EMBANKMENT (FINAL) (DENS CONT) (TY D) CY     1,628.000 25.00000 1
132 2013 EMBANKMENT (ORIGINAL) (ORD COMP) (TY C) CY     637.000 31.00000 1
132 2015 EMBANKMENT (ORIGINAL) (ORD COMP) (TY D) CY     165.000 43.69697 2
132 2017 EMBANKMENT (VEHICLE) (ORD COMP) (TY A) CY     442.000 30.85973 3
132 2019 EMBANKMENT (VEHICLE) (ORD COMP) (TY B) CY     8,839.500 22.58417 28
132 2021 EMBANKMENT (VEHICLE) (ORD COMP) (TY C) CY     13,852.000 16.20486 5
132 2036 EMBANK (FINAL) (DC) (TY E) (CSBE) CY     10.000 20.00000 1
134 2001 BACKFILL (TY A) STA     5,943.080 79.62610 12
134 2002 BACKFILL (TY B) STA     5,665.360 98.79914 30
134 2003 BACKFILL (TY C) STA     3,224.000 101.48883 2
134 2004 BACKFILL (TY A OR B) STA 670.000 147.51000 3,968.020 155.30228 16
134 2005 BACKFILL TY A CY     14.800 200.00000 1
134 2010 BACKFILL (TY B) LF     339,615.000 0.45000 2
150 2001 BLADING STA     18,668.480 38.74674 18
150 2002 BLADING HR 2.000 222.00000 823.000 115.58645 29
152 2001 ROAD GRADER WORK (ORD COMP) STA     1,324.080 138.63583 7
156 2001 BULLDOZER WORK HR     24.000 70.00000 1
158 2002 SPEC EXCAV WORK (BACKHOE) HR     42.000 83.80952 3
158 2003 SPEC EXCAV WORK (HYD EXCAVATOR) HR     81.000 71.92593 4
158 2005 SPEC EXCAV WORK (ORIGINAL) CY     738.000 29.81572 4
158 2006 SPEC EXCAV WORK (VEHICLE) CY     1,802.000 15.39401 2
160 2001 FURNISHING AND PLACING TOPSOIL (4") STA     124.690 275.00000 1
160 2003 FURNISHING AND PLACING TOPSOIL (4") SY 751.000 3.00000 46,681.370 1.65373 12
160 2004 FURNISHING AND PLACING TOPSOIL (6") SY     531.000 5.20200 2
161 2002 COMPOST MANUF TOPSOIL (BOS) (4") SY     504.000 2.00000 1
161 2005 COMPOST MANUF TOPSOIL (PB) (4") SY     312.000 6.75000 1
161 2008 EROSION CONTROL COMPOST (2") SY     120.000 6.00000 1
161 2014 COMPOST MANUF TOPSOIL (BOS OR PB) (4") SY     17,144.000 4.00000 1
161 2017 COMPOST MANUF TOPSOIL (BIP) (4") SY     2,260.000 2.19000 1
162 2002 BLOCK SODDING SY     28,733.070 4.10298 23
164 2001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 751.000 1.50000 319,720.300 0.14006 16
164 2002 BROADCAST SEED (PERM) (RURAL) (SANDY) AC     32.510 561.59151 4
164 2003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY     153,786.760 0.23780 14
164 2004 BROADCAST SEED (PERM) (RURAL) (CLAY) AC     12.000 611.67000 2
164 2005 BROADCAST SEED (PERM) (URBAN) (SANDY) SY     3,000.000 0.39000 1
164 2007 BROADCAST SEED (PERM) (URBAN) (CLAY) SY     15,049.000 0.61369 6
164 2009 BROADCAST SEED (TEMP) (WARM) SY     131,360.000 0.21525 19
164 2010 BROADCAST SEED (TEMP) (WARM) AC     5.100 424.00000 1