Monthly State Let Construction Report For Atlanta District As Of Jul 13, 2021 Page 1 Of 2

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
HighwayUS 67
FromAT JENNINGS SLOUGH
To.
CSJ0010-10-026
Proj IDBR 2021(581)
Work TypeBRIDGE REPLACEMENT
 
0.2466039514.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days283
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-10-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213211
Totals6039514.500.000.000.0

CountyCASS ETC
HighwayUS 67 ETC
FromBOWIE C/L
ToMORRIS C/L
CSJ0010-10-029
Proj IDSTP 2B20(269)
Work TypeSEAL COAT
 
163.9817634180.355044622.4066.0
Work Order12-11-20
Work Began05-24-21
Work Completed
Time Computed05-03-21
Contract Working Days69
Addl Days Granted0
Working Days Charged20
Percent Time Used28
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-10-029
BARRICADES PLUS, LLC (0.00)
STRIPING TECHNOLOGY, L.P. (0.00)
BRYDL CONTRACTING, INC. (0.00)
Contract #10203029
Totals7634180.352272233.205044622.4066.0

CountyBOWIE ETC
HighwayUS 67 ETC
FromAT FM 991
To.
CSJ0010-12-073
Proj IDSTP 2B20(160)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.051526434.46516988.2898.2
Work Order10-21-20
Work Began03-04-21
Work Completed
Time Computed12-21-20
Contract Working Days110
Addl Days Granted0
Working Days Charged65
Percent Time Used59
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-12-073
DALLAS LITE AND BARRICADE, INC. (2.39)
Contract #08203052
Totals526434.4626421.23516988.2898.2

CountyBOWIE ETC
HighwayFM 991 ETC
FromUS 67W
ToUS 67E
CSJ0010-19-013
Proj IDSTP 2020(786)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
473.966659420.00411149.3862.3
Work Order05-12-20
Work Began10-12-20
Work Completed
Time Computed07-13-20
Contract Working Days91
Addl Days Granted0
Working Days Charged63
Percent Time Used69
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-19-013
ON THE ROAD CONSTRUCTION, LLC (14.18)
Contract #03203033
Totals659420.0046982.04411149.3862.3

CountyBOWIE
HighwaySH 8
FromAT SULPHUR RIVER & SULPHUR RIV REL
To.
CSJ0062-01-035
Proj IDBR 2019(689)
Work TypeBRIDGE REPLACEMENT
 
1.55135121366.7221859460.9062.2
CountyCASS
HighwaySH 8
FromAT SULPHUR RIVER & SULPHUR RIV REL
To.
CSJ0062-02-024
Proj IDBR 2019(690)
Work TypeBRIDGE REPLACEMENT
 
0.3602612244.52670995.6625.6
Work Order05-02-19
Work Began05-13-19
Work Completed
Time Computed05-13-19
Contract Working Days1,215
Addl Days Granted11
Working Days Charged336
Percent Time Used27
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0062-01-035
BOWMAN ENGINEERING & CONSULTING, INC. (4.17)
ISAACS CONSTRUCTION SERVICES LLC (0.09)
JB PINNACLE GROUP, LLC (2.55)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.60)
PANOLA SIGN & BARRICADE, INC. (0.16)
STRIPING TECHNOLOGY, L.P. (0.73)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.30)
MASSEY CONTRACTORS, LLC (0.13)
FARR FOUNDATION, INC. (1.00)
Contract #04193002
Totals37733611.24119653.1422530456.5659.7

CountyCASS ETC
HighwayUS 59
From1.46 MI. S. OF SH 155
ToMARION COUNTY LINE
CSJ0062-04-050
Proj IDNH 2021(099)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
35.7654434952.65929400.3520.9
Work Order12-15-20
Work Began01-26-21
Work Completed
Time Computed01-14-21
Contract Working Days276
Addl Days Granted0
Working Days Charged26
Percent Time Used9
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-04-050
FLORES CONCRETE (27.84)
PANOLA SIGN & BARRICADE, INC. (0.66)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.08)
Contract #11203011
Totals4434952.655970.00929400.3520.9

CountyMARION
HighwayUS 59
FromSH 49
To0.9 MI. N. OF SH 49
CSJ0062-05-062
Proj IDNH 2021(317)
Work TypeOVERLAY
 
2.3402827413.51239221.808.4
Work Order03-18-21
Work Began06-01-21
Work Completed
Time Computed04-19-21
Contract Working Days150
Addl Days Granted0
Working Days Charged31
Percent Time Used20
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-05-062
MORRIS COUNTY CONTRACTORS, L.L.C. (1.27)
NATION SERVICES CO., INC. (0.23)
PANOLA SIGN & BARRICADE, INC. (0.51)
PRIMATE CONSTRUCTION, LP (11.92)
R & G CONSTRUCTION, LLC (24.76)
STRIPING TECHNOLOGY, L.P. (4.29)
Contract #01213012
Totals2827413.51213585.96239221.808.4

CountyHARRISON
HighwayUS 59
From0.5 MI. N. OF SL 390
To0.5 MI. S. OF SL 390
CSJ0062-07-094
Proj IDSTP 2021(325)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.999468445.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days125
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-094
CARTHAGE DRILLING, INC. (3.04)
PANOLA SIGN & BARRICADE, INC. (2.15)
Contract #04213015
Totals468445.500.000.000.0

CountyHARRISON ETC
HighwayUS 59 ETC
From0.5 MI. N. OF FM 1793
To0.5 MI. S. OF FM 1793
CSJ0062-07-096
Proj IDSTP 2021(332)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.000539434.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days125
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213231
Totals539434.000.000.000.0

CountyHARRISON ETC
HighwayFM 1186 ETC
FromUS 59
ToPANOLA C/L
CSJ0063-01-094
Proj IDSTP 2020(439)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
28.7471847139.901592955.4586.2
Work Order04-21-20
Work Began05-21-20
Work Completed
Time Computed05-21-20
Contract Working Days305
Addl Days Granted0
Working Days Charged214
Percent Time Used70
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0063-01-094
ISAACS CONSTRUCTION SERVICES LLC (0.49)
PANOLA SIGN & BARRICADE, INC. (0.92)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.18)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.84)
CELESTINO CAMPOZANO (0.09)
Contract #03203019
Totals1847139.90110251.741592955.4586.2

CountyPANOLA
HighwayUS 59
FromBU 59D
ToUS 79
CSJ0063-03-062
Proj IDSTP 2020(978)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.214170539.600.000.0
CountyPANOLA
HighwayUS 59
FromBU 59-D NORTH OF CARTHAGE
ToUS 79 EAST OF CARTHAGE
CSJ0063-03-065
Proj IDNH 2020(979)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.2148694246.332933348.2233.7
Work Order08-26-20
Work Began09-25-20
Work Completed
Time Computed09-25-20
Contract Working Days503
Addl Days Granted7
Working Days Charged134
Percent Time Used26
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0063-03-062
STATEWIDE SAFETY SYSTEMS (0.37)
AMERICAN REMEDIATION OPTIONS, INC. (2.51)
ISAACS CONSTRUCTION SERVICES LLC (0.60)
STRIPING TECHNOLOGY, L.P. (4.85)
WEST TEXAS ROCK RESOURCES, LLC (0.04)
ANTIGO CONSTRUCTION, INC. (0.40)
Contract #07203210
Totals8864785.9380954.622933348.2233.0

CountyPANOLA
HighwaySH 149
FromUS 79
To0.8 MI S. OF SH 315
CSJ0063-11-042
Proj IDSTP 2016(625)
Work TypeGR, STR, BS, SURF
 
1.98020892969.2321101559.9699.9
Work Order08-05-16
Work Began09-08-16
Work Completed
Time Computed09-05-16
Contract Working Days540
Addl Days Granted5
Working Days Charged554
Percent Time Used101
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-042
PANOLA SIGN & BARRICADE, INC. (0.22)
WEST TEXAS RUMBLE STRIP (0.02)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (0.51)
SCOTT DERR PAINTING CO, LLC (0.00)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.56)
OSCAR ORDUNO, INC. (0.57)
STRIPING TECHNOLOGY, L.P. (3.67)
CARTHAGE DRILLING, INC. (0.05)
DIRECTIONAL DRILLING (0.03)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.74)
ISAACS CONSTRUCTION SERVICES, LLC. (0.22)
TJT CONSTRUCTION (0.52)
RAYFORD"S TRUCK & TRACTOR (0.28)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.16)
MCL CONTRACTING, LLC (0.03)
REYNOLDS & KAY, LTD. (0.01)
DFW REBAR, INC. (0.03)
SOUTHEAST GRINDING & GROOVING, LLC (0.03)
D&D PIPELINE CONSULTANTS, LLC (0.04)
Contract #04163202
Totals20892969.2319804.4721101559.9699.9

CountyMORRIS ETC
HighwayUS 259 ETC
From1.507 MI. N. OF SH 338
ToSH 49
CSJ0084-01-090
Proj IDSTP 2020(365)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
145.3552282831.612239730.1098.1
Work Order01-31-20
Work Began05-07-20
Work Completed
Time Computed03-31-20
Contract Working Days72
Addl Days Granted0
Working Days Charged71
Percent Time Used98
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0084-01-090
BRYDL CONTRACTING, INC. (2.15)
Contract #12193021
Totals2282831.610.002239730.1098.1

CountyBOWIE ETC
HighwayFM 2735 ETC
From8.3 MI. N. OF US 82
ToUS 82
CSJ0085-03-017
Proj IDSTP 2021(299)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
58.3451493307.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days285
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0085-03-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213026
Totals1493307.900.000.000.0

