Detail Letting Schedule for Real County (FY 2019)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Real County (FY 2019) |
CCSJ: 0235-03-034 |
|||
District: | SAN ANGELO | Let Date: | Feb 2019 |
Highway: | SH 55 | Let Status: | Actual |
Project ID: | STP 2019(508)HES | CSJ: | 0235-03-034 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | 7.0 M N OF UVALDE CO LINE | Fund Cat: | 8 |
Limits To: | UVALDE CO LINE | ESTIMATE: | $83,312 |
Length: | 7.0 | Actual | $81,495 |
District: | SAN ANGELO | Let Date: | Feb 2019 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | STP 2019(508)HES | CSJ: | 0159-02-076 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SL 110 | Fund Cat: | 8 |
Limits To: | SCHLEICHER COUNTY LINE | ESTIMATE: | $83,935 |
Length: | 6.9 | Actual | $82,030 |
District: | SAN ANGELO | Let Date: | Feb 2019 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | STP 2019(508)HES | CSJ: | 0159-03-027 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | TOM GREEN COUNTY LINE | Fund Cat: | 8 |
Limits To: | 12.0 MI S OF TOM GREEN CO LINE | ESTIMATE: | $138,929 |
Length: | 12.0 | Actual | $138,290 |
District: | SAN ANGELO | Let Date: | Feb 2019 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | STP 2019(508)HES | CSJ: | 0159-04-035 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | 12.0 MI S OF TOM GREEN CO LINE | Fund Cat: | 8 |
Limits To: | 21.1 MI S OF TOM GREEN CO LINE | ESTIMATE: | $108,618 |
Length: | 9.1 | Actual | $107,981 |
District: | SAN ANGELO | Let Date: | Feb 2019 |
Highway: | SH 41 | Let Status: | Actual |
Project ID: | STP 2019(508)HES | CSJ: | 0201-06-030 |
Description: | CENTERLINE AND SHOULDER TEXTURING | Handling Code: | |
Limits From: | EDWARDS COUNTY LINE | Fund Cat: | 8 |
Limits To: | KERR COUNTY LINE | ESTIMATE: | $195,369 |
Length: | 18.1 | Actual | $194,320 |
District: | SAN ANGELO | Let Date: | Feb 2019 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | STP 2019(508)HES | CSJ: | 0264-05-028 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SH 158 | Fund Cat: | 8 |
Limits To: | TOM GREEN COUNTY LINE | ESTIMATE: | $150,989 |
Length: | 13.8 | Actual | $151,050 |
District: | SAN ANGELO | Let Date: | Feb 2019 |
Highway: | RM 853 | Let Status: | Actual |
Project ID: | STP 2019(508)HES | CSJ: | 0555-04-015 |
Description: | CENTERLINE AND SHOULDER TEXTURING | Handling Code: | |
Limits From: | US 67 | Fund Cat: | 8 |
Limits To: | TOM GREEN COUNTY LINE | ESTIMATE: | $174,392 |
Length: | 15.2 | Actual | $172,854 |
Back... | Totals for 0235-03-034 | ||
---|---|---|---|
Length: | 82.1 | ||
Estimate: | $935,544 | ||
Actual: | $928,020 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |