Monthly Local Let Maintenance Report For Atlanta District As Of Nov 10, 2024 Page 3 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMARION
HighwaySH0049
From.
To.
CSJ6457-39-001
Proj IDSUP - 645739001
Work TypeJANITORIAL MAINTENANCE
 
0.0106850.006500.0094.8
Work Order10-01-23
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days366
Addl Days Granted365
Working Days Charged397
Percent Time Used54
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6457-39-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #09231931
Totals6850.00500.006500.0094.8

CountyTITUS
HighwayUS0271
From.
To.
CSJ6459-61-001
Proj IDSUP - 645961001
Work TypeGROUNDS MAINTENANCE
 
0.0105520.005520.0099.9
Work Order10-27-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days366
Addl Days Granted365
Working Days Charged366
Percent Time Used50
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6459-61-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #10231931
Totals5520.00460.005520.0099.9

CountyCASS
HighwayUS0059
From.
To.
CSJ6459-63-001
Proj IDSUP - 645963001
Work TypePICNIC AREA MAINTENANCE
 
0.01049300.0049300.0099.9
Work Order10-27-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days366
Addl Days Granted365
Working Days Charged366
Percent Time Used50
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6459-63-001
CAMP COUNTY SERVICE INDUSTRIES (204.86)
Contract #10231932
Totals49300.003980.0049300.0099.9

CountyCASS
HighwayFM0249
From.
To.
CSJ6460-91-001
Proj IDSUP - 646091001
Work TypeGROUNDS MAINTENANCE
 
0.01037200.0033750.0090.7
Work Order11-16-23
Work Began12-01-23
Work Completed
Time Computed12-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged336
Percent Time Used91
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6460-91-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #11231931
Totals37200.004100.0033750.0090.7

CountyMORRIS
HighwayUS0067
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6464-21-001
Proj IDBPM - 646421001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010842650.000.000.0
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed10-21-24
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6464-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241902
Totals842650.000.000.000.0

CountyUPSHUR
HighwayUS0271
FromUS0271/SH0155
ToUS0271/SH0155
CSJ6464-54-001
Proj IDRMC - 646454001
Work TypeLANDSCAPE MAINTENANCE
 
0.01053300.0013200.0024.7
Work Order00-00-00
Work Began05-20-24
Work Completed
Time Computed05-20-24
Contract Working Days730
Addl Days Granted0
Working Days Charged165
Percent Time Used22
Contractor(s)
SCOUT 5 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6464-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03241901
Totals53300.002200.0013200.0024.7

CountyCASS
HighwayFM0249
From.
To.
CSJ6465-11-001
Proj IDSUP - 646511001
Work TypeJANITORIAL MAINTENANCE
 
0.01095101.2840850.3942.9
Work Order03-19-24
Work Began04-01-24
Work Completed
Time Computed04-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-11-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #02241931
Totals95101.285835.7740850.3942.9

CountyBOWIE
HighwayIH0369
From.
To.
CSJ6466-34-001
Proj IDSUP - 646634001
Work TypeGROUNDS MAINTENANCE
 
0.01016126.569689.6460.0
Work Order04-26-24
Work Began05-01-24
Work Completed
Time Computed05-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6466-34-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #03241931
Totals16126.56583.499689.6460.0

CountyCASS
HighwaySH0008
FromVARIOUS ROADWAYS IN
ToBOWIE AND CASS COUNTIES
CSJ6468-87-001
Proj IDRMC - 646887001
Work TypeTREE REMOVAL
 
0.010615004.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6468-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241902
Totals615004.000.000.000.0

CountyTITUS
HighwayUS0271
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6470-63-001
Proj IDSUP - 647063001
Work TypeLITTER REMOVAL
 
0.010119265.6638630.2232.3
Work Order07-01-24
Work Began07-01-24
Work Completed
Time Computed07-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6470-63-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #06241931
Totals119265.663959.0238630.2232.3

CountyTITUS
HighwayFM0071
From.
To.
CSJ6470-64-001
Proj IDRMC - 647064001
Work TypeCRACK SEAL
 
0.010624941.00670929.00100.0
Work Order00-00-00
Work Began10-14-24
Work Completed10-31-24
Time Computed10-14-24
Contract Working Days43
Addl Days Granted1
Working Days Charged14
Percent Time Used31
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6470-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09241901
Totals624941.00670929.00670929.00100.0

CountyHARRISON
HighwayIH0020
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6473-69-001
Proj IDMMC - 647369001
Work TypeAGGREGATE
 
0.0101118576.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began11-01-24
Work Completed
Time Computed11-01-24
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241901
Totals1118576.400.000.000.0

CountyCASS
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6473-70-001
Proj IDMMC - 647370001
Work TypeHOT MIX
 
0.010415200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began12-08-24
Work Completed
Time Computed12-08-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241909
Totals415200.000.000.000.0

CountyPANOLA
HighwayUS0079
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6473-71-001
Proj IDMMC - 647371001
Work TypeHOT MIX
 
0.010396480.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began12-08-24
Work Completed
Time Computed12-08-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241905
Totals396480.000.000.000.0

CountyMORRIS
HighwayUS0259
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6473-72-001
Proj IDMMC - 647372001
Work TypeHOT MIX
 
0.010377000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began12-08-24
Work Completed
Time Computed12-08-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241906
Totals377000.000.000.000.0

CountyUPSHUR
HighwayUS0271
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6473-73-001
Proj IDMMC - 647373001
Work TypeHOT MIX
 
0.010387000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began12-08-24
Work Completed
Time Computed12-08-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241907
Totals387000.000.000.000.0

CountyMARION
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6473-74-001
Proj IDMMC - 647374001
Work TypeHOT MIX
 
0.010396480.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began12-08-24
Work Completed
Time Computed12-08-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241908
Totals396480.000.000.000.0

CountyHARRISON
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6473-76-001
Proj IDMMC - 647376001
Work TypeHOT MIX
 
0.010396480.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began12-08-24
Work Completed
Time Computed12-08-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6473-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241910
Totals396480.000.000.000.0

CountyTITUS
HighwayUS0271
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6473-77-001
Proj IDMMC - 647377001
Work TypeHOT MIX
 
0.010377000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began12-08-24
Work Completed
Time Computed12-08-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241911
Totals377000.000.000.000.0

CountyBOWIE
HighwayUS0082
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6473-78-001
Proj IDMMC - 647378001
Work TypeHOT MIX
 
0.010412700.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-24
Work Began12-08-24
Work Completed
Time Computed12-08-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6473-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10241912
Totals412700.000.000.000.0

page 1 | page 2 | page 3 | page 4