|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | ROBERTSON |
Highway | US 79 |
From | 0.1 MI S OF 5TH STREET |
To | 0.1 MI N OF 5TH STREET |
CSJ | 0049-07-069 |
Proj ID | STP 2024(610)VRU |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 467833.55 | | 183015.25 | 39.1 |
County | ROBERTSON |
Highway | US 190 |
From | 0.3 MI N OF SAN GABRIEL ACCESS DRIVEWAY |
To | 0.4 MI S OF SAN GABRIEL ACCESS DRIVEWAY |
CSJ | 0049-08-077 |
Proj ID | F 2024(611) |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 435233.75 | | 169167.40 | 38.8 |
Work Order | 03-21-24 |
Work Began | 04-11-24 |
Work Completed | |
Time Computed | 04-11-24 |
Contract Working Days | 73 |
Addl Days Granted | 0 |
Working Days Charged | 61 |
Percent Time Used | 83 |
Contractor(s) |
ELECNOR BELCO ELECTRIC, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-07-069 BUYERS BARRICADES, INC. (1.52) PAVEMENT MARKINGS INC. (3.32) ACCURATE DRILLING & CONSTRUCTION, INCORPORATED (1.10)
|
Contract # | 01243036 |
| Totals | 903067.30 | 16998.40 | 352182.65 | 38.9 |
|
County | ROBERTSON ETC |
Highway | US 190 ETC |
From | FM 391 |
To | BRADFORD STREET |
CSJ | 0049-08-074 |
Proj ID | STP 2022(856)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 4264422.03 | | 4540993.63 | 99.9 |
Work Order | 09-20-22 |
Work Began | 01-19-23 |
Work Completed | |
Time Computed | 12-19-22 |
Contract Working Days | 211 |
Addl Days Granted | 0 |
Working Days Charged | 207 |
Percent Time Used | 98 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-074 ALLSTATE SIGNAL & CONSTRUCTION, LLC (26.88) CEN TEX HYDROSEED, INC. (1.93) STRIPE LINES, INC. (1.59)
|
Contract # | 08223221 |
| Totals | 4264422.03 | 2855.00 | 4540993.63 | 99.9 |
|
County | ROBERTSON |
Highway | US 190 |
From | 0.15 MI N OF SPRING OAKS DR. |
To | 0.1 MI S OF SADBERRY |
CSJ | 0049-08-076 |
Proj ID | STP 2B24(087)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 5.654 | 2487590.72 | | 808348.67 | 32.4 |
Work Order | 06-26-24 |
Work Began | 10-03-24 |
Work Completed | |
Time Computed | 09-24-24 |
Contract Working Days | 106 |
Addl Days Granted | 0 |
Working Days Charged | 10 |
Percent Time Used | 9 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-076 BROCK CONSTRUCTION, LLC (2.22) THIRD COAST SERVICES LLC (1.48) DUSTIN ALLEN, INC. (0.93) D. I. J. CONSTRUCTION, INC. (4.26) HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.50) MURRAY CONSTRUCTION (0.29) CEN TEX HYDROSEED, INC. (3.08)
|
Contract # | 05243028 |
| Totals | 2487590.72 | 808348.67 | 808348.67 | 32.4 |
|
County | ROBERTSON |
Highway | US 190 |
From | 1 MI N OF OSR |
To | OSR |
CSJ | 0049-08-078 |
Proj ID | C 49-8-78 |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| | 1275456.91 | | 0.00 | 0.0 |
Work Order | 08-02-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-31-24 |
Contract Working Days | 118 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
BRAZOS PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-078 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06243243 |
| Totals | 1275456.91 | 0.00 | 0.00 | 0.0 |
|
County | BRAZOS |
Highway | BS 6-R |
From | OLD HEARNE ROAD |
To | 15TH STREET |
CSJ | 0049-09-087 |
Proj ID | C 49-9-87 |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| | 4137992.91 | | 4212931.25 | 99.9 |
Work Order | 01-20-22 |
Work Began | 05-13-22 |
Work Completed | |
Time Computed | 04-20-22 |
Contract Working Days | 151 |
Addl Days Granted | 0 |
Working Days Charged | 230 |
Percent Time Used | 152 |
Contractor(s) |
LARRY YOUNG PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-087 BROCK CONSTRUCTION, LLC (0.24) CEN TEX HYDROSEED, INC. (2.20) CITYLYNX, INC. (24.49) ELLIOTT CONSTRUCTION, LLC (0.00) STRIPE LINES, INC. (2.58) LANDSHARK HYDROEXCAVATION SERVICES, INC. (0.16) HORSESHOE CONSTRUCTION, INC. (2.08) JOHN WRIGHT CONSTRUCTION (0.65) SARVICUS LLC (25.73) BATTEN DRILLING, INC. (0.82)
|
Contract # | 12213210 |
| Totals | 4137992.91 | 50934.00 | 4212931.25 | 99.9 |
|
County | BRAZOS ETC |
Highway | US 190 ETC |
From | 0.43 MI S OF FM 2818 |
To | 0.61 MI S OF FM 2818 |
CSJ | 0049-09-089 |
Proj ID | STP 2022(860)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 5909647.30 | | 6470509.11 | 99.9 |
Work Order | 09-20-22 |
Work Began | 01-17-23 |
Work Completed | |
Time Computed | 12-19-22 |
Contract Working Days | 178 |
Addl Days Granted | 33 |
Working Days Charged | 192 |
Percent Time Used | 90 |
Contractor(s) |
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-089 CEN TEX HYDROSEED, INC. (1.96) BROCK CONSTRUCTION, LLC (0.61) J & M CONTRACTING, COMPANY (12.64) MILSTEAD HIGHWAY SERVICES, LLC (1.94) PINNACLE GRINDING AND GROOVING LLC (0.17) STRIPE LINES, INC. (1.92) PROFESSIONAL TRAFFIC CONTROL LLC (0.17) THIRD COAST SERVICES LLC (0.13) ODUM SERVICES, LLC (1.53)
|
Contract # | 08223216 |
| Totals | 5909647.30 | 0.00 | 6470509.11 | 99.9 |
|
County | BRAZOS ETC |
Highway | US 190 ETC |
From | ON US 190 WFR FROM OSR |
To | BS 6R |
CSJ | 0049-09-095 |
Proj ID | F 2024(097) |
Work Type | SEAL COAT |
|
| 3.863 | 24509977.03 | | 22061496.85 | 90.0 |
Work Order | 11-16-23 |
Work Began | 04-22-24 |
Work Completed | |
Time Computed | 04-22-24 |
Contract Working Days | 135 |
Addl Days Granted | 0 |
Working Days Charged | 98 |
Percent Time Used | 72 |
Contractor(s) |
D. I. J. CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-095 INTERSTATE BARRICADES & MARKINGS, INC. (1.83) RED SIXTEEN CONSTRUCTION, INC (1.71) MEMCO STAFFING, LLC (0.00)
|
Contract # | 10233005 |
| Totals | 24509977.03 | 123434.00 | 22061496.85 | 90.0 |
|
County | BRAZOS |
Highway | US 190 ETC |
From | ON US 190 WFR |
To | AT ELM FORK CREEK |
CSJ | 0049-09-096 |
Proj ID | BR 2023(632) |
Work Type | BRIDGE MAINTENANCE |
|
| | 1888555.00 | | 1823297.03 | 96.7 |
Work Order | 06-14-23 |
Work Began | 07-18-23 |
Work Completed | |
Time Computed | 07-14-23 |
Contract Working Days | 170 |
Addl Days Granted | 0 |
Working Days Charged | 175 |
Percent Time Used | 102 |
Contractor(s) |
MB WESTERN INDUSTRIAL CONTRACTING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-096 DIIBS SPECIALISTS, LLC (7.09) MACIAS SPECIALTY CONTRACTING LLC (10.76) BROCK CONSTRUCTION, LLC (1.02) CHEROKEE SERVICES (3.18) S & S BRIDGE PAINTING, INC. (18.26) LONESTAR TRAFFIC SAFETY, LLC (0.74) AWP SAFETY (0.10) SAPO ENGINEERING CONSULTANTS, LLC (2.73) STRUCTURAL INTEGRITY GROUP LLC (1.49) HIGHWAY 1 LLC (2.19) CEN TEX HYDROSEED, INC. (0.12)
|
Contract # | 05233232 |
| Totals | 1888555.00 | 1813.32 | 1823297.03 | 96.7 |
|
County | BRAZOS ETC |
Highway | US 190 ETC |
From | ON US 190 WFR FROM OSR |
To | BS 6R |
CSJ | 0049-09-099 |
Proj ID | F 2025(075) |
Work Type | TRAFFIC CONTROL DEVICES |
|
| 3.863 | 4187005.86 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-22-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 100 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
D. I. J. CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-099 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09243214 |
| Totals | 4187005.86 | 0.00 | 0.00 | 0.0 |
|
County | BRAZOS |
Highway | US 190 |
From | FM 2818 |
To | 0.55 MI S OF FM 2818 |
CSJ | 0049-09-101 |
Proj ID | STP 2B24(359)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 96135.71 | | 0.00 | 0.0 |
County | BRAZOS |
Highway | US 190 |
From | 0.55 MI S OF FM 2818 |
To | SH 21 |
CSJ | 0049-12-150 |
Proj ID | STP 2B24(359)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 924669.54 | | 0.00 | 0.0 |
County | BRAZOS |
Highway | SH 21 |
From | 3.6 MI W OF FM 2818 |
To | 1.7 MI W OF FM 2818 |
CSJ | 0116-04-114 |
Proj ID | STP 2B24(359)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 327235.75 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-18-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 44 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MASSANA CONSTRUCTION INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-101 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08243223 |
| Totals | 1348041.00 | 0.00 | 0.00 | 0.0 |
|
County | GRIMES |
Highway | SH 6 |
From | AT FM 2 |
To | . |
CSJ | 0050-03-096 |
Proj ID | STP 2021(770)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 1.400 | 18052622.00 | | 15535619.21 | 85.4 |
Work Order | 09-16-21 |
Work Began | 11-01-21 |
Work Completed | |
Time Computed | 11-01-21 |
Contract Working Days | 579 |
Addl Days Granted | 0 |
Working Days Charged | 514 |
Percent Time Used | 88 |
Contractor(s) |
LARRY YOUNG PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-096 ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.47) DIIBS SPECIALISTS, LLC (0.86) JB PINNACLE GROUP, LLC (0.99) PINNACLE GRINDING AND GROOVING LLC (0.16) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.23) D. I. J. CONSTRUCTION, INC. (1.08) LONESTAR TRAFFIC SAFETY, LLC (0.30) TEXAS STERLING CONSTRUCTION CO. (3.19) TORO BRAVO CONSTRUCTION, LLC (0.32) BATTEN DRILLING, INC. (0.92) TOM-MAC, INC. (0.73) WATERS CONSTRUCTION COMPANY, INC. (0.83) SCOTT DERR PAINTING CO, LLC (0.01)
|
Contract # | 08213005 |
| Totals | 18052622.00 | 455659.55 | 15535619.21 | 85.4 |
|
County | GRIMES |
Highway | SH 6 |
From | BRAZOS COUNTY LINE |
To | WALLER COUNTY LINE |
CSJ | 0050-03-100 |
Proj ID | C 50-3-100 |
Work Type | OVERLAY |
|
| 14.383 | 5798125.91 | | 7521268.08 | 99.9 |
Work Order | 08-17-18 |
Work Began | 08-12-19 |
Work Completed | |
Time Computed | 11-15-18 |
Contract Working Days | 72 |
Addl Days Granted | 95 |
Working Days Charged | 176 |
Percent Time Used | 105 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-100 AREA WIDE PROTECTIVE, INC. (0.12) BATTERSON,LLP (3.03) CPAVE, INC. (3.60) DUSTROL, INC. (4.21) SURFACE PREPARATION TECHNOLOGIES, LLC (0.35) CEN TEX HYDROSEED, INC. (0.49)
|
Contract # | 07183040 |
| Totals | 5798125.91 | 18798.84 | 7521268.08 | 99.9 |
|
County | GRIMES |
Highway | SH 6 |
From | 0.3 MI N OF FM 2988 |
To | 0.1 MI S OF FM 2988 |
CSJ | 0050-03-109 |
Proj ID | STP 2B23(029)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 620873.55 | | 525367.48 | 84.6 |
County | GRIMES |
Highway | FM 149 |
From | SH 90 |
To | 0.2 MI E OF FM 2562 |
CSJ | 0720-01-044 |
Proj ID | STP 2B23(029)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 4951395.50 | | 4037843.82 | 81.5 |
Work Order | 09-07-23 |
Work Began | 11-08-23 |
Work Completed | |
Time Computed | 11-08-23 |
Contract Working Days | 232 |
Addl Days Granted | 0 |
Working Days Charged | 203 |
Percent Time Used | 87 |
Contractor(s) |
LARRY YOUNG PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-109 CEN TEX HYDROSEED, INC. (2.10) DIIBS SPECIALISTS, LLC (1.10) HIGHWAY 1 LLC (2.39) MURRAY CONSTRUCTION (1.04) PROFESSIONAL TRAFFIC CONTROL LLC (0.12) WATERS CONSTRUCTION COMPANY, INC. (2.03) JB PINNACLE GROUP, LLC (0.00)
|
Contract # | 08233231 |
| Totals | 5572269.05 | 307586.39 | 4563211.30 | 81.8 |
|
County | GRIMES |
Highway | SH 6 ETC |
From | ON SH 6 SB |
To | AT BS 6S NB |
CSJ | 0050-03-114 |
Proj ID | BR 2B23(226) |
Work Type | BRIDGE MAINTENANCE |
|
| | 2245311.70 | | 2131444.61 | 94.9 |
Work Order | 10-23-23 |
Work Began | 01-17-24 |
Work Completed | |
Time Computed | 11-22-23 |
Contract Working Days | 164 |
Addl Days Granted | 0 |
Working Days Charged | 164 |
Percent Time Used | 100 |
Contractor(s) |
SCR CIVIL CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-114 S & S BRIDGE PAINTING, INC. (6.68) JB PINNACLE GROUP, LLC (11.09) JE CASEY, LLC (3.24) HIGHWAY 1 LLC (3.10) DUSTROL, INC. (1.00) J. H. ODEN CONTRACTING COMPANY (2.07) NELSON INDUSTRIAL SERVICES, INC. (1.20) LONESTAR TRAFFIC SAFETY, LLC (1.13)
|
Contract # | 09233018 |
| Totals | 2245311.70 | 312665.80 | 2131444.61 | 94.9 |
|
County | GRIMES ETC |
Highway | BS 6-S ETC |
From | SH 6 N |
To | SH 6 S |
CSJ | 0050-11-023 |
Proj ID | F 2025(135) |
Work Type | SEAL COAT |
|
| | 28059691.76 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 134 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
D. I. J. CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0050-11-023 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10243006 |
| Totals | 28059691.76 | 0.00 | 0.00 | 0.0 |
|
County | FREESTONE |
Highway | US 84 |
From | 0.2 MI W OF FM 1366 |
To | 0.2 MI E OF FM 1366 |
CSJ | 0057-02-038 |
Proj ID | STP 2B24(526)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 221187.30 | | 0.00 | 0.0 |
County | MADISON |
Highway | SH 21 |
From | 0.1 MI W OF OSR |
To | FM 2548 |
CSJ | 0117-05-059 |
Proj ID | STP 2B24(386)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 717145.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-18-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 41 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
LARRY YOUNG PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0057-02-038 MURRAY CONSTRUCTION (5.14) AWP SAFETY (1.27) CEN TEX HYDROSEED, INC. (0.98) HIGHWAY 1 LLC (4.70)
|
Contract # | 08243028 |
| Totals | 938332.30 | 0.00 | 0.00 | 0.0 |
|
County | WALKER ETC |
Highway | SH 19 ETC |
From | 0.4 MI N OF SH 30 |
To | IH 45 |
CSJ | 0109-09-068 |
Proj ID | F 2B23(022) |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 4204817.53 | | 3956759.30 | 94.1 |
Work Order | 09-14-23 |
Work Began | 01-09-24 |
Work Completed | |
Time Computed | 10-14-23 |
Contract Working Days | 100 |
Addl Days Granted | 0 |
Working Days Charged | 58 |
Percent Time Used | 58 |
Contractor(s) |
D. I. J. CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0109-09-068 SURFACE PREPARATION TECHNOLOGIES, LLC (1.41)
|
Contract # | 08233225 |
| Totals | 4204817.53 | 0.00 | 3956759.30 | 94.1 |
|
County | WALKER |
Highway | SH 75 |
From | AT 2793 |
To | . |
CSJ | 0110-01-049 |
Proj ID | F 2021(717) |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| 0.200 | 946421.73 | | 1253819.72 | 99.9 |
Work Order | 09-29-21 |
Work Began | 12-16-21 |
Work Completed | |
Time Computed | 12-16-21 |
Contract Working Days | 47 |
Addl Days Granted | 8 |
Working Days Charged | 100 |
Percent Time Used | 181 |
Contractor(s) |
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0110-01-049 STRIPE LINES, INC. (5.65) CEN TEX HYDROSEED, INC. (2.93) COLD CREEK CONSTRUCTION, LTD (3.92) J & M CONTRACTING, COMPANY (4.05) AREA WIDE PROTECTIVE, INC. (1.90) STRIPE-A-ZONE, LLC (1.32)
|
Contract # | 07213042 |
| Totals | 946421.73 | 0.00 | 1253819.72 | 99.9 |
|
County | WASHINGTON ETC |
Highway | US 290 ETC |
From | 0.1 MI W OF FM 390 |
To | 0.1 MI E OF FM 2679 |
CSJ | 0114-09-089 |
Proj ID | F 2021(776) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 2.600 | 1254827.80 | | 1250521.21 | 99.6 |
Work Order | 09-21-21 |
Work Began | 04-26-22 |
Work Completed | |
Time Computed | 12-20-21 |
Contract Working Days | 199 |
Addl Days Granted | 45 |
Working Days Charged | 241 |
Percent Time Used | 98 |
Contractor(s) |
CITYLYNX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-089 SEMPER STRIPING LLC (2.75)
|
Contract # | 08213250 |
| Totals | 1254827.80 | 14147.00 | 1250521.21 | 99.6 |
|
County | WASHINGTON ETC |
Highway | US 290 ETC |
From | 0.1 MI W OF FM 1948 |
To | 0.1 MI E OF FM 1948 |
CSJ | 0114-09-090 |
Proj ID | STP 2022(622)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 286956.50 | | 288478.32 | 99.9 |
Work Order | 07-11-22 |
Work Began | 06-15-23 |
Work Completed | |
Time Computed | 10-09-22 |
Contract Working Days | 118 |
Addl Days Granted | 0 |
Working Days Charged | 112 |
Percent Time Used | 94 |
Contractor(s) |
THIRD COAST SERVICES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-090 SEMPER STRIPING LLC (5.23) HIGHWAY 1 LLC (5.27)
|
Contract # | 06223039 |
| Totals | 286956.50 | 0.00 | 288478.32 | 99.9 |
|