Detail Letting Schedule for Bell County (FY 2014)
Bell County (FY 2014) |
CCSJ: 0015-07-081 | |||
District: | Waco | Let Date: | SEP 2013 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | IM 0354(241) | CSJ: | 0015-07-081 |
Description: | LEVELUP AND PROVIDE PFC OVERLAY | Handling Code: |
|
Limits From: | 0.3 MI S OF GRAINGER/HACKBERRY UP | Fund Cat: | 1 |
Limits To: | GRAINGER/HACKBERRY UP (SB MAINLANE) | Estimate: | $166,655 |
Length: | 0.2 Miles | Actual: | $168,925 |
Back... |
Totals for 0015-07-081 | ||
---|---|---|---|
Length: | 0.2 Miles | ||
Estimate: | $166,655 | ||
Actual: | $168,925 | ||
CCSJ: 0231-10-017 | |||
District: | Waco | Let Date: | AUG 2014 |
Highway: | BU 190F | Let Status: | Actual |
Project ID: | STP 1402(041)HES | CSJ: | 0231-10-017 |
Description: | IMPROVE TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ FM 439 INTERS | Fund Cat: | 8 |
Limits To: | . | Estimate: | $125,575 |
Length: | 0.1 Miles | Actual: | $114,526 |
District: | Waco | Let Date: | AUG 2014 |
Highway: | FM 439 | Let Status: | Actual |
Project ID: | STP 1402(042)HESG | CSJ: | 0836-03-059 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ SPARTA RD | Fund Cat: | 8 |
Limits To: | . | Estimate: | $134,968 |
Length: | 0.0 Miles | Actual: | $121,255 |
Bid Tabulations Back... |
Totals for 0231-10-017 | ||
Length: | 0.1 Miles | ||
Estimate: | $260,543 | ||
Actual: | $235,781 | ||
CCSJ: 0231-16-030 | |||
District: | Waco | Let Date: | APR 2014 |
Highway: | FM 436 | Let Status: | Actual |
Project ID: | BR 2013(589) | CSJ: | 0231-16-030 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | @ LEON RIVER | Fund Cat: | 6 |
Limits To: | (STR #042) | Estimate: | $1,628,661 |
Length: | 0.3 Miles | Actual: | $1,748,781 |
Back... |
Totals for 0231-16-030 | ||
Length: | 0.3 Miles | ||
Estimate: | $1,628,661 | ||
Actual: | $1,748,781 | ||
CCSJ: 0909-36-135 | |||
District: | Waco | Let Date: | NOV 2013 |
Highway: | CS | Let Status: | Actual |
Project ID: | STP 2011(231)TE | CSJ: | 0909-36-135 |
Description: | CONSTRUCT ALTERNATE TRANSPORATION ROUTE CONSISTING OF | Handling Code: |
LC |
Limits From: | HARRIS COMMUNITY PARK | Fund Cat: | 3 |
Limits To: | UNIVERSITY OF MARY-HARDIN BAYLOR | Estimate: | $2,294,576 |
Length: | 0.1 Miles | Actual: | $1,534,974 |
Back... |
Totals for 0909-36-135 | ||
Length: | 0.1 Miles | ||
Estimate: | $2,294,576 | ||
Actual: | $1,534,974 | ||
CCSJ: 0909-36-136 | |||
District: | Waco | Let Date: | JUL 2014 |
Highway: | CS | Let Status: | Actual |
Project ID: | BR 2013(959) | CSJ: | 0909-36-136 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | LAMPASAS RV ON TOLL BRDG RD | Fund Cat: | 6 |
Limits To: | (MAP #48-BELTON) | Estimate: | $906,432 |
Length: | 0.2 Miles | Actual: | $924,031 |
Back... |
Totals for 0909-36-136 | ||
Length: | 0.2 Miles | ||
Estimate: | $906,432 | ||
Actual: | $924,031 | ||
CCSJ: 0909-36-149 | |||
District: | Waco | Let Date: | AUG 2014 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 1402(229)MM | CSJ: | 0909-36-149 |
Description: | PURCHASE 2 BUSES FOR FIXED ROUTE SERVICE IN TEMPLE URBANIZED | Handling Code: |
TR |
Limits From: | CITYWIDE IN TEMPLE | Fund Cat: | 3 |
Limits To: | . | Estimate: | $803,303 |
Length: | 0.1 Miles | Actual: | $803,303 |
Back... |
Totals for 0909-36-149 | ||
Length: | 0.1 Miles | ||
Estimate: | $803,303 | ||
Actual: | $803,303 | ||
CCSJ: 2304-02-039 | |||
District: | Waco | Let Date: | JUN 2014 |
Highway: | FM 2410 | Let Status: | Actual |
Project ID: | STP 2014(781)MM | CSJ: | 2304-02-039 |
Description: | ADD TURN LANES TO REDUCE CONGESTION AND ENHANCE SAFETY | Handling Code: |
|
Limits From: | 822 FT W OF HIGHLAND OAKS | Fund Cat: | 3 |
Limits To: | 686 FT E OF HIGHLAND OAKS | Estimate: | $494,010 |
Length: | 0.3 Miles | Actual: | $571,433 |
Back... |
Totals for 2304-02-039 | ||
Length: | 0.3 Miles | ||
Estimate: | $494,010 | ||
Actual: | $571,433 |
|