Detail Letting Schedule for Nacogdoches County (FY 2018)
Nacogdoches County (FY 2018) |
CCSJ: 0118-08-074 |
|||
District: | LUFKIN | Let Date: | Dec 2017 |
Highway: | SH 21 | Let Status: | Actual |
Project ID: | STP 2018(366)HES | CSJ: | 0118-08-074 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS, SAFETY TREAT FIXED | Handling Code: | |
Limits From: | SH 7 | Fund Cat: | 8 |
Limits To: | SAN AUGUSTINE COUNTY LINE | ESTIMATE: | $1,633,555 |
Length: | 21.8 | Actual | $1,306,803 |
District: | LUFKIN | Let Date: | Dec 2017 |
Highway: | SH 21 | Let Status: | Actual |
Project ID: | STP 2018(366)HES | CSJ: | 0119-02-019 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS, SAFETY TREAT FIXED | Handling Code: | |
Limits From: | SAN AUGUSTINE COUNTY LINE | Fund Cat: | 8 |
Limits To: | FM 3448 | ESTIMATE: | $209,588 |
Length: | 2.1 | Actual | $271,748 |
Proposal Request Bid List List Showing Order Bid Tabulations Award Status Back... | Totals for 0118-08-074 | ||
---|---|---|---|
Length: | 23.9 | ||
Estimate: | $1,843,142 | ||
Actual: | $1,578,551 | ||
CCSJ: 0138-06-045 |
|||
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 1802(576)HES | CSJ: | 0138-06-045 |
Description: | UPGRADE INSTALL SAFETY LIGHTING WITHIN PROJECT | Handling Code: | |
Limits From: | RUSK COUNTY LINE | Fund Cat: | 8 |
Limits To: | BU 59-F | ESTIMATE: | $30,755 |
Length: | 11.4 | Actual | $23,544 |
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 1802(576)HES | CSJ: | 0176-05-189 |
Description: | UPGRADE INSTALL SAFETY LIGHTING WITHIN PROJECT | Handling Code: | |
Limits From: | 0.162 MILES NORTH OF FM 942 | Fund Cat: | 8 |
Limits To: | 0.218 MILES SOUTH OF US 190 | ESTIMATE: | $104,740 |
Length: | 21.6 | Actual | $95,297 |
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | BU 59-J | Let Status: | Actual |
Project ID: | STP 1802(576)HES | CSJ: | 0176-06-014 |
Description: | UPGRADE INSTALL SAFETY LIGHTING WITHIN PROJECT | Handling Code: | |
Limits From: | 0.488 MILE NORTH OF US 59 | Fund Cat: | 8 |
Limits To: | FM 1988 | ESTIMATE: | $114,030 |
Length: | 4.6 | Actual | $104,416 |
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 1802(576)HES | CSJ: | 0177-01-109 |
Description: | UPGRADE INSTALL SAFETY LIGHTING WITHIN PROJECT | Handling Code: | |
Limits From: | 0.218 MILES SOUTH OF US 190 | Fund Cat: | 8 |
Limits To: | SAN JACINTO COUNTY LINE | ESTIMATE: | $95,080 |
Length: | 9.7 | Actual | $86,857 |
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 1802(576)HES | CSJ: | 2560-01-084 |
Description: | UPGRADE INSTALL SAFETY LIGHTING WITHIN PROJECT | Handling Code: | |
Limits From: | 0.325 MILES SOUTH OF US 259 | Fund Cat: | 8 |
Limits To: | 0.326 MILES SOUTH OF BU 59 | ESTIMATE: | $294,150 |
Length: | 7.8 | Actual | $264,700 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Back... | Totals for 0138-06-045 | ||
Length: | 55.1 | ||
Estimate: | $638,755 | ||
Actual: | $574,813 | ||
CCSJ: 0336-06-028 |
|||
District: | LUFKIN | Let Date: | Oct 2017 |
Highway: | SH 103 | Let Status: | Actual |
Project ID: | STP 2018(156)HES | CSJ: | 0336-06-028 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS | Handling Code: | |
Limits From: | ANGELINA COUNTY LINE | Fund Cat: | 8 |
Limits To: | SAN AUGUSTINE COUNTY LINE | ESTIMATE: | $424,316 |
Length: | 8.6 | Actual | $427,031 |
District: | LUFKIN | Let Date: | Oct 2017 |
Highway: | SH 7 | Let Status: | Actual |
Project ID: | STP 2018(157)HES | CSJ: | 0553-03-031 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS | Handling Code: | |
Limits From: | ANGELINA COUNTY LINE | Fund Cat: | 8 |
Limits To: | BU 59-F | ESTIMATE: | $171,891 |
Length: | 12.1 | Actual | $170,861 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0336-06-028 | ||
Length: | 20.7 | ||
Estimate: | $596,207 | ||
Actual: | $597,892 | ||
CCSJ: 0706-04-019 |
|||
District: | LUFKIN | Let Date: | Jan 2018 |
Highway: | FM 95 | Let Status: | Actual |
Project ID: | BR 2018(426) | CSJ: | 0706-04-019 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: | |
Limits From: | AT TERRAPIN CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $1,436,386 |
Length: | 0.2 | Actual | $1,145,849 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0706-04-019 | ||
Length: | 0.2 | ||
Estimate: | $1,436,386 | ||
Actual: | $1,145,849 | ||
CCSJ: 0893-01-034 |
|||
District: | LUFKIN | Let Date: | May 2018 |
Highway: | FM 226 | Let Status: | Actual |
Project ID: | STP 2018(812)HES | CSJ: | 0893-01-034 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS,SAFETY TREAT FIXED | Handling Code: | |
Limits From: | SH 21 | Fund Cat: | 8 |
Limits To: | SH 103 | ESTIMATE: | $889,836 |
Length: | 17.0 | Actual | $895,372 |
District: | LUFKIN | Let Date: | May 2018 |
Highway: | FM 226 | Let Status: | Actual |
Project ID: | STP 2018(812)HES | CSJ: | 0893-01-035 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS,SAFETY TREAT FIXED | Handling Code: | |
Limits From: | SH 103 | Fund Cat: | 8 |
Limits To: | 5.668 MI S OF SH 103 | ESTIMATE: | $193,108 |
Length: | 6.0 | Actual | $188,631 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0893-01-034 | ||
Length: | 23 | ||
Estimate: | $1,082,944 | ||
Actual: | $1,084,003 | ||
CCSJ: 1407-02-023 |
|||
District: | LUFKIN | Let Date: | May 2018 |
Highway: | FM 1638 | Let Status: | Actual |
Project ID: | STP 2018(814)HES | CSJ: | 1407-02-023 |
Description: | SAFETY TREAT FIXED OBJECTS; PROVIDE ADDITIONAL PAVED SURFACE | Handling Code: | |
Limits From: | FM 698 | Fund Cat: | 8 |
Limits To: | US 59/SL 224 | ESTIMATE: | $2,764,682 |
Length: | 4.2 | Actual | $2,498,804 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 1407-02-023 | ||
Length: | 4.2 | ||
Estimate: | $2,764,682 | ||
Actual: | $2,498,804 | ||
CCSJ: 1407-03-018 |
|||
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | FM 1275 | Let Status: | Actual |
Project ID: | STP 1802(577)HES | CSJ: | 1407-03-018 |
Description: | IMPROVE TRAFFIC AND PEDESTRIAN SIGNALS AT LOCATION | Handling Code: | |
Limits From: | AT EAST COLLEGE ST | Fund Cat: | 8 |
Limits To: | AT EAST COLLEGE ST | ESTIMATE: | $199,913 |
Length: | 0.2 | Actual | $223,327 |
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 1802(578)HES | CSJ: | 0176-04-083 |
Description: | INSTALL ADVANCE INTERSECTION WARNING SIGNALS-EXISTING | Handling Code: | |
Limits From: | AT US 287 IN CORRIGAN | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $37,780 |
Length: | 0.2 | Actual | $36,827 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Back... | Totals for 1407-03-018 | ||
Length: | 0.4 | ||
Estimate: | $237,693 | ||
Actual: | $260,154 | ||
CCSJ: 2590-01-020 |
|||
District: | LUFKIN | Let Date: | Jul 2018 |
Highway: | FM 2609 | Let Status: | Actual |
Project ID: | STP 2013(518) | CSJ: | 2590-01-020 |
Description: | WIDEN FROM 2 TO 4 LANES | Handling Code: | |
Limits From: | RAGUET STREET | Fund Cat: | 11 |
Limits To: | NORTH STREET (BU 59-F) | ESTIMATE: | $2,711,569 |
Length: | 0.3 | Actual | $2,896,894 |
Proposal Request Bid List List Showing Order Addenda Bid Tabulations Award Status Back... | Totals for 2590-01-020 | ||
Length: | 0.3 | ||
Estimate: | $2,711,569 | ||
Actual: | $2,896,894 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |