Letting Schedule for Lufkin District (FY 2018)
Lufkin District (FY 2018) |
Angelina | Houston | Nacogdoches | Polk | San Augustine | San Jacinto | Shelby | Trinity | | |||||||
Angelina County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0200-01-083 | US 69 | Actual | Dec 2017 | $1,595,129 | 1 | RESURFACE WITH THIN OVERLAY MIXTURE | 0.0 |
0200-01-089 | US 69 | Actual | Feb 2018 | $161,145 | 1 | INSTALL TRAFFIC SIGNAL | 0.0 |
2960-01-012 | FM 1194 | Actual | Nov 2017 | $451,924 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | 0.0 |
0176-03-135 | US 59 | Actual | Apr 2018 | $8,390,438 | 1 | PLANE, HMA, OCST, PFC | 0.0 |
1794-01-025 | FM 1818 | Actual | Jul 2018 | $11,414 | 10 | EMERGENCY ROADWAY REPAIRS | 0.0 |
1157-01-014 | FM 841 | Actual | Mar 2018 | $1,083,170 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0911-38-069 | CR | Actual | May 2018 | $359,675 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0911-00-075 | VA | Actual | Jun 2018 | $2,625,024 | 10 | CONSTRUCT CURB RAMPS ON VARIOUS LOCATIONS IN THE LUFKIN | 5.5 |
0200-02-039 | US 69 | Actual | May 2018 | $72,924,632 | 1 | WIDEN FROM 2 LANES TO 4 LANE DIVIDED RURAL | 5.5 |
0176-08-024 | FM 324 | Actual | Jul 2018 | $566,358 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS, SAFETY TREAT FIXED | 4.0 |
0176-03-131 | US 59 | Actual | Jul 2018 | $1,676,068 | 1 | IMPROVE GUARDRAIL TO DESIGN STANDARDS | 5.0 |
Houston County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0109-06-040 | SH 19 | Actual | May 2018 | $890,156 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARD/SAFETY TREAT FIXED | 5.0 |
0117-06-045 | SH 21 | Actual | Jun 2018 | $13,653,276 | 1 | RECONSTRUCT PAVEMENT AND ADD PASSING LANES | 4.0 |
0911-28-041 | CR | Actual | Jun 2018 | $637,127 | 6 | REPLACE BRIDGE AND APPROACHES | 3.0 |
3034-01-005 | FM 2967 | Actual | Jun 2018 | $1,828,547 | 1 | RECONSTRUCT AND WIDEN PAVEMENT | 0.0 |
0117-06-049 | SH 21 | Actual | Oct 2017 | $1,083,343 | 6 | REPAIR SUBSTRUCTURE | 0.0 |
0117-07-041 | SH 7 | Actual | Nov 2017 | $8,650,958 | 1 | RESURFACE WITH SEAL COAT | 0.0 |
0109-06-041 | SH 19 | Actual | Feb 2018 | $352,902 | 8 | MILLED EDGELINE AND CENTERLINE RUMBLE STRIPS | 0.0 |
Nacogdoches County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0336-06-028 | SH 103 | Actual | Oct 2017 | $596,207 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS | 0.0 |
1407-02-023 | FM 1638 | Actual | May 2018 | $2,764,682 | 8 | SAFETY TREAT FIXED OBJECTS; PROVIDE ADDITIONAL PAVED SURFACE | 0.0 |
0706-04-019 | FM 95 | Actual | Jan 2018 | $1,436,386 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
2590-01-020 | FM 2609 | Actual | Jul 2018 | $2,711,569 | 11 | WIDEN FROM 2 TO 4 LANES | 6.0 |
0138-06-045 | US 259 | Actual | Aug 2018 | $638,755 | 8 | UPGRADE INSTALL SAFETY LIGHTING WITHIN PROJECT | 0.0 |
0893-01-034 | FM 226 | Actual | May 2018 | $1,082,944 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS,SAFETY TREAT FIXED | 5.5 |
1407-03-018 | FM 1275 | Actual | Aug 2018 | $237,693 | 8 | IMPROVE TRAFFIC AND PEDESTRIAN SIGNALS AT LOCATION | 0.0 |
0118-08-074 | SH 21 | Actual | Dec 2017 | $1,843,142 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS, SAFETY TREAT FIXED | 6.0 |
Polk County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0928-02-020 | FM 350 | Actual | May 2018 | $1,793,394 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS, SAFETY TREAT FIXED | 6.0 |
0177-01-108 | US 59 | Tentative | Aug 2018 | $430,594 | 10 | REPLACE DAMAGED RIPRAP AND REPAIR SLOPE FAILURE NEXT TO RIPR | 0.0 |
0177-01-103 | US 59 | Actual | Mar 2018 | $640,572 | 11 | OVERLAY WITH PFC_(NORTH BOUND LANES ONLY) | 0.0 |
0911-04-046 | CR | Actual | Apr 2018 | $509,909 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
1194-01-022 | FM 943 | Actual | Apr 2018 | $9,885 | 10 | EMERGENCY ROADWAY REPAIRS | 0.0 |
San Augustine County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
1680-01-016 | FM 711 | Actual | Jan 2018 | $5,524,106 | 1 | RECONSTRUCT AND WIDEN PAVEMENT (24 FT) | 1.5 |
San Jacinto County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0403-01-049 | SH 156 | Tentative | Aug 2018 | $53,076 | 10 | RE-ESTABLISH THE SLOPE AND RESET GUARDRAIL. CONCRETE RIRAP W | 0.0 |
0756-04-013 | FM 2693 | Actual | Aug 2018 | $25,419 | 10 | REMOVE AND RESET SEPARATED BOX CULVERT. REPOUR NEW WINGWALL | 0.0 |
0403-02-019 | FM 224 | Actual | Jul 2018 | $520,554 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS | 0.0 |
0177-02-102 | US 59 | Tentative | Aug 2018 | $624,386 | 10 | REPAIR PAVING EROSION, REPLACE DAMAGED MBGF AND REBUILD BACK | 0.0 |
2668-01-010 | FM 2666 | Actual | Apr 2018 | $8,408 | 10 | EMERGENCY ROADWAY REPAIRS | 0.0 |
Shelby County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0059-03-020 | SH 7 | Actual | Feb 2018 | $2,054,209 | 1 | OVERLAY WITH PFC | 0.0 |
0063-06-098 | US 96 | Actual | Mar 2018 | $10,452,733 | 11 | PLANE, LEVEL-UP AND PFC | 0.0 |
0064-01-067 | SH 87 | Actual | Oct 2017 | $1,168,099 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS, SAFETY TREAT FIXED | 4.5 |
Trinity County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
2387-01-017 | FM 2262 | Actual | Oct 2017 | $4,509,850 | 1 | RECONSTRUCT AND WIDEN PAVEMENT TO 24 FT | 3.0 |
|