Monthly State Let Construction Report For Austin District As Of Nov 10, 2024 Page 2 Of 6

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGILLESPIE
HighwayUS 290
FromKIMBLE C/L
ToW OF FLAG CREEK
CSJ0112-02-036
Proj IDF 2024(364)
Work TypeSEAL COAT
 
3888100.804066932.9599.9
Work Order12-06-23
Work Began02-07-24
Work Completed
Time Computed02-07-24
Contract Working Days158
Addl Days Granted0
Working Days Charged100
Percent Time Used63
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0112-02-036
KELLER TRUCKING, INC. (0.00)
MPB, INC. (0.00)
D. I. J. CONSTRUCTION, INC. (0.00)
Contract #11233210
Totals3888100.80472935.904066932.9599.9

CountyGILLESPIE
HighwayUS 290
FromE. OF REEH RD
ToUS 87
CSJ0112-03-036
Proj IDF 2024(027)
Work TypeSEAL COAT
 
3070929.923017065.7698.2
Work Order10-12-23
Work Began01-08-24
Work Completed
Time Computed01-08-24
Contract Working Days57
Addl Days Granted0
Working Days Charged53
Percent Time Used92
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0112-03-036
D. I. J. CONSTRUCTION, INC. (0.00)
MPB, INC. (0.00)
KELLER TRUCKING, INC. (0.00)
Contract #09233218
Totals3070929.92213252.193017065.7698.2

CountyGILLESPIE
HighwayUS 290
FromJENSCHKE LANE
ToCEMETERY RD
CSJ0113-02-063
Proj IDC 113-2-63
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
2.90012041546.057715613.9664.0
Work Order07-19-23
Work Began10-30-23
Work Completed
Time Computed08-18-23
Contract Working Days219
Addl Days Granted60
Working Days Charged161
Percent Time Used57
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0113-02-063
D. I. J. CONSTRUCTION, INC. (0.00)
LINDAMOOD, INC. (0.00)
LONE STAR EROSION CONTROL (0.00)
MPB, INC. (0.00)
MURRAY CONSTRUCTION (0.00)
PRIMATE CONSTRUCTION, LP (0.00)
ROADWAY SPECIALTIES, INC. (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.00)
TEXAS SHAFTS, INC. (0.00)
FLASHER EQUIPMENT COMPANY (0.00)
EGGEMEYER LAND CLEARING, LLC (0.00)
THE LEVY COMPANY, INC. (0.00)
HARDY HOLE DRILLING (0.00)
UNDERGROUND SERVICES, INC. (0.00)
CAPITAL EXCAVATION COMPANY (0.00)
Contract #06233206
Totals12041546.052139738.507715613.9664.0

CountyTRAVIS
HighwayUS 290
FromAT LEDGESTONE TERRACE
To.
CSJ0113-08-091
Proj IDF 2025(030)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
478253.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days23
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AARON CONCRETE CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0113-08-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243237
Totals478253.000.000.000.0

CountyTRAVIS
HighwayUS 290
FromSL 1
ToW OF WESTGATE BLVD
CSJ0113-09-073
Proj IDC 113-9-73
Work TypeOVERLAY
 
1494644.671398775.5093.5
CountyTRAVIS
HighwayUS 290
FromSH 343
ToSL 360
CSJ0113-13-184
Proj IDC 113-13-184
Work TypeOVERLAY
 
532176.56541565.1499.9
Work Order02-02-24
Work Began07-25-24
Work Completed
Time Computed07-25-24
Contract Working Days48
Addl Days Granted0
Working Days Charged18
Percent Time Used37
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-09-073
TRP CONSTRUCTION GROUP, LLC (6.98)
GBC GENERAL BARRICADE COMPANY LLC (0.00)
CHEROKEE SERVICES (1.37)
GBC GENERAL BARRICADE COMPANY LLC (1.37)
Contract #01243030
Totals2026821.2348034.121940340.6495.7

CountyTRAVIS
HighwayUS 290
From0.246 MILES WEST OF SL 1
ToWEST GATE BLVD
CSJ0113-09-077
Proj IDSTP 2B24(415)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
406602.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-09-077
ENVIRONMENTAL SAFETY SERVICES, INC. (3.88)
ROADWAY TRAFFIC CONTROL LLC (1.31)
Contract #08243254
Totals406602.550.000.000.0

CountyTRAVIS
HighwaySL 360
FromAT WESTLAKE DRIVE
To.
CSJ0113-13-166
Proj IDF 2022(160)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.05459242343.7729922231.4950.5
CountyTRAVIS
HighwaySL 360
FromAT WESTLAKE DRIVE
To.
CSJ0113-13-183
Proj IDROW 113-13-183
Work TypeRIGHT OF WAY
 
1.05412088071.8913208494.0699.9
Work Order02-15-22
Work Began07-05-22
Work Completed
Time Computed05-16-22
Contract Working Days714
Addl Days Granted54
Working Days Charged524
Percent Time Used68
Contractor(s)
COPASA INC
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-166
GUERRA UNDERGROUND LLC (17.00)
HERMANOS STEEL, LLC (0.41)
TEXAS TRAFFIC AND BARRICADE, LLC (0.07)
QUALITY TURF FARMS, L.C. (0.76)
WHO-B TRUCKING, INC. (0.40)
ROADWAY SPECIALTIES, INC. (1.75)
LONE STAR PAVING COMPANY (6.31)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.88)
JPC CONSTRUCTION, INC. (2.22)
BRAZOS RIVER CONTRACTORS LLC (9.01)
ROAD MAKER CONTRACTORS (6.35)
TEXAS AUGER BORING LLC (0.00)
STATEWIDE MATERIALS TRANSPORT, LTD. (0.70)
TRP CONSTRUCTION GROUP, LLC (1.21)
MELENDREZ TRUCKING LLC (0.00)
DAN GUERRERO TRUCKING AND DISPATCH SERVICES (0.00)
CENTRAL TEXAS ROAD BORING (0.00)
STRIPE IT UP, LLC (0.00)
SILVAS TRUCKING, LLC (0.00)
FARR FOUNDATION, INC. (7.50)
VORTEX LINING SYSTEMS, LLC (1.34)
PEREZ CONSTRUCTION CO. (0.22)
DAKOTA UTILITY CONTRACTORS, INC. (0.00)
SUPERIOR PUMP SOLUTIONS LLC (0.00)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
TEXOP CONSTRUCTION (0.23)
YGCD, LLC DBA GRIND TIME ROCK MILLING (2.61)
Contract #12213001
Totals71330415.661669405.4143130725.5560.4

CountyTRAVIS
HighwayUS 290
From0.115 MI W OF GEORGE BUSH ST
ToCEDER ST
CSJ0114-02-113
Proj IDSTP 2B24(411)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.284738482.220.000.0
CountyTRAVIS
HighwayUS 290
FromAT LEXINGTON
To.
CSJ0114-02-114
Proj IDSTP 2B24(413)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.100387820.680.000.0
CountyTRAVIS
HighwayUS 290
From0.202 MI EAST OF LEXINGTON ST
To0.203 MI EAST OF LEXINGTON ST
CSJ0114-02-117
Proj IDF 2B24(416)
Work TypeCULVERT & STORM DRAINAGE WORK
 
93117.700.000.0
Work Order09-06-24
Work Began00-00-00
Work Completed
Time Computed09-17-24
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0114-02-113
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.43)
D. I. J. CONSTRUCTION, INC. (7.28)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.76)
TEXAS MATERIALS GROUP, INC. (30.73)
Contract #08243021
Totals1219420.600.000.000.0

CountyLEE
HighwayUS 290
FromNAVARRO
ToCR 226
CSJ0114-07-087
Proj IDC 114-7-87
Work TypeOVERLAY
 
2209194.340.000.0
Work Order09-18-24
Work Began00-00-00
Work Completed
Time Computed10-18-24
Contract Working Days32
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0114-07-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243225
Totals2209194.340.000.000.0

CountyTRAVIS
HighwaySL 212
FromUS 290
ToWILBARGER CREEK
CSJ0114-20-014
Proj IDC 114-20-14
Work TypeOVERLAY
 
799753.90811162.8799.9
Work Order03-21-24
Work Began07-09-24
Work Completed
Time Computed07-09-24
Contract Working Days24
Addl Days Granted0
Working Days Charged21
Percent Time Used87
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-20-014
D. I. J. CONSTRUCTION, INC. (5.70)
TRP CONSTRUCTION GROUP, LLC (2.20)
PRIMATE CONSTRUCTION, LP (2.37)
ROADWAY TRAFFIC CONTROL LLC (2.50)
BROTHERS RDC PAVING, LLC (1.94)
Contract #02243233
Totals799753.9041787.93811162.8799.9

CountyCALDWELL
HighwayFM 20
FromGUADALUPE COUNTY LINE
ToPR 10
CSJ0115-02-019
Proj IDC 115-2-19
Work TypeSEAL COAT
 
9.6082629208.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0115-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243021
Totals2629208.430.000.000.0

CountyLLANO
HighwaySH 29
From0.3 MILES WEST OF RM 2241
To3.8 MILES EAST OF RM 2241
CSJ0150-04-046
Proj IDC 150-4-46
Work TypeSUPER-2 HIGHWAY
 
4.0847398988.998732740.1099.9
Work Order09-20-21
Work Began01-24-22
Work Completed
Time Computed10-20-21
Contract Working Days369
Addl Days Granted15
Working Days Charged384
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0150-04-046
STATEWIDE SAFETY SYSTEMS (0.30)
MPB, INC. (23.77)
D. I. J. CONSTRUCTION, INC. (1.98)
DIIBS SPECIALISTS, LLC (3.56)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.30)
EGGEMEYER LAND CLEARING, LLC (0.78)
INTERSTATE BARRICADES & MARKINGS, INC. (0.35)
LONE STAR EROSION CONTROL (0.55)
Contract #08213023
Totals7398988.9978150.688732740.1099.9

CountyTRAVIS
HighwayUS 183
FromAT RIVERSIDE DR.
To.
CSJ0152-01-089
Proj IDSTP 2025(142)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
855115.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days39
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0152-01-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243027
Totals855115.150.000.000.0

CountyCALDWELL
HighwayUS 183
FromCEMETERY STREET
ToCITY PARK ROAD
CSJ0152-02-071
Proj IDC 152-2-71
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
323325.00173787.0053.7
Work Order05-08-24
Work Began07-10-24
Work Completed
Time Computed06-07-24
Contract Working Days102
Addl Days Granted0
Working Days Charged37
Percent Time Used36
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0152-02-071
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.00)
Contract #04243036
Totals323325.0037750.00173787.0053.7

CountyWILLIAMSON
HighwayUS 79
From0.58 MI EAST OF FM 1460
ToFM 685
CSJ0204-01-074
Proj IDSTP 2024(756)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3597980.302062511.2657.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-05-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days368
Addl Days Granted0
Working Days Charged94
Percent Time Used25
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0204-01-074
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (4.48)
Contract #02243221
Totals3597980.30200032.212062511.2657.3

CountyWILLIAMSON
HighwayUS 79
FromFM 1660
ToFM 3349
CSJ0204-02-036
Proj IDC 204-2-36
Work TypeOVERLAY
 
3840828.304107484.2799.9
Work Order03-14-24
Work Began07-22-24
Work Completed
Time Computed07-22-24
Contract Working Days68
Addl Days Granted0
Working Days Charged37
Percent Time Used54
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0204-02-036
D. I. J. CONSTRUCTION, INC. (5.06)
LONE STAR SITEWORK, LLC (1.92)
SAN ANTONIO SWEEPING SERVICES, INC. (0.26)
STRIPE IT UP, LLC (0.26)
TRP CONSTRUCTION GROUP, LLC (0.16)
TEXAS TRAFFIC AND BARRICADE, LLC (0.21)
Contract #02243218
Totals3840828.30193906.734107484.2799.9

CountyLEE
HighwayUS 77
FromAT ELM CREEK
To.
CSJ0211-04-027
Proj IDBR 2024(835)
Work TypeBRIDGE MAINTENANCE
 
768531.22255719.7633.2
CountyLEE
HighwaySH 21
FromAT WEST YEGUA CREEK
To.
CSJ0473-02-042
Proj IDBR 2024(835)
Work TypeBRIDGE MAINTENANCE
 
513832.720.000.0
Work Order05-16-24
Work Began09-16-24
Work Completed
Time Computed06-15-24
Contract Working Days130
Addl Days Granted0
Working Days Charged30
Percent Time Used23
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0211-04-027
CHEROKEE SERVICES (0.00)
S & S BRIDGE PAINTING, INC. (0.00)
FLASHER EQUIPMENT COMPANY (0.00)
DIIBS SPECIALISTS, LLC (0.00)
Contract #04243225
Totals1282363.94203958.24255719.7619.9

CountyBURNET
HighwayUS 281
FromAT SH 71
To.
CSJ0252-02-063
Proj IDSTP 2023(736)HES
Work TypeTRAFFIC CONTROL DEVICES
 
221866.00292778.4199.9
CountyBASTROP
HighwayFM 812
FromAT SH 21
To.
CSJ1149-02-031
Proj IDSTP 2023(733)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
375658.87395269.8799.9
Work Order06-28-23
Work Began12-02-23
Work Completed
Time Computed10-26-23
Contract Working Days79
Addl Days Granted10
Working Days Charged73
Percent Time Used82
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0252-02-063
LLANO AUGER SERVICE (0.00)
LOZANO CONSTRUCTION COMPANY, INC. (0.00)
FIBERTEL, LLC (0.00)
ROADWAY SPECIALTIES, INC. (0.00)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.00)
Contract #05233244
Totals597524.870.00688048.2899.9

CountyBURNET
HighwayUS 281
From3RD STREET
ToRM 2147 E
CSJ0252-02-064
Proj IDC 252-2-64
Work TypeOVERLAY
 
5701426.305424914.2594.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-21-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted2
Working Days Charged57
Percent Time Used77
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0252-02-064
D. I. J. CONSTRUCTION, INC. (0.00)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.00)
MPB, INC. (0.00)
Contract #02243014
Totals5701426.3068444.655424914.2594.3

CountyBLANCO
HighwayUS 281
From0.05MI S OF RM 962
To0.65 MI S OF RM 962
CSJ0252-03-053
Proj IDSTP 2024(757)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1486872.5650132.843.3
CountyBLANCO
HighwayUS 281
FromBURNET COUNTY LINE
To0.25 MI N OF RM 962
CSJ0252-03-054
Proj IDSTP 2024(757)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9702238.592443199.0425.1
Work Order04-18-24
Work Began00-00-00
Work Completed
Time Computed05-18-24
Contract Working Days254
Addl Days Granted16
Working Days Charged38
Percent Time Used14
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0252-03-053
GREYCO CONSTRUCTION, LLC (0.00)
A K FUQUAY CONSTRUCTION (0.00)
LONE STAR EROSION CONTROL (0.00)
MPB, INC. (0.00)
EGGEMEYER LAND CLEARING, LLC (0.00)
BUYERS BARRICADES AUSTIN, LLC (0.00)
D. I. J. CONSTRUCTION, INC. (0.00)
J. H. ODEN CONTRACTING COMPANY (0.00)
THE LEVY COMPANY, INC. (0.00)
Contract #03243206
Totals11189111.15402550.072493331.8822.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6