Detail Letting Schedule for Midland County (FY 2021)

Last Update: Tuesday, August 13, 2024

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Midland County (FY 2021)

CCSJ: 0005-02-113

District:ODESSALet Date:Jan 2020
Highway:BI 20-ELet Status:Tentative
Project ID:STP ( )FRS4CSJ:0005-02-113
Description:INSTALL ADVANCE PREEMPTION ON RR AND RELOCATING A TRACKHandling
Code:
XX
Limits From:AT CR 1250Fund Cat:8
Limits To:.ESTIMATE:$1,800,000
Length:0.2Actual$0
 
Back...
Totals for 0005-02-113
Length:0.2
Estimate:$1,800,000
Actual:

CCSJ: 0005-02-118

District:ODESSALet Date:Feb 2020
Highway:BI 20-ELet Status:Tentative
Project ID:NH ( )CSJ:0005-02-118
Description:MILL AND FILLHandling
Code:
 
Limits From:SL 250Fund Cat:1
Limits To:SL 268ESTIMATE:$3,081,903
Length:2.3Actual$0
 
District:ODESSALet Date:Feb 2020
Highway:BI 20-ELet Status:Tentative
Project ID:NH ( )CSJ:0005-03-076
Description:MILL AND FILLHandling
Code:
 
Limits From:WALL STFund Cat:1
Limits To:FAIRGROUNDSESTIMATE:$1,931,289
Length:1.4Actual$0
 
District:ODESSALet Date:Feb 2020
Highway:BI 20-ELet Status:Tentative
Project ID:NH ( )CSJ:0005-09-022
Description:MILL AND FILLHandling
Code:
 
Limits From:SL 268Fund Cat:1
Limits To:WALL STESTIMATE:$3,635,448
Length:2.7Actual$0
 
Back...
Totals for 0005-02-118
Length:6.4
Estimate:$8,648,640
Actual:

CCSJ: 0005-03-070

District:ODESSALet Date:Jan 2020
Highway:BI 20-ELet Status:Tentative
Project ID:STP ( )FRS4CSJ:0005-03-070
Description:INSTALL TRAFFIC SIGNAL FOR DOT# 796 348PHandling
Code:
XX
Limits From:AT 0.5 MILES EAST OF E. SL 250Fund Cat:8
Limits To:.ESTIMATE:$800,000
Length:0.5Actual$0
 
Back...
Totals for 0005-03-070
Length:0.5
Estimate:$800,000
Actual:

CCSJ: 0005-03-071

District:ODESSALet Date:Jan 2020
Highway:BI 20-ELet Status:Tentative
Project ID:STP ( )FRS4CSJ:0005-03-071
Description:INSTALL ADVANCE PREEMPTION ON RR FOR DOT# 796 348PHandling
Code:
XX
Limits From:AT 0.5 MILES EAST OF E. SL 250Fund Cat:8
Limits To:.ESTIMATE:$500,000
Length:0.1Actual$0
 
Back...
Totals for 0005-03-071
Length:0.1
Estimate:$500,000
Actual:

CCSJ: 0005-03-072

District:ODESSALet Date:Jan 2020
Highway:BI 20-ELet Status:Tentative
Project ID:STP ( )FRS4CSJ:0005-03-072
Description:INSTALL TRAFFIC SIGNAL FOR DOT# 796 345UHandling
Code:
XX
Limits From:AT CR 1140Fund Cat:8
Limits To:.ESTIMATE:$800,000
Length:0.5Actual$0
 
Back...
Totals for 0005-03-072
Length:0.5
Estimate:$800,000
Actual:

CCSJ: 0005-03-073

District:ODESSALet Date:Jan 2020
Highway:BI 20-ELet Status:Tentative
Project ID:STP ( )FRS4CSJ:0005-03-073
Description:INSTALL ADVANCE PREEMPTION ON RR FOR DOT# 796 345UHandling
Code:
XX
Limits From:AT CR 1140Fund Cat:8
Limits To:.ESTIMATE:$500,000
Length:0.2Actual$0
 
Back...
Totals for 0005-03-073
Length:0.2
Estimate:$500,000
Actual:

CCSJ: 0005-14-067

District:ODESSALet Date:Jan 2020
Highway:IH 20Let Status:Tentative
Project ID:NH ( )CSJ:0005-14-067
Description:REPLACE EXISTING UNDERPASS WITH A 4-LANE WIDE OVERPASSHandling
Code:
 
Limits From:SL 250Fund Cat:2U
Limits To:0.5 MILES EAST OF MIDKIFF RDESTIMATE:$28,160,001
Length:10.1Actual$0
 
Bid Tabulations
Back...
Totals for 0005-14-067
Length:10.1
Estimate:$28,160,001
Actual:

CCSJ: 0005-14-084

District:ODESSALet Date:Feb 2020
Highway:IH 20Let Status:Tentative
Project ID:NH ( )CSJ:0005-14-084
Description:CONSTRUCT NEW INTERCHANGEHandling
Code:
 
Limits From:AT CR 1250Fund Cat:1
Limits To:.ESTIMATE:$29,550,001
Length:1.0Actual$0
 
Bid Tabulations
Back...
Totals for 0005-14-084
Length:1
Estimate:$29,550,001
Actual:

CCSJ: 0005-15-090

District:ODESSALet Date:May 2020
Highway:IH 20Let Status:Tentative
Project ID:STP ( )HESCSJ:0005-15-090
Description:INSTALL TRAFFIC SIGNAL AND SAFETY LIGHTING AT INTERSECTIONHandling
Code:
 
Limits From:@ SL 250Fund Cat:8
Limits To:.ESTIMATE:$513,261
Length:0.2Actual$0
 
Back...
Totals for 0005-15-090
Length:0.2
Estimate:$513,261
Actual:

CCSJ: 0380-09-092

District:ODESSALet Date:Dec 2019
Highway:SH 349Let Status:Tentative
Project ID:NH ( )CSJ:0380-09-092
Description:ROADWAY REHABILITATIONHandling
Code:
 
Limits From:CR 140Fund Cat:11
Limits To:7.1 MILES SOUTH OF CR 140ESTIMATE:$6,650,000
Length:7.1Actual$0
 
District:ODESSALet Date:Dec 2019
Highway:SH 349Let Status:Tentative
Project ID:STP ( )CSJ:0380-10-023
Description:ROADWAY REHABILITATIONHandling
Code:
 
Limits From:7.1 MILES SOUTH OF CR140Fund Cat:11
Limits To:UPTON COUNTY LINEESTIMATE:$11,700,000
Length:12.6Actual$0
 
Award Status
Back...
Totals for 0380-09-092
Length:19.7
Estimate:$18,350,000
Actual:

CCSJ: 1188-02-089

District:ODESSALet Date:Jan 2020
Highway:SL 250Let Status:Tentative
Project ID:STP ( )CSJ:1188-02-089
Description:CONSTRUCT NEW INTERCHANGEHandling
Code:
 
Limits From:AT CR 1140Fund Cat:2U
Limits To:.ESTIMATE:$29,915,000
Length:1.9Actual$0
 
Back...
Totals for 1188-02-089
Length:1.9
Estimate:$29,915,000
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract