Detail Letting Schedule for Real County (FY 2019)

Last Update: Monday, November 13, 2017
Real County (FY 2019)

CCSJ: 0235-03-034

District:SAN ANGELOLet Date:Feb 2019
Highway:SH 55Let Status:Tentative
Project ID:STP ( )HESCSJ:0235-03-034
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:7.0 M N OF UVALDE CO LINEFund Cat:8
Limits To:UVALDE CO LINEESTIMATE:$183,824
Length:7.0Actual$0
 
District:SAN ANGELOLet Date:Feb 2019
Highway:US 277Let Status:Tentative
Project ID:STP ( )HESCSJ:0159-02-076
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:SL 110Fund Cat:8
Limits To:SCHLEICHER COUNTY LINEESTIMATE:$181,548
Length:6.9Actual$0
 
District:SAN ANGELOLet Date:Feb 2019
Highway:US 277Let Status:Tentative
Project ID:STP ( )HESCSJ:0159-03-027
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:TOM GREEN COUNTY LINEFund Cat:8
Limits To:12.0 MI S OF TOM GREEN CO LINEESTIMATE:$314,491
Length:12.0Actual$0
 
District:SAN ANGELOLet Date:Feb 2019
Highway:US 277Let Status:Tentative
Project ID:STP ( )HESCSJ:0159-04-035
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:12.0 MI S OF TOM GREEN CO LINEFund Cat:8
Limits To:21.1 MI S OF TOM GREEN CO LINEESTIMATE:$237,739
Length:9.1Actual$0
 
District:SAN ANGELOLet Date:Feb 2019
Highway:US 277Let Status:Tentative
Project ID:STP ( )HESCSJ:0160-01-037
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:SL 467Fund Cat:8
Limits To:12.3 MI N OF EDWARDS CO LINEESTIMATE:$235,515
Length:9.0Actual$0
 
District:SAN ANGELOLet Date:Feb 2019
Highway:SH 41Let Status:Tentative
Project ID:STP ( )HESCSJ:0201-06-030
Description:CENTERLINE AND SHOULDER TEXTURINGHandling
Code:
 
Limits From:EDWARDS COUNTY LINEFund Cat:8
Limits To:KERR COUNTY LINEESTIMATE:$387,411
Length:18.1Actual$0
 
District:SAN ANGELOLet Date:Feb 2019
Highway:US 277Let Status:Tentative
Project ID:STP ( )HESCSJ:0264-05-028
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:SH 158Fund Cat:8
Limits To:TOM GREEN COUNTY LINEESTIMATE:$361,343
Length:13.8Actual$0
 
District:SAN ANGELOLet Date:Feb 2019
Highway:US 277Let Status:Tentative
Project ID:STP ( )HESCSJ:0264-06-041
Description:PROFILE EDGELINE AND CENTERLINE MARKINGHandling
Code:
 
Limits From:COKE COUNTY LINEFund Cat:8
Limits To:US 67ESTIMATE:$358,806
Length:13.7Actual$0
 
District:SAN ANGELOLet Date:Feb 2019
Highway:SH 137Let Status:Tentative
Project ID:STP ( )HESCSJ:0494-09-016
Description:PROFILE EDGELINE AND CENTERLINE MARKINGSHandling
Code:
 
Limits From:GLASSCOCK CO LINEFund Cat:8
Limits To:11.5 MI S OF GLASSCOCK CO LINEESTIMATE:$301,438
Length:11.5Actual$0
 
District:SAN ANGELOLet Date:Feb 2019
Highway:RM 853Let Status:Tentative
Project ID:STP ( )HESCSJ:0555-04-015
Description:CENTERLINE AND SHOULDER TEXTURINGHandling
Code:
 
Limits From:US 67Fund Cat:8
Limits To:TOM GREEN COUNTY LINEESTIMATE:$324,721
Length:15.2Actual$0
 
Back...
Totals for 0235-03-034
Length:116.3
Estimate:$2,886,836
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract