Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
El Paso District (FY 2020) |
Culberson | El Paso | Hudspeth | Presidio | | |||||||
Culberson County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0020-02-019 | US 90 | Actual | Jul 2020 | $767,820 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
1314-02-014 | RM 652 | Actual | Jan 2020 | $18,624,732 | 11 | SURFACING/ROADWAY RESTORATION | 8.0 |
0924-08-006 | CR | Actual | Aug 2020 | $250,000 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
El Paso County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0924-06-601 | VA | Actual | May 2020 | $2,966,650 | 1 | BRIDGE MAINTENANCE | 0.0 |
0001-02-055 | SH 20 | Actual | Nov 2019 | $13,248,155 | 1 | SURFACING/ROADWAY RESTORATION | 8.0 |
2552-02-034 | SL 375 | Actual | Jun 2020 | $1,075,793 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
2121-02-171 | IH 10 | Actual | Jul 2020 | $653,428 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
2121-05-051 | IH 10 | Actual | Jul 2020 | $5,397,225 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0924-06-539 | CS | Actual | Jun 2020 | $1,297,000 | 3 | INFRASTRUCTURE IMPROVEMENTS | 0.0 |
0924-06-560 | CS | Actual | Jun 2020 | $2,143,913 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
2121-03-060 | IH 10 | Actual | Jun 2020 | $10,118,234 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0924-06-421 | CS | Approved | Aug 2020 | $1,752,015 | 3 | BRIDGE REPLACEMENT | 7.0 |
0924-06-422 | CS | Approved | Aug 2020 | $1,898,899 | 3 | BRIDGE REPLACEMENT | 0.0 |
0924-06-425 | CS | Approved | Aug 2020 | $984,989 | 3 | BRIDGE REPLACEMENT | 0.0 |
2552-03-049 | SL 375 | Actual | Jul 2020 | $72,562,802 | 11 | CONSTRUCT NEW ROAD | 10.0 |
0001-02-069 | SH 20 | Actual | Aug 2020 | $1,692,784 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0924-06-419 | CS | Approved | Aug 2020 | $443,208 | 3 | BRIDGE REPLACEMENT | 0.0 |
0924-06-603 | VA | Actual | Apr 2020 | $1,929,431 | 1 | PREVENTIVE MAINTENANCE | 6.0 |
0924-06-551 | VA | Actual | Jan 2020 | $1,000,000 | 5 | TRANSPORTATION SERVICE OPERATIONS | 0.0 |
0924-06-553 | VA | Actual | Jan 2020 | $1,000,000 | 5 | TRANSPORTATION SERVICE OPERATIONS | 0.0 |
0167-01-128 | US 54 | Actual | Feb 2020 | $9,234,847 | 1 | PREVENTIVE MAINTENANCE | 8.0 |
0167-02-063 | BU 54-A | Actual | Dec 2019 | $3,063,331 | 1 | SURFACING/ROADWAY RESTORATION | 8.0 |
0665-01-009 | FM 3255 | Actual | Jan 2020 | $4,902,103 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0924-06-540 | VA | Actual | Jan 2020 | $1,000,000 | 5 | TRANSPORTATION SERVICE OPERATIONS | 0.0 |
0924-00-142 | VA | Actual | Feb 2020 | $3,003,681 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0167-01-120 | US 54 | Actual | Apr 2020 | $1,029,343 | 1 | PREVENTIVE MAINTENANCE | 5.5 |
0167-01-127 | US 54 | Actual | Apr 2020 | $699,747 | 1 | INSTALL INTELLIGENT VEHICLE HIGHWAY SYSTEM | 0.0 |
0924-06-534 | CS | Actual | Feb 2020 | $23,000,000 | 3 | CONSTRUCT NEW ROAD | 0.0 |
Hudspeth County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0002-05-050 | IH 10 | Actual | May 2020 | $2,218,954 | 1 | REPLACE GUARDRAIL | 0.0 |
0002-07-054 | IH 10 | Actual | Jul 2020 | $2,857,251 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0002-06-054 | IH 10 | Actual | Dec 2019 | $4,128,429 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0957-01-019 | FM 192 | Actual | Aug 2020 | $582,867 | 6 | BRIDGE REPLACEMENT | 4.0 |
Presidio County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
7124-01-003 | RL SO | Actual | Jun 2020 | $9,065,208 | 3 | INFRASTRUCTURE IMPROVEMENTS | 0.0 |
0924-07-013 | VA | Actual | Nov 2019 | $4,323,207 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 10.0 |
0924-07-017 | CS | Actual | Apr 2020 | $490,999 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
|