CountyCASS ETC
HighwayFM 248 ETC
FromSH 43
ToMARION C/L
CSJ0138-10-029
Proj IDSTP 2021(287)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
98.4602714170.795844.000.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days304
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-10-029
PANOLA SIGN & BARRICADE, INC. (1.19)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.90)
JM YANEZ CONSTRUCTION, INC. (14.01)
Contract #04213005
Totals2714170.795844.005844.000.2

CountyMARION ETC
HighwayFM 248 ETC
FromAT FM 2683
To.
CSJ0138-11-032
Proj IDSTP 2021(148)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.0801138920.94551677.8248.4
Work Order01-12-21
Work Began06-03-21
Work Completed
Time Computed05-12-21
Contract Working Days200
Addl Days Granted0
Working Days Charged26
Percent Time Used13
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-11-032
RANSOM DRILLING SERVICES, LLC (0.00)
AREA WIDE PROTECTIVE, INC. (0.00)
DOUBLE S CONSTRUCTION (0.00)
Contract #12203019
Totals1138920.94407167.67551677.8248.4

CountyCASS ETC
HighwayUS 59 ETC
From1.9 MI S OF FM 2328S
To4.07 MI S OF FM 2328S
CSJ0218-04-121
Proj IDSTP 2020(042)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.9952417417.002635855.2099.9
Work Order09-18-20
Work Began02-02-21
Work Completed
Time Computed10-19-20
Contract Working Days72
Addl Days Granted3
Working Days Charged51
Percent Time Used68
Contractor(s)
THE TRUESDELL CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0218-04-121
STRIPING TECHNOLOGY, L.P. (0.00)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.00)
DALLAS LITE AND BARRICADE, INC. (0.00)
EAST TEXAS BRIDGE, INC. (0.00)
Contract #08203233
Totals2417417.00592093.382635855.2099.9

CountyTITUS
HighwaySH 49
FromBU 271
ToMT. PLEASANT CITY LIMITS
CSJ0222-01-056
Proj IDSTP 2021(464)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.3133739806.75174924.014.6
Work Order05-20-21
Work Began06-23-21
Work Completed
Time Computed06-21-21
Contract Working Days257
Addl Days Granted0
Working Days Charged7
Percent Time Used2
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0222-01-056
TEXAS TRAFFIC AND BARRICADE, LLC (0.66)
ISAACS CONSTRUCTION SERVICES LLC (0.16)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (0.37)
STRIPING TECHNOLOGY, L.P. (2.56)
Contract #04213211
Totals3739806.75174924.01174924.014.6

CountyTITUS
HighwaySH 49
From0.1 MI E FM 1735
ToMORRIS C/L
CSJ0222-01-058
Proj IDSTP 2019(849)
Work TypeREHABILITATION OF EXISTING ROAD
 
13.47011689370.978389600.0971.7
Work Order06-21-19
Work Began07-29-19
Work Completed
Time Computed07-29-19
Contract Working Days320
Addl Days Granted0
Working Days Charged234
Percent Time Used73
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0222-01-058
MORRIS COUNTY CONTRACTORS, L.L.C. (0.48)
ISAACS CONSTRUCTION SERVICES LLC (0.27)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (0.26)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
PANOLA SIGN & BARRICADE, INC. (0.53)
STRIPING TECHNOLOGY, L.P. (2.36)
REYNOLDS & KAY, LTD. (0.03)
Contract #05193213
Totals11689370.9722405.608389600.0971.7

CountyPANOLA
HighwayUS 79
From1.4 MI. E. OF FM 124
ToRUSK C/L
CSJ0246-02-050
Proj IDSTP 2020(497)
Work TypeREHABILITATION OF EXISTING ROAD
 
8.19913117512.348017240.3661.1
CountyPANOLA
HighwayUS 79
FromSH 149
To1.4 MI. E. OF FM 124
CSJ0246-02-052
Proj IDSTP 2020(498)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
116377.630.000.0
CountyPANOLA
HighwayUS 79
From1.4 MI. E. OF FM 124
ToRUSK C/L
CSJ0246-02-053
Proj IDSTP 2020(498)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.323109292.2035632.0032.6
Work Order04-23-20
Work Began06-15-20
Work Completed
Time Computed05-25-20
Contract Working Days262
Addl Days Granted0
Working Days Charged193
Percent Time Used73
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0246-02-050
A.L. CONSTRUCTION LLC (1.04)
AMERICAN REMEDIATION OPTIONS, INC. (1.12)
CEN TEX HYDROSEED, INC. (1.26)
CHEROKEE SERVICES (1.15)
PANOLA SIGN & BARRICADE, INC. (0.27)
STRIPE-A-ZONE, INC. (2.04)
MADDEN CONTRACTING COMPANY, LLC. (22.96)
FORTSON CONTRACTING, INC. (0.09)
A BROTHERS MILLING, LLC (0.43)
Contract #03203207
Totals13343182.171263464.998052872.3660.3