Detail Letting Schedule for Mitchell County (FY 2016)

Last Update: Monday, February 9, 2015
Mitchell County (FY 2016)

CCSJ: 2331-01-014

District: Abilene Let Date: JUN 2016
Highway: FM 2836 Let Status: Tentative
Project ID: BR ( ) CSJ: 2331-01-014
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: AT CHERRY CREEK Fund Cat: 6
Limits To: . Estimate: $2,110,227
Length: 0.1 Miles Actual:  
 
Back...

Totals for 2331-01-014
Length: 0.1 Miles
Estimate: $2,110,227
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract