Monthly State Let Construction Report For Bryan District As Of Jan 10, 2023 Page 1 Of 4

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON
HighwaySH 6
FromFALLS COUNTY LINE
ToFM 1644 WEST
CSJ0049-06-079
Proj IDNH 2019(977)
Work TypeOVERLAY
 
14.6027687390.678933955.1299.9
Work Order05-14-19
Work Began11-25-19
Work Completed
Time Computed08-12-19
Contract Working Days93
Addl Days Granted15
Working Days Charged107
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-079
AREA WIDE PROTECTIVE, INC. (0.18)
CEN TEX HYDROSEED, INC. (0.18)
FORTSON CONTRACTING, INC. (2.81)
SCR CIVIL CONSTRUCTION, LLC (0.45)
STRIPE-A-ZONE, INC. (0.48)
TRP CONSTRUCTION GROUP, LLC (3.23)
POTTER TRUCKING (0.00)
VELASCO"S TRANSPORTS (0.00)
Contract #04193241
Totals7687390.670.008933955.1299.9

CountyROBERTSON
HighwayUS 190
From0.27 MI NORTH OF CR 226 (ABBOTT RD)
To0.45 MILES S OF CR806 (SADBERRY RD)
CSJ0049-08-065
Proj IDNH 2018(615)
Work TypeRIGHT TURN DECEL / ACCEL LANES
 
12.3277241078.3211187549.7499.9
CountyROBERTSON
HighwayUS 190
From0.45 MI S OF CR 806 (SADBERRY RD)
ToOSR (COUNTY LINE)
CSJ0049-08-067
Proj IDC 49-8-67
Work TypeMILLING AND HMA OVERLAY
 
2.4651046311.602077937.8899.9
Work Order07-31-18
Work Began10-22-18
Work Completed
Time Computed08-30-18
Contract Working Days298
Addl Days Granted75
Working Days Charged382
Percent Time Used102
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-065
AREA WIDE PROTECTIVE, INC. (0.33)
CHEROKEE SERVICES (0.36)
COMEN ENTERPRISE LLC (1.41)
D. I. J. CONSTRUCTION, INC. (2.58)
J. H. ODEN CONTRACTING COMPANY (0.22)
STRIPE-A-ZONE, INC. (0.32)
NIXON ENGINEERING (0.00)
Contract #06183239
Totals8287389.92510981.5313265487.6299.9

CountyROBERTSON ETC
HighwayUS 190 ETC
FromFM 391
ToBRADFORD STREET
CSJ0049-08-074
Proj IDSTP 2022(856)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4264422.0347194.001.1
Work Order09-20-22
Work Began00-00-00
Work Completed
Time Computed12-19-22
Contract Working Days211
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-074
ALLSTATE SIGNAL & CONSTRUCTION, LLC (26.88)
CEN TEX HYDROSEED, INC. (1.93)
STRIPE LINES, INC. (1.59)
Contract #08223221
Totals4264422.034332.0047194.001.1

CountyBRAZOS
HighwayBS 6-R
From15TH STREET
ToFM 158
CSJ0049-09-076
Proj IDF 2022(857)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.754284960.000.000.0
CountyBRAZOS
HighwayBS 6-R
FromSH 21
ToFM 158
CSJ0049-09-083
Proj IDSTP 2022(858)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.977730947.270.000.0
CountyBRAZOS
HighwayBS 6-R
FromFM 158
ToFM 60
CSJ0050-01-083
Proj IDF 2022(857)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
4.1121.250.000.0
CountyBRAZOS
HighwayBS 6-R
FromFM 158
ToFM 60
CSJ0050-01-088
Proj IDSTP 2022(858)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.1254220936.540.000.0
Work Order09-21-22
Work Began00-00-00
Work Completed
Time Computed12-20-22
Contract Working Days119
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAZOS PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223008
Totals5236845.060.000.000.0

CountyBRAZOS
HighwayBS 6-R
FromOLD HEARNE ROAD
To15TH STREET
CSJ0049-09-087
Proj IDC 49-9-87
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
4137992.911607925.9638.8
Work Order01-20-22
Work Began05-13-22
Work Completed
Time Computed04-20-22
Contract Working Days151
Addl Days Granted0
Working Days Charged135
Percent Time Used89
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-087
BROCK CONSTRUCTION, LLC (0.24)
CEN TEX HYDROSEED, INC. (2.20)
CITYLYNX, INC. (24.49)
ELLIOTT CONSTRUCTION, LLC (0.00)
STRIPE LINES, INC. (2.58)
LANDSHARK HYDROEXCAVATION SERVICES, INC. (0.16)
HORSESHOE CONSTRUCTION, INC. (2.08)
JOHN WRIGHT CONSTRUCTION (0.65)
Contract #12213210
Totals4137992.91245551.401607925.9638.8

CountyBRAZOS ETC
HighwayUS 190 ETC
From0.43 MI S OF FM 2818
To0.61 MI S OF FM 2818
CSJ0049-09-089
Proj IDSTP 2022(860)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5909647.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-22
Work Began00-00-00
Work Completed
Time Computed12-19-22
Contract Working Days178
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-089
CEN TEX HYDROSEED, INC. (1.96)
BROCK CONSTRUCTION, LLC (0.61)
J & M CONTRACTING, COMPANY (12.64)
MILSTEAD HIGHWAY SERVICES, LLC (1.94)
PINNACLE GRINDING AND GROOVING LLC (0.17)
STRIPE LINES, INC. (1.92)
Contract #08223216
Totals5909647.300.000.000.0

CountyBRAZOS
HighwayUS 190
FromSH OSR
ToFM 2818
CSJ0049-09-090
Proj IDSTP 2022(235)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
490974.56488404.4099.4
CountyBRAZOS
HighwaySH 6
FromFM 159
ToGRIMES COUNTY LINE
CSJ0050-02-119
Proj IDSTP 2022(235)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.001957152.34931058.5097.2
Work Order02-15-22
Work Began06-13-22
Work Completed
Time Computed05-16-22
Contract Working Days111
Addl Days Granted0
Working Days Charged98
Percent Time Used88
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-090
FOX CONTRACTING KY, INC. (16.53)
LONESTAR TRAFFIC SAFETY, LLC (0.59)
ODUM SERVICES, LLC (1.04)
Contract #01223016
Totals1448126.9018987.691419462.9098.0

CountyBRAZOS ETC
HighwayBS 6-R ETC
FromSH 6 N
ToSH 21
CSJ0049-09-094
Proj IDF 2023(216)
Work TypeTRAFFIC CONTROL DEVICES
 
4.8272897017.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-05-22
Work Began00-00-00
Work Completed
Time Computed01-04-23
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09223012
Totals2897017.810.000.000.0

CountyBRAZOS ETC
HighwaySH 6 ETC
FromAT DRAW ON EFR AND WFR
To.
CSJ0049-12-105
Proj IDBR 2020(085)
Work TypeBRIDGE MAINTENANCE
 
1.4911471134.301700154.8499.9
Work Order11-20-19
Work Began03-10-20
Work Completed
Time Computed02-18-20
Contract Working Days152
Addl Days Granted29
Working Days Charged159
Percent Time Used87
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-105
FLASHER EQUIPMENT COMPANY (1.36)
BLACKTOP INDUSTRIES LLC (18.12)
DUSTROL, INC. (0.46)
MOBILE ENTERPRISES, INC. (5.93)
STRIPE LINES, INC. (0.00)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.93)
WILLOW CITY SIGN & RAIL, INC. (1.13)
Contract #10193020
Totals1471134.300.001700154.8499.9

CountyROBERTSON ETC
HighwayFM 46 ETC
FromFALLS COUNTY LINE
ToSH 14
CSJ0049-14-014
Proj IDF 2021(768)
Work TypeTRAFFIC CONTROL DEVICES
 
16.2762552415.922076856.3981.3
Work Order06-22-22
Work Began08-25-22
Work Completed
Time Computed07-22-22
Contract Working Days65
Addl Days Granted0
Working Days Charged66
Percent Time Used101
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04223014
Totals2552415.92658.952076856.3981.3

CountyROBERTSON ETC
HighwaySH 14 ETC
FromFM 46
ToSH 6
CSJ0049-15-014
Proj IDF 2022(080)
Work TypeSEAL COAT
 
4.82714704110.3513973211.6795.0
Work Order12-30-21
Work Began04-18-22
Work Completed
Time Computed04-18-22
Contract Working Days122
Addl Days Granted0
Working Days Charged101
Percent Time Used82
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-15-014
RED SIXTEEN CONSTRUCTION, INC (0.86)
INTERSTATE BARRICADES & MARKINGS, INC. (1.27)
MEMCO STAFFING, LLC (0.06)
Contract #10213001
Totals14704110.35162586.1013973211.6795.0

CountyBRAZOS ETC
HighwayBS 6-R ETC
FromAT WALTON DRIVE/NEW MAIN DRIVE
To.WA
CSJ0050-01-087
Proj IDSTP 2021(024)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.6001136623.601153931.2099.9
Work Order11-19-20
Work Began04-20-21
Work Completed
Time Computed02-17-21
Contract Working Days158
Addl Days Granted0
Working Days Charged167
Percent Time Used105
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-087
AREA WIDE PROTECTIVE, INC. (1.66)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (3.47)
LINEAR TRAFFIC MARKINGS LLC (0.48)
PALOMARES CONSTRUCTION, INC. (1.40)
A. L. HELMCAMP, INC. (8.13)
Contract #10203019
Totals1136623.6070117.501153931.2099.9

CountyGRIMES
HighwaySH 6
FromAT FM 2
To.
CSJ0050-03-096
Proj IDSTP 2021(770)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.40018052622.005818607.8632.2
Work Order09-16-21
Work Began11-01-21
Work Completed
Time Computed11-01-21
Contract Working Days579
Addl Days Granted0
Working Days Charged152
Percent Time Used26
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-096
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.47)
DIIBS SPECIALISTS, LLC (0.86)
JB PINNACLE GROUP, LLC (0.99)
PINNACLE GRINDING AND GROOVING LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.23)
D. I. J. CONSTRUCTION, INC. (1.08)
LONESTAR TRAFFIC SAFETY, LLC (0.30)
TEXAS STERLING CONSTRUCTION CO. (3.19)
TORO BRAVO CONSTRUCTION, LLC (0.32)
Contract #08213005
Totals18052622.00304810.975818607.8632.2

CountyGRIMES
HighwaySH 6
FromBRAZOS COUNTY LINE
ToWALLER COUNTY LINE
CSJ0050-03-100
Proj IDC 50-3-100
Work TypeOVERLAY
 
14.3835798125.916601301.2299.9
Work Order08-17-18
Work Began08-12-19
Work Completed
Time Computed11-15-18
Contract Working Days72
Addl Days Granted54
Working Days Charged159
Percent Time Used126
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-100
AREA WIDE PROTECTIVE, INC. (0.12)
BATTERSON,LLP (3.03)
CPAVE, INC. (3.60)
DUSTROL, INC. (4.21)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.35)
Contract #07183040
Totals5798125.918228.726601301.2299.9

CountyWALKER ETC
HighwaySH 19 ETC
From0.4 MI N OF SH 30
ToIH 45
CSJ0109-09-066
Proj IDF 2023(144)
Work TypeSEAL COAT
 
23496228.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-05-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days135
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-09-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10223004
Totals23496228.970.000.000.0

CountyWALKER
HighwaySH 75
FromAT 2793
To.
CSJ0110-01-049
Proj IDF 2021(717)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.200946421.73400396.7842.3
Work Order09-29-21
Work Began12-16-21
Work Completed
Time Computed12-16-21
Contract Working Days47
Addl Days Granted0
Working Days Charged37
Percent Time Used78
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0110-01-049
STRIPE LINES, INC. (5.65)
CEN TEX HYDROSEED, INC. (2.93)
COLD CREEK CONSTRUCTION, LTD (3.92)
J & M CONTRACTING, COMPANY (4.05)
AREA WIDE PROTECTIVE, INC. (1.90)
STRIPE-A-ZONE, LLC (1.32)
Contract #07213042
Totals946421.731725.47400396.7842.3

CountyWASHINGTON
HighwayBU 290F
FromBS 36-J
ToMARKET STREET
CSJ0114-09-077
Proj IDSTP 2B20(105)
Work TypeOVERLAY
 
2.6392697457.952967560.2299.9
Work Order11-19-20
Work Began02-08-21
Work Completed
Time Computed02-08-21
Contract Working Days108
Addl Days Granted54
Working Days Charged146
Percent Time Used90
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-077
CITYLYNX, INC. (3.60)
CEN TEX HYDROSEED, INC. (0.09)
A BROTHERS MILLING, LLC (5.83)
STRIPE LINES, INC. (3.43)
WILLOW CITY SIGN & RAIL, INC. (1.69)
Contract #08203030
Totals2697457.950.002967560.2299.9

CountyWASHINGTON ETC
HighwayUS 290 ETC
From0.1 MI W OF FM 390
To0.1 MI E OF FM 2679
CSJ0114-09-089
Proj IDF 2021(776)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.6001254827.80279514.8522.2
Work Order09-21-21
Work Began04-26-22
Work Completed
Time Computed12-20-21
Contract Working Days199
Addl Days Granted0
Working Days Charged161
Percent Time Used80
Contractor(s)
CITYLYNX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-089
SEMPER STRIPING LLC (2.75)
Contract #08213250
Totals1254827.8029407.25279514.8522.2

CountyWASHINGTON ETC
HighwayUS 290 ETC
From0.1 MI W OF FM 1948
To0.1 MI E OF FM 1948
CSJ0114-09-090
Proj IDSTP 2022(622)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
286956.505558.001.9
Work Order07-11-22
Work Began00-00-00
Work Completed
Time Computed10-09-22
Contract Working Days118
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-090
SEMPER STRIPING LLC (5.23)
Contract #06223039
Totals286956.505558.005558.001.9

CountyBURLESON
HighwaySH 21
FromAT FM 2000
To.
CSJ0116-03-066
Proj IDF 2022(488)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
2941282.432826423.4596.0
Work Order06-09-22
Work Began07-08-22
Work Completed
Time Computed07-08-22
Contract Working Days133
Addl Days Granted0
Working Days Charged83
Percent Time Used62
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0116-03-066
ROAD SOLUTIONS L.L.C. (3.61)
STRIPE LINES, INC. (2.35)
J & M CONTRACTING, COMPANY (15.76)
BROCK CONSTRUCTION, LLC (0.00)
J. H. ODEN CONTRACTING COMPANY (2.50)
PINNACLE GRINDING AND GROOVING LLC (0.00)
Contract #05223225
Totals2941282.4360827.602826423.4596.0

page 1 | page 2 | page 3 | page 4