Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
|
December, 2020 (FY 2021) | (see Links) |
SEP 2020 | OCT 2020 | NOV 2020 | DEC 2020 | JAN 2021 | FEB 2021 | MAR 2021 | APR 2021 | MAY 2021 | JUN 2021 | JUL 2021 | AUG 2021 | | |||||||
CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0916-38-013 | Aransas/ Corpus Christi | CS | Actual | $838,190 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 5.0 |
0915-12-509 | Bexar/ San Antonio | CR | Actual | $8,097,480 | 3 | WIDEN ROAD - ADD LANES | 8.0 |
0915-00-199 | Bexar/ San Antonio | VA | Actual | $291,350 | 1 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0915-12-610 | Bexar/ San Antonio | CS | Actual | $1,000,000 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0253-01-061 | Blanco/ Austin | US 281 | Actual | $3,368,547 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
2523-02-068 | Brazoria/ Houston | FM 2004 | Actual | $32,419,999 | 1 | HIGHWAY IMPROVEMENT | 7.0 |
0179-10-109 | Calhoun/ Yoakum | SH 35 | Actual | $1,460,071 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0921-06-345 | Cameron/ Pharr | CR | Actual | $5,262,841 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0282-03-030 | Clay/ Wichita Falls | SH 79 | Actual | $2,272,114 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0035-04-038 | Concho/ San Angelo | US 83 | Actual | $11,546,569 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0918-47-200 | Dallas/ Dallas | CS | Actual | $433,821 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0918-47-072 | Dallas/ Dallas | CS | Actual | $2,260,000 | 3 | INSTALL RAISED MEDIAN | 0.0 |
0196-06-033 | Dallas/ Dallas | SL 354 | Actual | $1,527,802 | 3 | TRAFFIC SIGNAL IMPROVEMENTS | 6.0 |
0918-47-199 | Dallas/ Dallas | CS | Actual | $254,268 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0270-02-041 | Dewitt/ Yoakum | SH 72 | Actual | $46,818,310 | 11 | WIDEN ROAD - ADD LANES | 8.0 |
0310-01-043 | Donley/ Childress | SH 70 | Actual | $1,046,839 | 6 | BRIDGE MAINTENANCE | 0.0 |
2121-02-174 | El Paso/ El Paso | IH 10 | Actual | $2,526,198 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0924-06-573 | El Paso/ El Paso | VA | Actual | $1,538,029 | 3 | TRANSPORTATION SERVICE OPERATIONS | 0.0 |
0924-06-572 | El Paso/ El Paso | VA | Actual | $2,288,542 | 3 | TRANSPORTATION SERVICE OPERATIONS | 0.0 |
0924-06-422 | El Paso/ El Paso | CS | Actual | $1,898,899 | 3 | BRIDGE REPLACEMENT | 0.0 |
0167-01-117 | El Paso/ El Paso | US 54 | Actual | $1,849,005 | 8 | HAZARD ELIMINATION & SAFETY | 6.0 |
0596-02-040 | Ellis/ Dallas | FM 66 | Actual | $2,446,425 | 1 | BRIDGE REPLACEMENT | 7.5 |
0027-12-152 | Fort Bend/ Houston | IH 69 | Actual | $4,613,352 | 1 | ADVANCED TRAFFIC MANAGEMENT SYSTEM | 0.0 |
0494-08-015 | Glasscock/ San Angelo | SH 137 | Actual | $30,651,534 | 1 | SURFACING/ROADWAY RESTORATION | 4.0 |
0901-19-196 | Grayson/ Paris | VA | Actual | $1,503,950 | 11 | PREVENTIVE MAINTENANCE | 0.0 |
0915-46-050 | Guadalupe/ San Antonio | CS | Actual | $1,158,266 | 3 | HIKE AND/OR BIKE | 0.0 |
0912-00-592 | Harris/ Houston | VA | Actual | $2,476,494 | 1 | SIGNAL IMPROVEMENTS,LEDS & GPS CLOCKS | 0.0 |
0912-00-623 | Harris/ Houston | VA | Actual | $2,344,000 | 5 | TRANSPORTATION NON-ROADWAY | 0.0 |
0500-03-625 | Harris/ Houston | IH 45 | Actual | $3,603,275 | 1 | INSTALL/UPGRADE ROADWAY LIGHTING | 0.0 |
0912-00-558 | Harris/ Houston | VA | Actual | $10,391,000 | 3 | REGIONAL TRAVEL MANAGEMENT PROGRAM | 0.0 |
0178-01-037 | Harris/ Houston | SH 35 | Actual | $321,468 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0110-06-144 | Harris/ Houston | IH 45 | Actual | $1,252,363 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0010-02-096 | Hopkins/ Paris | IH 30 | Actual | $9,693,181 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0009-13-176 | Hunt/ Paris | IH 30 | Actual | $14,345,092 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0104-02-030 | Jeff Davis/ El Paso | SH 17 | Actual | $6,862,905 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0017-08-096 | La Salle/ Laredo | IH 35 | Actual | $12,481,136 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0639-02-033 | Madison/ Bryan | FM 39 | Actual | $164,905 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0138-11-032 | Marion/ Atlanta | FM 248 | Actual | $1,288,999 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0070-06-041 | Mcculloch/ Brownwood | US 87 | Actual | $8,250,439 | 1 | RECONSTRUCT EXISTING ROADWAY | 7.0 |
0909-22-182 | Mclennan/ Waco | CS | Actual | $2,700,000 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0909-00-055 | Mclennan/ Waco | VA | Actual | $125,000 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0005-07-058 | Mitchell/ Abilene | IH 20 | Actual | $15,223,700 | 1 | PREVENTIVE MAINTENANCE | 8.5 |
0911-08-047 | Nacogdoches/ Lufkin | CR | Actual | $300,000 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0006-03-137 | Nolan/ Abilene | IH 20 | Actual | $14,245,678 | 1 | SEAL COAT | 0.0 |
0102-03-087 | Nueces/ Corpus Christi | US 77 | Actual | $7,927,833 | 1 | CONSTRUCT RAMPS | 0.0 |
0902-39-035 | Palo Pinto/ Ft Worth | VA | Actual | $3,578,993 | 10 | STATE PARK IMPROVEMENTS | 0.0 |
0008-03-119 | Parker/ Ft Worth | US 180 | Actual | $4,220,000 | 3 | INTERSECTION IMPROVEMENT | 0.0 |
0171-03-074 | Parker/ Ft Worth | SH 199 | Actual | $8,447,004 | 1 | RESURFACE ROADWAY | 0.0 |
2635-03-024 | Randall/ Amarillo | SL 335 | Actual | $28,174,171 | 1 | CONSTRUCT NEW ROAD | 0.0 |
0910-42-042 | Rusk/ Tyler | VA | Actual | $167,625 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0916-28-069 | San Patricio/ Corpus Christi | VA | Actual | $359,878 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0910-16-144 | Smith/ Tyler | CS | Actual | $1,022,312 | 3 | HIKE AND/OR BIKE | 0.0 |
0902-90-081 | Tarrant/ Ft Worth | VA | Actual | $2,096,401 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 7.0 |
0908-00-103 | Taylor/ Abilene | VA | Actual | $1,003,979 | 11 | PREVENTIVE MAINTENANCE | 0.0 |
0908-00-102 | Taylor/ Abilene | VA | Actual | $1,025,115 | 11 | PREVENTIVE MAINTENANCE | 0.0 |
0908-00-098 | Taylor/ Abilene | VA | Actual | $2,393,916 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0908-00-097 | Taylor/ Abilene | VA | Actual | $1,694,738 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0908-00-104 | Taylor/ Abilene | VA | Actual | $1,019,531 | 11 | PREVENTIVE MAINTENANCE | 0.0 |
0070-02-096 | Tom Green/ San Angelo | US 87 | Actual | $6,776,639 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0914-00-434 | Travis/ Austin | VA | Actual | $805,539 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0914-00-433 | Travis/ Austin | VA | Actual | $824,967 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0095-06-074 | Van Zandt/ Tyler | US 80 | Actual | $13,215,240 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0802-02-075 | Wichita/ Wichita Falls | FM 369 | Actual | $1,303,273 | 1 | SURFACING/ROADWAY RESTORATION | 5.0 |
|