AVERAGE LOW BID UNIT PRICE - MAINTENANCE - STATEWIDE

Last Update: Thursday, March 20, 2014
ITEMS 100 2001 TO 164 2009
Items Items Bid Code Range
0100 - 0169
0204 - 0292
0305 - 0361
0400 - 0496
0500 - 0560
0610 - 0690
0700 - 0788
1004 - 1138
2092 - 2199
3035 - 3281
4003 - 4644
5049 - 5953
6005 - 6986
7008 - 7649
8020 - 8987
9054 - 9606
100 2001 - 164 2009
164 2010 - 169 2006
Item No Description Units February 28, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 2001 PREPARING ROW AC 0.650 8,000.00000 16.596 7,795.81827 16
100 2002 PREPARING ROW STA 44.620 691.73420 1,995.270 272.16556 34
100 2003 PREPARING ROW (TREE) (5" TO 12" DIA) EA     74.000 418.91892 3
100 2008 PREPARING ROW (TREE) (0" TO 6" DIA) EA 1.000 600.00000 8.000 443.12500 3
100 2009 PREPARING ROW (TREE) (6" TO 24" DIA) EA 1.000 2,400.00000 1.000 2,400.00000 1
100 2020 PREPARING ROW (DENSITY A) STA     75.040 4,800.00000 1
100 2021 PREPARING ROW (DENSITY B) STA     15.030 4,800.00000 1
100 2022 PREPARING ROW (DENSITY C) STA     96.290 4,800.00000 1
104 2001 REMOVING CONC (PAV) SY 5.000 50.00000 4,730.560 21.83945 6
104 2009 REMOVING CONC (RIPRAP) SY 745.000 10.61477 14,021.400 18.19294 47
104 2010 REMOVING CONC (RIPRAP) CY     1,710.900 52.41405 11
104 2011 REMOVING CONC (MEDIANS) SY     1,870.000 21.28907 4
104 2012 REMOVING CONC (MEDIANS) CY     130.000 57.67000 1
104 2013 REMOVING CONC (FOUNDATIONS) SY 13.000 200.74000 13.000 200.74000 1
104 2014 REMOVING CONC (FOUNDATIONS) CY     74.000 375.27027 3
104 2015 REMOVING CONC (SIDEWALKS) SY     1,568.000 19.22506 16
104 2017 REMOVING CONC (DRIVEWAYS) SY     474.000 22.00844 6
104 2020 REMOVING CONC (OTHER APPURTENANCES) CY     100.000 43.87000 1
104 2021 REMOVING CONC (CURB) LF 130.000 10.09231 14,114.000 4.73560 31
104 2022 REMOVING CONC (CURB AND GUTTER) LF     13,175.000 17.54081 19
104 2023 REMOVING CONC (CTB) LF 300.000 76.06000 2,293.000 28.61143 4
104 2025 REMOVE CONC (WINGWALL) CY     55.930 668.40694 6
104 2027 REMOVING CONC (APPR SLAB) SY     546.000 27.69231 2
104 2028 REMOVING CONC (MISC) SY     4,136.420 13.73085 12
104 2029 REMOVING CONC (CURB OR CURB & GUTTER) LF     2,485.000 12.81690 2
104 2030 REMOVING CONC (PILE ENCASEMENT) CY     13.000 653.84615 2
104 2031 REMOVING CONC (HEADWALL) CY     2.540 700.00000 1
104 2032 REMOVING CONC (WHEELCHAIR RAMP) SY     94.000 25.26596 4
104 2034 REMOVING CONC (COPING) LF     76.000 27.00000 1
104 2036 REMOVING CONC (SIDEWALK OR RAMP) SY     409.120 22.06052 5
104 2037 REMOVE CONC (RAIL) LF 37.000 20.00000 834.500 55.87981 6
104 2038 REMOVE CONC (ABUTMENT CAP) CY     7.500 2,000.00000 1
104 2040 REMOVING CONC (PAVERS) SY     656.000 14.67416 4
104 2044 REMOVING CONC (FLUME) SY 11.000 41.81818 485.000 44.92784 3
104 2045 REMOVE CONC (MISC) EA     29.000 1,106.89655 4
104 2048 REMOVING CONC (SIDEWALKS) (RMA) SY     550.000 10.00000 1
104 2054 REMOVING CONCRETE (MOW STRIP) LF     50.000 20.00000 1
105 2002 REMOVING STAB BASE AND ASPH PAV (2") SY     4,554.000 5.00000 1
105 2005 REMOVING STAB BASE AND ASPH PAV (3") SY     340.000 12.40000 1
105 2008 REMOVING STAB BASE AND ASPH PAV (6") SY     910.560 10.00000 1
105 2011 REMOVING STAB BASE AND ASPH PAV (2" - 6" SY     3,400.000 5.80294 2
105 2014 REMOVING STAB BASE & ASPH PAV (7" - 12") SY     2,540.000 6.18701 3
105 2015 REMOVING STAB BASE & ASPH PAV (8" - 10") SY     65.000 10.26000 1
105 2016 REMOVING STAB BASE & ASPH PAV (16") SY     410.000 42.00000 1
105 2018 REMOVING STAB BASE AND ASPH PAV (7") SY     2,440.000 6.00000 1
105 2019 REMOVING STAB BASE & ASPH PAV (14") SY 1,591.040 12.25000 1,591.040 12.25000 1
105 2020 REMOVING STAB BASE & ASPH PAV (12") SY     1,234.000 15.80956 3
105 2026 REMOVE STAB BASE & ASPH PAV (13" - 18") SY     4,500.000 10.00000 1
105 2033 REMOVING STB BASE AND ASPH PAV (10 - 14") SY     138.000 20.00000 1
105 2041 REMOVING STAB BASE AND ASPH PAV (8") SY     37,914.700 4.35883 4
105 2050 REMOV STAB BASE AND ASPH PAV (24") SY     419.000 9.99000 1
105 2058 REMOVING STAB BASE & ASPH PAV (10" - 12" SY     1,498.000 25.00000 1
105 2069 REMOVING STAB BASE & ASPH PAV (4" - 6" SY     197.000 12.00000 1
110 2001 EXCAVATION (ROADWAY) CY 1,145.000 14.68699 89,910.900 8.64799 37
110 2002 EXCAVATION (CHANNEL) CY 1,541.000 12.00000 10,901.000 15.17471 18
110 2003 EXCAVATION (SPECIAL) CY     5,628.990 21.36779 15
112 2001 SUBGRADE WIDENING (ORD COMP) STA 400.240 295.78193 6,377.140 234.58722 32
112 2002 SUBGRADE WIDENING (DENS CONT) STA     2,202.590 274.72504 10
132 2001 EMBANKMENT (FINAL) (ORD COMP) (TY A) CY 20.000 91.00000 8,502.500 19.10186 16
132 2002 EMBANKMENT (FINAL) (DENS CONT) (TY A) CY     1,660.000 20.00000 1
132 2003 EMBANKMENT (FINAL) (ORD COMP) (TY B) CY 2,237.000 6.84705 21,190.700 8.23118 19
132 2004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY 4,047.000 22.00000 26,553.000 12.37467 8
132 2005 EMBANKMENT (FINAL) (ORD COMP) (TY C) CY     5,583.440 24.85666 10
132 2006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY 25.000 75.00000 883.000 23.00227 3
132 2007 EMBANKMENT (FINAL) (ORD COMP) (TY D) CY 987.000 18.34043 4,422.000 18.52148 9
132 2008 EMBANKMENT (FINAL) (DENS CONT) (TY D) CY     1,628.000 25.00000 1
132 2013 EMBANKMENT (ORIGINAL) (ORD COMP) (TY C) CY     637.000 31.00000 1
132 2015 EMBANKMENT (ORIGINAL) (ORD COMP) (TY D) CY     165.000 43.69697 2
132 2017 EMBANKMENT (VEHICLE) (ORD COMP) (TY A) CY     494.000 31.17409 6
132 2019 EMBANKMENT (VEHICLE) (ORD COMP) (TY B) CY 103.000 25.00000 9,979.500 18.89522 33
132 2021 EMBANKMENT (VEHICLE) (ORD COMP) (TY C) CY     11,592.000 16.92890 3
132 2026 EMBANKMENT (FINAL) (DENS CONT) (TY C2) CY     90.000 55.00000 1
134 2001 BACKFILL (TY A) STA     7,318.970 76.14147 18
134 2002 BACKFILL (TY B) STA 579.120 139.13999 8,321.350 92.48659 45
134 2003 BACKFILL (TY C) STA     175.000 575.00000 1
134 2004 BACKFILL (TY A OR B) STA 21.000 400.00000 3,102.850 140.19523 16
134 2010 BACKFILL (TY B) LF     339,615.000 0.45000 2
150 2001 BLADING STA 7,011.000 36.07032 19,061.850 38.45568 22
150 2002 BLADING HR 5.000 40.00000 872.000 118.52607 30
152 2001 ROAD GRADER WORK (ORD COMP) STA     1,673.830 132.89460 10
156 2001 BULLDOZER WORK HR     1,173.000 43.50384 6
158 2002 SPEC EXCAV WORK (BACKHOE) HR     247.000 126.59919 7
158 2003 SPEC EXCAV WORK (HYD EXCAVATOR) HR     262.000 142.46565 4
158 2005 SPEC EXCAV WORK (ORIGINAL) CY     478.000 15.48954 2
158 2006 SPEC EXCAV WORK (VEHICLE) CY     1,802.000 15.39401 2
160 2003 FURNISHING AND PLACING TOPSOIL (4") SY     69,764.270 0.71613 10
160 2004 FURNISHING AND PLACING TOPSOIL (6") SY     804.000 4.92289 3
161 2002 COMPOST MANUF TOPSOIL (BOS) (4") SY     58,209.000 0.95909 2
161 2005 COMPOST MANUF TOPSOIL (PB) (4") SY     312.000 6.75000 1
161 2008 EROSION CONTROL COMPOST (2") SY 120.000 6.00000 57,825.000 1.50934 2
161 2014 COMPOST MANUF TOPSOIL (BOS OR PB) (4") SY     17,144.000 4.00000 1
161 2017 COMPOST MANUF TOPSOIL (BIP) (4") SY     2,260.000 2.19000 1
162 2002 BLOCK SODDING SY 2,199.000 3.35686 27,977.960 4.84331 27
164 2001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY     387,672.300 0.14242 16
164 2002 BROADCAST SEED (PERM) (RURAL) (SANDY) AC     32.510 561.59151 4
164 2003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 10,782.000 0.17059 326,317.760 0.13420 12
164 2004 BROADCAST SEED (PERM) (RURAL) (CLAY) AC     12.000 611.67000 2
164 2005 BROADCAST SEED (PERM) (URBAN) (SANDY) SY     3,000.000 0.39000 1
164 2007 BROADCAST SEED (PERM) (URBAN) (CLAY) SY     12,367.000 0.65492 4
164 2009 BROADCAST SEED (TEMP) (WARM) SY 4,784.000 0.22000 113,960.000 0.24502 20