Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | BOWIE ETC |
Highway | US 67 ETC |
From | 0.5 MI E OF SH 8 |
To | 0.5 MI W OF SH 8 |
CSJ | 0010-12-075 |
Proj ID | STP 2023(375)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 11.000 | 1397827.97 | | 175983.38 | 12.5 |
Work Order | 03-23-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 07-20-23 |
Contract Working Days | 172 |
Addl Days Granted | 0 |
Working Days Charged | 43 |
Percent Time Used | 25 |
Contractor(s) |
WG ENGINEERING & CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0010-12-075 GOMEZ PROPERTY SOLUTIONS LLC (3.54) RANSOM DRILLING SERVICES, LLC (2.87) MEDELLIN HDD LLC (7.50)
|
Contract # | 01233222 |
| Totals | 1397827.97 | 11004.00 | 175983.38 | 12.5 |
|
County | BOWIE ETC |
Highway | FM 991 ETC |
From | US 67 W |
To | US 67 E |
CSJ | 0010-19-014 |
Proj ID | F 2024(073) |
Work Type | SEAL COAT |
|
| 201.632 | 11823241.45 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 88 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
CDM HOLDINGS |
SUBCONTRACTOR(S) FOR CCSJ: 0010-19-014 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10233008 |
| Totals | 11823241.45 | 0.00 | 0.00 | 0.0 |
|
County | BOWIE |
Highway | SH 8 |
From | AT SULPHUR RIVER & SULPHUR RIV REL |
To | . |
CSJ | 0062-01-035 |
Proj ID | BR 2019(689) |
Work Type | BRIDGE REPLACEMENT |
|
| 1.551 | 35121366.72 | | 31827664.27 | 90.6 |
County | CASS |
Highway | SH 8 |
From | AT SULPHUR RIVER & SULPHUR RIV REL |
To | . |
CSJ | 0062-02-024 |
Proj ID | BR 2019(690) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.360 | 2612244.52 | | 1429555.12 | 54.7 |
Work Order | 05-02-19 |
Work Began | 05-13-19 |
Work Completed | |
Time Computed | 05-13-19 |
Contract Working Days | 1,215 |
Addl Days Granted | 11 |
Working Days Charged | 786 |
Percent Time Used | 64 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0062-01-035 BOWMAN ENGINEERING & CONSULTING, INC. (4.17) ISAACS CONSTRUCTION SERVICES LLC (0.09) JB PINNACLE GROUP, LLC (2.55) MORRIS COUNTY CONTRACTORS, L.L.C. (0.60) PANOLA SIGN & BARRICADE, INC. (0.16) STRIPING TECHNOLOGY, L.P. (0.73) TEXAS ALTERNATIVE GRASSER INCORPORATED (0.30) MASSEY CONTRACTORS, LLC (0.13) FARR FOUNDATION, INC. (1.00) CAP RIVER LLC (0.36) HERMANOS STEEL, LLC (0.03)
|
Contract # | 04193002 |
| Totals | 37733611.24 | 408858.60 | 33257219.39 | 88.1 |
|
County | PANOLA |
Highway | US 59 |
From | BU 59D |
To | US 79 |
CSJ | 0063-03-062 |
Proj ID | STP 2020(978)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 2.214 | 170539.60 | | 21721.70 | 12.7 |
County | PANOLA |
Highway | US 59 |
From | BU 59-D NORTH OF CARTHAGE |
To | US 79 EAST OF CARTHAGE |
CSJ | 0063-03-065 |
Proj ID | NH 2020(979) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 2.214 | 8694246.33 | | 8701267.62 | 99.9 |
Work Order | 08-26-20 |
Work Began | 09-25-20 |
Work Completed | |
Time Computed | 09-25-20 |
Contract Working Days | 503 |
Addl Days Granted | 7 |
Working Days Charged | 518 |
Percent Time Used | 101 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0063-03-062 STATEWIDE SAFETY SYSTEMS (0.37) AMERICAN REMEDIATION OPTIONS, INC. (2.51) ISAACS CONSTRUCTION SERVICES LLC (0.60) STRIPING TECHNOLOGY, L.P. (4.85) WEST TEXAS ROCK RESOURCES, LLC (0.04) ANTIGO CONSTRUCTION, INC. (0.40)
|
Contract # | 07203210 |
| Totals | 8864785.93 | 47490.89 | 8722989.32 | 98.5 |
|
County | PANOLA |
Highway | US 59 |
From | 1.4 MI. N. OF SHELBY C/L |
To | SHELBY C/L |
CSJ | 0063-05-040 |
Proj ID | STP 2022(448)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 1.403 | 480465.19 | | 898005.33 | 99.9 |
County | CASS |
Highway | US 59 |
From | SH 43N |
To | 0.1 MI. N. OF SH 77/FM 249 |
CSJ | 0218-04-122 |
Proj ID | STP 2022(448)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 2.155 | 299386.45 | | 153084.70 | 51.1 |
County | UPSHUR |
Highway | US 259 |
From | 0.9 MI. S. OF FM 450 |
To | 0.25 MI. N. OF FM 726 |
CSJ | 0392-02-101 |
Proj ID | STP 2022(448)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 3.346 | 546014.55 | | 330040.00 | 60.4 |
County | HARRISON |
Highway | IH 20 |
From | 0.2 MI. W. OF US 80 |
To | 0.1 MI. W. OF FM 134 |
CSJ | 0495-10-102 |
Proj ID | STP 2022(448)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 3.928 | 808760.02 | | 510211.00 | 63.0 |
Work Order | 05-10-22 |
Work Began | 08-07-23 |
Work Completed | |
Time Computed | 06-09-22 |
Contract Working Days | 149 |
Addl Days Granted | 0 |
Working Days Charged | 120 |
Percent Time Used | 80 |
Contractor(s) |
GRATIOT CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0063-05-040 FOX CONTRACTING KY, INC. (21.46) FC TRAFFIC CONTROL, INC. (1.98)
|
Contract # | 04223013 |
| Totals | 2134626.21 | 5000.00 | 1891341.03 | 88.6 |
|
County | PANOLA |
Highway | US 59 |
From | AT INTERSECTION OF FM 1794 |
To | . |
CSJ | 0063-10-015 |
Proj ID | C 63-10-15 |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| 1.458 | 36905848.45 | | 6002584.95 | 16.2 |
Work Order | 07-13-23 |
Work Began | 08-08-23 |
Work Completed | |
Time Computed | 08-08-23 |
Contract Working Days | 504 |
Addl Days Granted | 0 |
Working Days Charged | 54 |
Percent Time Used | 10 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0063-10-015 HODGES AND SON CONSTRUCTION COMPANY, INC. (0.46) MORRIS COUNTY CONTRACTORS, L.L.C. (0.39) PANOLA SIGN & BARRICADE, INC. (0.15) SOUTHWEST ENVIRONMENT SERVICES LLC (0.34) STRIPING TECHNOLOGY, L.P. (1.58) TORO BRAVO CONSTRUCTION, LLC (0.33) ISAACS CONSTRUCTION SERVICES LLC (0.59) WEST TEXAS ROCK RESOURCES, LLC (0.01) A&A TREE SERVICES (0.00) HIGHWAY 1 LLC (0.39)
|
Contract # | 06233003 |
| Totals | 36905848.45 | 1361974.34 | 6002584.95 | 16.2 |
|
County | PANOLA |
Highway | SH 149 |
From | 0.8 MI S OF SH 315 |
To | US 59 |
CSJ | 0063-11-054 |
Proj ID | F 2023(026) |
Work Type | WIDEN NON-FREEWAY |
|
| 1.623 | 29546263.07 | | 14269837.56 | 48.2 |
Work Order | 10-19-22 |
Work Began | 11-03-22 |
Work Completed | |
Time Computed | 11-03-22 |
Contract Working Days | 205 |
Addl Days Granted | 199 |
Working Days Charged | 184 |
Percent Time Used | 45 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-054 CAP RIVER LLC (0.68) FARR FOUNDATION, INC. (2.38) ISAACS CONSTRUCTION SERVICES LLC (0.61) MORRIS COUNTY CONTRACTORS, L.L.C. (0.98) PANOLA SIGN & BARRICADE, INC. (0.12) SCOTT DERR PAINTING CO, LLC (0.03) STRIPING TECHNOLOGY, L.P. (2.28) INTERSTATE BARRICADES & MARKINGS, INC. (0.28) A&A TREE SERVICES (0.00) CARTHAGE DRILLING, INC. (0.03)
|
Contract # | 09223001 |
| Totals | 29546263.07 | 542666.51 | 14269837.56 | 48.2 |
|
County | BOWIE ETC |
Highway | FM 2735 ETC |
From | 8.3 MI. N. OF US 82 |
To | US 82 |
CSJ | 0085-03-017 |
Proj ID | STP 2021(299)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 58.345 | 1493307.90 | | 1288068.13 | 86.2 |
Work Order | 07-28-21 |
Work Began | 11-16-21 |
Work Completed | |
Time Computed | 08-30-21 |
Contract Working Days | 285 |
Addl Days Granted | 0 |
Working Days Charged | 269 |
Percent Time Used | 94 |
Contractor(s) |
HX FARMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0085-03-017 FLEX SUPPLY, LLC (1.67) H. V. CAVER, INC. (1.33) CLEANVAC ENVIRONMENTAL LLC (2.00)
|
Contract # | 06213026 |
| Totals | 1493307.90 | 57768.26 | 1288068.13 | 86.2 |
|
County | UPSHUR |
Highway | US 80 |
From | WOOD C/L |
To | 0.3 MI E OF SH 155N |
CSJ | 0096-03-075 |
Proj ID | F 2023(088) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 2.926 | 6277174.34 | | 1622120.04 | 25.8 |
Work Order | 10-11-22 |
Work Began | 03-23-23 |
Work Completed | |
Time Computed | 03-10-23 |
Contract Working Days | 162 |
Addl Days Granted | 0 |
Working Days Charged | 73 |
Percent Time Used | 45 |
Contractor(s) |
MADDEN CONTRACTING COMPANY, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 0096-03-075 COLD CREEK CONSTRUCTION, LTD (4.29) ISAACS CONSTRUCTION SERVICES LLC (2.06) MORRIS COUNTY CONTRACTORS, L.L.C. (1.66) SOUTHWEST ENVIRONMENT SERVICES LLC (0.88) PANOLA SIGN & BARRICADE, INC. (1.28) R & G CONSTRUCTION, LLC (17.73) REYNOLDS & KAY, LTD. (1.77) STRIPING TECHNOLOGY, L.P. (2.59)
|
Contract # | 09223025 |
| Totals | 6277174.34 | 386743.42 | 1622120.04 | 25.8 |
|
County | HARRISON |
Highway | US 80 |
From | GREGG C/L |
To | 0.1 MI. W. OF TOM BROWN PARKWAY |
CSJ | 0096-07-054 |
Proj ID | F 2B23(018) |
Work Type | OVERLAY |
|
| 6.742 | 6333886.66 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 128 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MADDEN CONTRACTING COMPANY, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 0096-07-054 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08233011 |
| Totals | 6333886.66 | 0.00 | 0.00 | 0.0 |
|
County | CASS ETC |
Highway | FM 248 ETC |
From | SH 43 |
To | MARION C/L |
CSJ | 0138-10-029 |
Proj ID | STP 2021(287)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 98.460 | 2714170.79 | | 3207148.36 | 99.9 |
Work Order | 05-20-21 |
Work Began | 07-06-21 |
Work Completed | |
Time Computed | 06-21-21 |
Contract Working Days | 304 |
Addl Days Granted | 145 |
Working Days Charged | 398 |
Percent Time Used | 88 |
Contractor(s) |
H. V. CAVER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0138-10-029 PANOLA SIGN & BARRICADE, INC. (1.19) SOUTHWEST ENVIRONMENT SERVICES LLC (1.90) JM YANEZ CONSTRUCTION, INC. (14.01) ISAACS CONSTRUCTION SERVICES LLC (1.21) CLEANVAC ENVIRONMENTAL LLC (0.73)
|
Contract # | 04213005 |
| Totals | 2714170.79 | 46944.90 | 3207148.36 | 99.9 |
|
County | CASS |
Highway | US 59 |
From | 0.2 MI N OF SL 236 (NORTHBOUND ONLY) |
To | 0.5 MI S OF FM 3129 |
CSJ | 0218-03-087 |
Proj ID | C 218-3-87 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 6.408 | 7622162.45 | | 7094111.82 | 93.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 03-13-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 89 |
Addl Days Granted | 2 |
Working Days Charged | 82 |
Percent Time Used | 90 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0218-03-087 DUSTIN ALLEN, INC. (0.30) J. H. ODEN CONTRACTING COMPANY (0.56) SOUTHWEST ENVIRONMENT SERVICES LLC (0.14) STRIPING TECHNOLOGY, L.P. (4.29) SURFACE PREPARATION TECHNOLOGIES, LLC (0.21) TEXOP CONSTRUCTION (7.45) TRAFFIC HIGHWAY MAINTENANCE, LLC (0.17) WITHERS CONSTRUCTION, LLC (1.12) BAHENA CONSTRUCTION CO.,INC. (0.28)
|
Contract # | 02233008 |
| Totals | 7622162.45 | 110940.74 | 7094111.82 | 93.0 |
|
County | CASS |
Highway | US 59 |
From | 0.1 MI. S OF FM 2328N |
To | 1.9 MI. S OF FM 2328S |
CSJ | 0218-04-119 |
Proj ID | C 218-4-119 |
Work Type | RESTORATION |
|
| 2.308 | 11842462.04 | | 10886921.03 | 91.9 |
Work Order | 08-02-22 |
Work Began | 01-09-23 |
Work Completed | |
Time Computed | 10-31-22 |
Contract Working Days | 136 |
Addl Days Granted | 0 |
Working Days Charged | 103 |
Percent Time Used | 75 |
Contractor(s) |
EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0218-04-119 DUSTIN ALLEN, INC. (0.28) J. H. ODEN CONTRACTING COMPANY (0.08) PANOLA SIGN & BARRICADE, INC. (0.22) STRIPING TECHNOLOGY, L.P. (1.86) TEXOP CONSTRUCTION (2.06) KITECO PROPERTY SOLUTIONS INC. (0.35) WEST TEXAS ROCK RESOURCES, LLC (0.03)
|
Contract # | 06223409 |
| Totals | 11842462.04 | 1200.00 | 10886921.03 | 91.9 |
|
County | CASS |
Highway | US 59 |
From | 4.0 MI S OF FM 2328S |
To | SH 11 |
CSJ | 0218-04-126 |
Proj ID | F 2023(626) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 4.958 | 2198711.21 | | 2291041.36 | 99.9 |
Work Order | 04-19-23 |
Work Began | 06-16-23 |
Work Completed | |
Time Computed | 05-19-23 |
Contract Working Days | 70 |
Addl Days Granted | 0 |
Working Days Charged | 102 |
Percent Time Used | 145 |
Contractor(s) |
WINDING ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0218-04-126 INTERSTATE IMPROVEMENT, INC. (26.89) STRIPING TECHNOLOGY, L.P. (18.97) GHB EQUIPMENT COMPANY, L.L.C. (6.36) BLASTERS, INC. (0.95)
|
Contract # | 03233038 |
| Totals | 2198711.21 | 391249.60 | 2291041.36 | 99.9 |
|
County | TITUS |
Highway | US 271 |
From | AT DICKSON CREEK, BIG SLOUGH, |
To | . |
CSJ | 0221-05-065 |
Proj ID | BR 2020(451) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.586 | 8328468.53 | | 5718041.20 | 68.6 |
County | TITUS |
Highway | US 271 |
From | AT WHITE OAK CREEK |
To | . |
CSJ | 0221-05-086 |
Proj ID | BR 2020(451) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.443 | 6685831.52 | | 2966630.05 | 44.3 |
County | TITUS |
Highway | US 271 |
From | AT WHITE OAK CREEK_ RELIEF |
To | . |
CSJ | 0221-05-087 |
Proj ID | BR 2020(451) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.644 | 7213058.98 | | 3009636.17 | 41.7 |
Work Order | 12-16-21 |
Work Began | 01-03-22 |
Work Completed | |
Time Computed | 01-05-22 |
Contract Working Days | 602 |
Addl Days Granted | 12 |
Working Days Charged | 303 |
Percent Time Used | 49 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0221-05-065 HODGES AND SON CONSTRUCTION COMPANY, INC. (0.00) ISAACS CONSTRUCTION SERVICES LLC (1.15) MORRIS COUNTY CONTRACTORS, L.L.C. (1.03) PANOLA SIGN & BARRICADE, INC. (0.15) STRIPING TECHNOLOGY, L.P. (0.74) TORO BRAVO CONSTRUCTION, LLC (3.02) FARR FOUNDATION, INC. (0.64) TORO BRAVO CONSTRUCTION, LLC (0.02)
|
Contract # | 11213228 |
| Totals | 22227359.03 | 70651.72 | 11694307.42 | 52.6 |
|
County | TITUS |
Highway | US 271 |
From | 0.3 MI. S. OF FM 3417 |
To | CAMP C/L |
CSJ | 0248-01-081 |
Proj ID | F 2023(099) |
Work Type | OVERLAY |
|
| 5.977 | 5186944.38 | | 5136985.85 | 99.0 |
Work Order | 10-06-22 |
Work Began | 08-07-23 |
Work Completed | |
Time Computed | 01-04-23 |
Contract Working Days | 72 |
Addl Days Granted | 11 |
Working Days Charged | 78 |
Percent Time Used | 93 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0248-01-081 PANOLA SIGN & BARRICADE, INC. (0.17) TEXOP CONSTRUCTION (7.47) DUSTIN ALLEN, INC. (1.77) MARCOM"S MOWING SERVICE, LLC (0.61) STRIPE-A-ZONE, LLC (4.04) J. H. ODEN CONTRACTING COMPANY (0.02) CHEROKEE SERVICES (3.32) BAHENA CONSTRUCTION CO.,INC. (0.92)
|
Contract # | 09223032 |
| Totals | 5186944.38 | 381474.39 | 5136985.85 | 99.0 |
|
County | UPSHUR |
Highway | US 271 |
From | 5.9 MI. N. OF SH 155 |
To | 1.5 MI. N. OF SH 155 |
CSJ | 0248-04-072 |
Proj ID | NH 2020(145) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 4.231 | 12013248.87 | | 11648265.34 | 98.6 |
Work Order | 12-22-21 |
Work Began | 02-25-22 |
Work Completed | |
Time Computed | 01-21-22 |
Contract Working Days | 189 |
Addl Days Granted | 0 |
Working Days Charged | 349 |
Percent Time Used | 184 |
Contractor(s) |
MADDEN CONTRACTING COMPANY, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 0248-04-072 STRIPING TECHNOLOGY, L.P. (1.20) R & G CONSTRUCTION, LLC (14.38) SURFACE PREPARATION TECHNOLOGIES, LLC (0.07) COLD CREEK CONSTRUCTION, LTD (0.83) ISAACS CONSTRUCTION SERVICES LLC (0.23) MORRIS COUNTY CONTRACTORS, L.L.C. (1.60) CF SOUTHWEST ENVIRONMENT SERVICES LLC (0.00) PRIMATE CONSTRUCTION, LP (0.98) PANOLA SIGN & BARRICADE, INC. (0.26) A. L. HELMCAMP, INC. (0.25) SOUTHWEST ENVIRONMENT SERVICES LLC (0.90)
|
Contract # | 11213227 |
| Totals | 12013248.87 | 138188.68 | 11648265.34 | 98.6 |
|
County | BOWIE |
Highway | SH 98 |
From | AT ANDERSON CREEK |
To | . |
CSJ | 0330-01-033 |
Proj ID | BR 2019(848) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.213 | 2307499.75 | | 2513937.20 | 99.9 |
County | BOWIE |
Highway | SH 98 |
From | AT ANDERSON CK RELIEF |
To | . |
CSJ | 0330-01-034 |
Proj ID | BR 2019(848) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.185 | 1612449.05 | | 1737456.54 | 99.9 |
Work Order | 07-27-20 |
Work Began | 09-08-20 |
Work Completed | |
Time Computed | 08-26-20 |
Contract Working Days | 287 |
Addl Days Granted | 6 |
Working Days Charged | 311 |
Percent Time Used | 106 |
Contractor(s) |
EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0330-01-033 M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.05) PANOLA SIGN & BARRICADE, INC. (0.32) MORRIS COUNTY CONTRACTORS, L.L.C. (1.30) ISAACS CONSTRUCTION SERVICES LLC (1.11) PENHALL COMPANY (0.27) SOUTHWEST ENVIRONMENT SERIVES, LLC (0.77) STRIPING TECHNOLOGY, L.P. (2.05) TORO BRAVO CONSTRUCTION, LLC (0.32) BAR H WELDING LLC (0.06) LUCKETT CRANE SERVICE (0.66) BRUNDAGE-BONE (0.06) BADGER DAYLIGHTING CORP. (0.20) TEXOP CONSTRUCTION (0.15) WEST TEXAS ROCK RESOURCES, LLC (0.14)
|
Contract # | 06203209 |
| Totals | 3919948.80 | 27520.00 | 4251393.74 | 99.9 |
|
County | UPSHUR |
Highway | SH 154 |
From | FM 726 S |
To | UPSHUR C/L |
CSJ | 0402-02-035 |
Proj ID | STP 2023(698)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 7.334 | 1394643.36 | | 1294827.30 | 92.8 |
County | HARRISON |
Highway | SH 154 |
From | UPSHUR C/L |
To | 4.43 MI E OF FM 2208 |
CSJ | 0402-03-042 |
Proj ID | STP 2023(698)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 13.133 | 2097779.54 | | 1420939.48 | 67.7 |
Work Order | 06-14-23 |
Work Began | 07-17-23 |
Work Completed | |
Time Computed | 07-17-23 |
Contract Working Days | 197 |
Addl Days Granted | 0 |
Working Days Charged | 74 |
Percent Time Used | 37 |
Contractor(s) |
EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0402-02-035 WITHERS CONSTRUCTION, LLC (13.40) PANOLA SIGN & BARRICADE, INC. (0.51) J. H. ODEN CONTRACTING COMPANY (3.82)
|
Contract # | 05233215 |
| Totals | 3492422.90 | 336699.90 | 2715766.78 | 77.7 |
|
County | PANOLA |
Highway | SH 315 |
From | 0.5 MI W OF FM 348 |
To | RUSK C/L |
CSJ | 0462-03-048 |
Proj ID | F 2B23(017) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 2.493 | 2393806.97 | | 0.00 | 0.0 |
County | PANOLA |
Highway | SH 315 |
From | FM 1970 |
To | 0.5 MI W OF FM 348 |
CSJ | 0462-03-050 |
Proj ID | STP 2B23(019)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 6.185 | 3576329.35 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-13-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-13-23 |
Contract Working Days | 199 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MADDEN CONTRACTING COMPANY, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 0462-03-048 CAP RIVER LLC (0.28) ISAACS CONSTRUCTION SERVICES LLC (0.22) MORRIS COUNTY CONTRACTORS, L.L.C. (0.94) PRIMATE CONSTRUCTION, LP (0.59) PANOLA SIGN & BARRICADE, INC. (0.69) R & G CONSTRUCTION, LLC (7.84) SOUTHWEST ENVIRONMENT SERVICES LLC (0.40) STRIPING TECHNOLOGY, L.P. (9.08)
|
Contract # | 08233012 |
| Totals | 5970136.32 | 0.00 | 0.00 | 0.0 |
|