Letting Schedule for Amarillo District (FY 2020)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Amarillo District (FY 2020) |
Armstrong | Carson | Dallam | Gray | Hemphill | Lipscomb | Oldham | Potter | | |||||||
Armstrong County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0042-04-043 | US 287 | Tentative | Jan 2020 | $6,936,000 | 1 | 2" ACP OVERLAY, PAVEMENT REPAIR AND ADD DECEL LANES AT | 0.0 |
Carson County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0275-02-070 | IH 40 | Tentative | Apr 2020 | $1,771,340 | 8 | INSTALL MEDIAN BARRIER | 0.0 |
Dallam County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0066-01-021 | US 287 | Tentative | Nov 2019 | $10,327,541 | 1 | THICK OVERLAY AND PAVEMENT REPAIR | 0.0 |
0238-03-064 | US 54 | Tentative | Sep 2019 | $13,380,500 | 1 | THICK OVERLAY AND PAVEMENT REPAIR | 0.0 |
Gray County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0275-11-083 | IH 40 | Tentative | Dec 2019 | $5,996,000 | 1 | CRCP REPAIR, OVERLAY AND BRIDGE RAIL REPLACEMENT (EBL ONLY) | 0.0 |
Hemphill County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0030-05-069 | US 83 | Tentative | Jan 2020 | $9,158,400 | 6 | REPLACE EXISTING BRIDGE | 0.0 |
Lipscomb County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
1819-01-015 | FM 1920 | Tentative | Apr 2020 | $9,457,800 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
Oldham County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0090-02-053 | IH 40 | Tentative | Apr 2020 | $1,622,305 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS | 0.0 |
Potter County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0275-01-205 | IH 40 | Tentative | May 2020 | $13,340,000 | 6 | 2018 BMIP REPAIR WB BRIDGE | 0.0 |
0904-00-173 | VA | Tentative | Sep 2019 | $750,000 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0041-08-004 | SL 434 | Tentative | Nov 2019 | $11,608,112 | 1 | SEALCOAT | 0.0 |
0275-01-199 | IH 40 | Tentative | Nov 2019 | $48,150,000 | 1 | B-2 PHASE II: RECONSTRUCT IH 40 2ND LEVEL MAINLANE BRIDGE AT | 0.0 |
2635-01-038 | SL 335 | Tentative | Oct 2019 | $8,300,000 | 1 | OVERLAY | 0.0 |
0090-05-100 | SL 279 | Tentative | Oct 2019 | $620,198 | 10 | CONSTRUCT CURB RAMPS | 0.0 |
|