Monthly State Let Construction Report For Atlanta District As Of Jan 10, 2023 Page 1 Of 3

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTITUS ETC
HighwayUS 67 ETC
From0.1 MI E OF FM 1734 (W)
To0.1 MI W OF US 271
CSJ0010-06-044
Proj IDF 2023(130)
Work TypeSEAL COAT
 
156.76610814286.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-06-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10223010
Totals10814286.760.000.000.0

CountyCASS
HighwayUS 67
FromAT JENNINGS SLOUGH
To.
CSJ0010-10-026
Proj IDBR 2021(581)
Work TypeBRIDGE REPLACEMENT
 
0.2466039514.505418592.9089.7
Work Order07-20-21
Work Began08-09-21
Work Completed
Time Computed08-09-21
Contract Working Days283
Addl Days Granted0
Working Days Charged265
Percent Time Used93
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-10-026
PEACHTREE CONSTRUCTION, LTD. (4.19)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (0.17)
STRIPING TECHNOLOGY, L.P. (0.62)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.44)
TEXAS TRAFFIC AND BARRICADE, LLC (0.39)
PRIMATE CONSTRUCTION, LP (0.14)
HERMANOS STEEL, LLC (0.07)
Contract #06213211
Totals6039514.5052254.205418592.9089.7

CountyBOWIE ETC
HighwayUS 67 ETC
FromFM 2149
To1.367 MI. E. OF FM 991
CSJ0010-12-074
Proj IDF 2021(829)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
276.2203499747.232502919.7071.5
Work Order09-20-21
Work Began11-15-21
Work Completed
Time Computed10-21-21
Contract Working Days143
Addl Days Granted0
Working Days Charged129
Percent Time Used90
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-12-074
BRYDL CONTRACTING, LLC (2.82)
Contract #08213231
Totals3499747.230.002502919.7071.5

CountyBOWIE ETC
HighwayUS 67 ETC
From0.5 MI E OF SH 8
To0.5 MI W OF SH 8
CSJ0010-12-075
Proj IDSTP 2023(375)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
11.0001397827.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days172
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-12-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233222
Totals1397827.970.000.000.0

CountyBOWIE
HighwayUS 82
FromAT FM 2148
To.
CSJ0046-06-082
Proj IDSTP 2022(407)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.500248913.27225897.4090.7
Work Order06-15-22
Work Began09-08-22
Work Completed
Time Computed09-06-22
Contract Working Days65
Addl Days Granted0
Working Days Charged45
Percent Time Used69
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0046-06-082
PANOLA SIGN & BARRICADE, INC. (1.79)
H. V. CAVER, INC. (20.89)
JOSH & ERICA ENTERPRISES LLC (10.44)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.55)
Contract #03223224
Totals248913.2723633.20225897.4090.7

CountyBOWIE
HighwaySH 8
FromAT SULPHUR RIVER & SULPHUR RIV REL
To.
CSJ0062-01-035
Proj IDBR 2019(689)
Work TypeBRIDGE REPLACEMENT
 
1.55135121366.7229278934.3283.3
CountyCASS
HighwaySH 8
FromAT SULPHUR RIVER & SULPHUR RIV REL
To.
CSJ0062-02-024
Proj IDBR 2019(690)
Work TypeBRIDGE REPLACEMENT
 
0.3602612244.521015255.0138.8
Work Order05-02-19
Work Began05-13-19
Work Completed
Time Computed05-13-19
Contract Working Days1,215
Addl Days Granted11
Working Days Charged652
Percent Time Used53
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0062-01-035
BOWMAN ENGINEERING & CONSULTING, INC. (4.17)
ISAACS CONSTRUCTION SERVICES LLC (0.09)
JB PINNACLE GROUP, LLC (2.55)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.60)
PANOLA SIGN & BARRICADE, INC. (0.16)
STRIPING TECHNOLOGY, L.P. (0.73)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.30)
MASSEY CONTRACTORS, LLC (0.13)
FARR FOUNDATION, INC. (1.00)
Contract #04193002
Totals37733611.24202823.2530294189.3380.2

CountyCASS ETC
HighwayUS 59
From1.46 MI. S. OF SH 155
ToMARION COUNTY LINE
CSJ0062-04-050
Proj IDNH 2021(099)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
35.7654434952.654834476.9199.9
Work Order12-15-20
Work Began01-26-21
Work Completed
Time Computed01-14-21
Contract Working Days276
Addl Days Granted0
Working Days Charged277
Percent Time Used100
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-04-050
FLORES CONCRETE (27.84)
PANOLA SIGN & BARRICADE, INC. (0.66)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.08)
Contract #11203011
Totals4434952.65160267.964834476.9199.9

CountyCASS ETC
HighwayUS 59 ETC
FromAT SH 155
To.
CSJ0062-04-051
Proj IDF 2022(515)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
25.000504893.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged2
Percent Time Used2
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-04-051
SNOWHILL CONTRACTING LLC (31.44)
Contract #04223235
Totals504893.320.000.000.0

CountyPANOLA
HighwayUS 59
FromBU 59D
ToUS 79
CSJ0063-03-062
Proj IDSTP 2020(978)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.214170539.600.000.0
CountyPANOLA
HighwayUS 59
FromBU 59-D NORTH OF CARTHAGE
ToUS 79 EAST OF CARTHAGE
CSJ0063-03-065
Proj IDNH 2020(979)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.2148694246.336649076.2376.4
Work Order08-26-20
Work Began09-25-20
Work Completed
Time Computed09-25-20
Contract Working Days503
Addl Days Granted7
Working Days Charged414
Percent Time Used81
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0063-03-062
STATEWIDE SAFETY SYSTEMS (0.37)
AMERICAN REMEDIATION OPTIONS, INC. (2.51)
ISAACS CONSTRUCTION SERVICES LLC (0.60)
STRIPING TECHNOLOGY, L.P. (4.85)
WEST TEXAS ROCK RESOURCES, LLC (0.04)
ANTIGO CONSTRUCTION, INC. (0.40)
Contract #07203210
Totals8864785.938500.006649076.2375.0

CountyPANOLA
HighwayUS 59
From1.4 MI. N. OF SHELBY C/L
ToSHELBY C/L
CSJ0063-05-040
Proj IDSTP 2022(448)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.403480465.190.000.0
CountyCASS
HighwayUS 59
FromSH 43N
To0.1 MI. N. OF SH 77/FM 249
CSJ0218-04-122
Proj IDSTP 2022(448)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.155299386.450.000.0
CountyUPSHUR
HighwayUS 259
From0.9 MI. S. OF FM 450
To0.25 MI. N. OF FM 726
CSJ0392-02-101
Proj IDSTP 2022(448)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.346546014.550.000.0
CountyHARRISON
HighwayIH 20
From0.2 MI. W. OF US 80
To0.1 MI. W. OF FM 134
CSJ0495-10-102
Proj IDSTP 2022(448)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.928808760.020.000.0
Work Order05-10-22
Work Began00-00-00
Work Completed
Time Computed06-09-22
Contract Working Days149
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0063-05-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04223013
Totals2134626.210.000.000.0

CountyPANOLA
HighwaySH 149
From0.8 MI S OF SH 315
ToUS 59
CSJ0063-11-054
Proj IDF 2023(026)
Work TypeWIDEN NON-FREEWAY
 
1.62329546263.073587467.0512.1
Work Order10-19-22
Work Began11-03-22
Work Completed
Time Computed11-03-22
Contract Working Days205
Addl Days Granted0
Working Days Charged17
Percent Time Used8
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-054
CAP RIVER LLC (0.68)
FARR FOUNDATION, INC. (2.38)
ISAACS CONSTRUCTION SERVICES LLC (0.61)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.98)
PANOLA SIGN & BARRICADE, INC. (0.12)
SCOTT DERR PAINTING CO, LLC (0.03)
STRIPING TECHNOLOGY, L.P. (2.28)
INTERSTATE BARRICADES & MARKINGS, INC. (0.28)
A&A TREE SERVICES (0.00)
Contract #09223001
Totals29546263.071294179.623587467.0512.1

CountyBOWIE ETC
HighwayFM 2735 ETC
From8.3 MI. N. OF US 82
ToUS 82
CSJ0085-03-017
Proj IDSTP 2021(299)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
58.3451493307.90734939.2349.2
Work Order07-28-21
Work Began11-16-21
Work Completed
Time Computed08-30-21
Contract Working Days285
Addl Days Granted0
Working Days Charged162
Percent Time Used56
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0085-03-017
FLEX SUPPLY, LLC (1.67)
H. V. CAVER, INC. (1.33)
CLEANVAC ENVIRONMENTAL LLC (2.00)
Contract #06213026
Totals1493307.908651.00734939.2349.2

CountyBOWIE ETC
HighwayUS 259 ETC
FromAT FM 1701
To.
CSJ0085-04-050
Proj IDF 2022(656)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.000587345.50153464.0026.1
Work Order07-19-22
Work Began11-30-22
Work Completed
Time Computed10-17-22
Contract Working Days128
Addl Days Granted0
Working Days Charged14
Percent Time Used10
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0085-04-050
MATRIX CONCRETE ROAD & BRIDGE, LLC (2.34)
Contract #06223027
Totals587345.5087030.00153464.0026.1

CountyUPSHUR
HighwayUS 80
FromWOOD C/L
To0.3 MI E OF SH 155N
CSJ0096-03-075
Proj IDF 2023(088)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.9266277174.340.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-11-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days162
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0096-03-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09223025
Totals6277174.340.000.000.0

CountyHARRISON
HighwayUS 80
FromSL 281
ToTOM BROWN PARKWAY
CSJ0096-07-052
Proj IDSTP 2023(025)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.5051144740.450.000.0
CountyMORRIS
HighwaySH 11
From0.72 MI E OF US 259
To3.47 MI E OF US 259
CSJ0222-03-064
Proj IDSTP 2023(025)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.749435418.820.000.0
CountyTITUS
HighwayUS 271
From1.0 MI S OF SH 49
To1.0 MI W OF BU 271
CSJ0248-09-006
Proj IDSTP 2023(025)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.704282823.010.000.0
Work Order10-13-22
Work Began00-00-00
Work Completed
Time Computed11-14-22
Contract Working Days117
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0096-07-052
FLEX SUPPLY, LLC (1.05)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.21)
Contract #09223217
Totals1862982.280.000.000.0

CountyCASS ETC
HighwayFM 248 ETC
FromSH 43
ToMARION C/L
CSJ0138-10-029
Proj IDSTP 2021(287)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
98.4602714170.792359954.0086.9
Work Order05-20-21
Work Began07-06-21
Work Completed
Time Computed06-21-21
Contract Working Days304
Addl Days Granted0
Working Days Charged270
Percent Time Used88
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-10-029
PANOLA SIGN & BARRICADE, INC. (1.19)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.90)
JM YANEZ CONSTRUCTION, INC. (14.01)
ISAACS CONSTRUCTION SERVICES LLC (1.21)
CLEANVAC ENVIRONMENTAL LLC (0.73)
Contract #04213005
Totals2714170.7937678.672359954.0086.9

CountyCASS
HighwayUS 59
From0.1 MI. S OF FM 2328N
To1.9 MI. S OF FM 2328S
CSJ0218-04-119
Proj IDC 218-4-119
Work TypeRESTORATION
 
2.30811842462.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-02-22
Work Began00-00-00
Work Completed
Time Computed10-31-22
Contract Working Days136
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0218-04-119
DUSTIN ALLEN, INC. (0.28)
J. H. ODEN CONTRACTING COMPANY (0.08)
PANOLA SIGN & BARRICADE, INC. (0.22)
STRIPING TECHNOLOGY, L.P. (1.86)
Contract #06223409
Totals11842462.040.000.000.0

CountyTITUS
HighwayUS 271
FromAT DICKSON CREEK, BIG SLOUGH,
To.
CSJ0221-05-065
Proj IDBR 2020(451)
Work TypeBRIDGE REPLACEMENT
 
0.5868328468.535056178.1260.7
CountyTITUS
HighwayUS 271
FromAT WHITE OAK CREEK
To.
CSJ0221-05-086
Proj IDBR 2020(451)
Work TypeBRIDGE REPLACEMENT
 
0.4436685831.52106479.691.5
CountyTITUS
HighwayUS 271
FromAT WHITE OAK CREEK_ RELIEF
To.
CSJ0221-05-087
Proj IDBR 2020(451)
Work TypeBRIDGE REPLACEMENT
 
0.6447213058.984847917.3067.2
Work Order12-16-21
Work Began01-03-22
Work Completed
Time Computed01-05-22
Contract Working Days602
Addl Days Granted2
Working Days Charged189
Percent Time Used31
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0221-05-065
HODGES AND SON CONSTRUCTION COMPANY, INC. (0.00)
ISAACS CONSTRUCTION SERVICES LLC (1.15)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.03)
PANOLA SIGN & BARRICADE, INC. (0.15)
STRIPING TECHNOLOGY, L.P. (0.74)
TORO BRAVO CONSTRUCTION, LLC (3.02)
FARR FOUNDATION, INC. (0.64)
TORO BRAVO CONSTRUCTION, LLC (0.02)
Contract #11213228
Totals22227359.0341043.489797615.7344.0

CountyTITUS
HighwayUS 271
From0.3 MI. S. OF FM 3417
ToCAMP C/L
CSJ0248-01-081
Proj IDF 2023(099)
Work TypeOVERLAY
 
5.9775186944.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0248-01-081
PANOLA SIGN & BARRICADE, INC. (0.17)
TEXOP CONSTRUCTION (7.47)
DUSTIN ALLEN, INC. (1.77)
MARCOM"S MOWING SERVICE, LLC (0.61)
STRIPE-A-ZONE, LLC (4.04)
J. H. ODEN CONTRACTING COMPANY (0.02)
Contract #09223032
Totals5186944.380.000.000.0

CountyUPSHUR
HighwayUS 271
From5.9 MI. N. OF SH 155
To1.5 MI. N. OF SH 155
CSJ0248-04-072
Proj IDNH 2020(145)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.23112013248.875970513.4649.6
Work Order12-22-21
Work Began02-25-22
Work Completed
Time Computed01-21-22
Contract Working Days189
Addl Days Granted0
Working Days Charged181
Percent Time Used95
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0248-04-072
STRIPING TECHNOLOGY, L.P. (1.20)
R & G CONSTRUCTION, LLC (14.38)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.07)
COLD CREEK CONSTRUCTION, LTD (0.83)
ISAACS CONSTRUCTION SERVICES LLC (0.23)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.60)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (0.90)
PRIMATE CONSTRUCTION, LP (0.98)
PANOLA SIGN & BARRICADE, INC. (0.26)
A. L. HELMCAMP, INC. (0.25)
Contract #11213227
Totals12013248.8751620.465970513.4649.6

page 1 | page 2 | page 3