Detail Letting Schedule for Sutton County (FY 2020)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Sutton County (FY 2020) |
CCSJ: 0141-03-063 |
|||
District: | SAN ANGELO | Let Date: | May 2020 |
Highway: | IH 10 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0141-03-063 |
Description: | SAFETY TREAT FIXED OBJECTS | Handling Code: | |
Limits From: | 1.554 MI W OF RM 1989 | Fund Cat: | 8 |
Limits To: | 0.05 MI E OF US 277 | ESTIMATE: | $1,734,108 |
Length: | 9.7 | Actual | $0 |
District: | SAN ANGELO | Let Date: | May 2020 |
Highway: | IH 10 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0141-05-028 |
Description: | SAFETY TREAT FIXED OBJECTS | Handling Code: | |
Limits From: | 3.618 MI E OF SL 467 | Fund Cat: | 8 |
Limits To: | 2.115 MI W OF RM 3130 | ESTIMATE: | $397,414 |
Length: | 10.5 | Actual | $0 |
District: | SAN ANGELO | Let Date: | May 2020 |
Highway: | IH 10 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0141-06-047 |
Description: | SAFETY TREAT FIXED OBJECTS | Handling Code: | |
Limits From: | 2.115 MI W OF RM 3130 | Fund Cat: | 8 |
Limits To: | 0.199 MI E OF PRIVATE ROAD 3389 | ESTIMATE: | $301,108 |
Length: | 9.3 | Actual | $0 |
District: | SAN ANGELO | Let Date: | May 2020 |
Highway: | US 67 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0158-02-090 |
Description: | SAFETY TREATED FIXED OBJECT | Handling Code: | |
Limits From: | 0.282 MI SW OF RUNNELS CO LINE | Fund Cat: | 8 |
Limits To: | CHADBOURNE ST | ESTIMATE: | $464,779 |
Length: | 15.6 | Actual | $0 |
Back... | Totals for 0141-03-063 | ||
---|---|---|---|
Length: | 45.1 | ||
Estimate: | $2,897,409 | ||
Actual: | |||
CCSJ: 0160-02-025 |
|||
District: | SAN ANGELO | Let Date: | Jun 2020 |
Highway: | US 277 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0160-02-025 |
Description: | ADD PASSING LANES | Handling Code: | |
Limits From: | 12.275 MI NORTH OF EDWARDS CO LINE | Fund Cat: | 1 |
Limits To: | EDWARDS COUNTY LINE | ESTIMATE: | $9,800,000 |
Length: | 12.3 | Actual | $0 |
District: | SAN ANGELO | Let Date: | Jun 2020 |
Highway: | US 277 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0160-02-026 |
Description: | PROFILE EDGELINE AND CENTERLINE MARKINGS | Handling Code: | |
Limits From: | 12.3 MI N OF EDWARDS CO LINE | Fund Cat: | 8 |
Limits To: | EDWARDS COUNTY LINE | ESTIMATE: | $321,110 |
Length: | 12.3 | Actual | $0 |
District: | SAN ANGELO | Let Date: | Jun 2020 |
Highway: | US 277 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0160-03-024 |
Description: | ADD PASSING LANES | Handling Code: | |
Limits From: | SUTTON COUNTY LINE | Fund Cat: | 1 |
Limits To: | VAL VERDE COUNTY LINE | ESTIMATE: | $10,856,000 |
Length: | 13.6 | Actual | $0 |
District: | SAN ANGELO | Let Date: | Jun 2020 |
Highway: | US 277 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0160-03-025 |
Description: | SAFETY TREATED FIXED OBJECTS | Handling Code: | |
Limits From: | SUTTON CL | Fund Cat: | 8 |
Limits To: | VAL VERDE CL | ESTIMATE: | $916,134 |
Length: | 13.1 | Actual | $0 |
Bid Tabulations Back... | Totals for 0160-02-025 | ||
Length: | 51.3 | ||
Estimate: | $21,893,244 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |