Monthly State Let Construction Report For Bryan District As Of Jul 13, 2021 Page 1 Of 3

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON
HighwaySH 6
FromFALLS COUNTY LINE
ToFM 1644 WEST
CSJ0049-06-079
Proj IDNH 2019(977)
Work TypeOVERLAY
 
14.6027687390.678496868.0899.9
Work Order05-14-19
Work Began11-25-19
Work Completed
Time Computed08-12-19
Contract Working Days93
Addl Days Granted5
Working Days Charged107
Percent Time Used109
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-079
AREA WIDE PROTECTIVE, INC. (0.18)
CEN TEX HYDROSEED, INC. (0.18)
FORTSON CONTRACTING, INC. (2.81)
SCR CIVIL CONSTRUCTION, LLC (0.45)
STRIPE-A-ZONE, INC. (0.48)
TRP CONSTRUCTION GROUP, LLC (3.23)
POTTER TRUCKING (0.00)
VELASCO"S TRANSPORTS (0.00)
Contract #04193241
Totals7687390.670.008496868.0899.9

CountyROBERTSON
HighwaySH 6
FromFALLS COUNTY LINE
To1.9 MILES SOUTH OF FM 1644
CSJ0049-06-081
Proj IDC 49-6-81
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4499882.693965614.2788.1
Work Order09-16-20
Work Began02-08-21
Work Completed
Time Computed12-15-20
Contract Working Days213
Addl Days Granted0
Working Days Charged78
Percent Time Used36
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-081
FOX CONTRACTING KY, INC. (0.00)
CEN TEX HYDROSEED, INC. (0.00)
A TOUCH OF CONSTRUCTION, LLC (0.00)
Contract #08203219
Totals4499882.69419035.703965614.2788.1

CountyROBERTSON
HighwayUS 190
From0.27 MI NORTH OF CR 226 (ABBOTT RD)
To0.45 MILES S OF CR806 (SADBERRY RD)
CSJ0049-08-065
Proj IDNH 2018(615)
Work TypeRIGHT TURN DECEL / ACCEL LANES
 
12.3277241078.3210156801.2999.9
CountyROBERTSON
HighwayUS 190
From0.45 MI S OF CR 806 (SADBERRY RD)
ToOSR (COUNTY LINE)
CSJ0049-08-067
Proj IDC 49-8-67
Work TypeMILLING AND HMA OVERLAY
 
2.4651046311.60661308.2263.2
Work Order07-31-18
Work Began10-22-18
Work Completed
Time Computed08-30-18
Contract Working Days298
Addl Days Granted50
Working Days Charged346
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-065
AREA WIDE PROTECTIVE, INC. (0.33)
CHEROKEE SERVICES (0.36)
COMEN ENTERPRISE LLC (1.41)
D. I. J. CONSTRUCTION, INC. (2.58)
J. H. ODEN CONTRACTING COMPANY (0.22)
STRIPE-A-ZONE, INC. (0.32)
NIXON ENGINEERING (0.00)
Contract #06183239
Totals8287389.92585568.7710818109.5199.9

CountyBRAZOS
HighwaySH 6
FromSH 21
ToFM 158
CSJ0049-12-096
Proj IDNH 1502(234)
Work TypeUPGRADE FREEWAY RAMPS
 
2.4597542870.378242538.5299.9
CountyZERO COUNTIES
Highway
From
To
CSJ0049-12-111
Proj ID
Work Type
 
0.00726261.700.0
Work Order08-20-15
Work Began02-29-16
Work Completed
Time Computed02-17-16
Contract Working Days308
Addl Days Granted145
Working Days Charged449
Percent Time Used99
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-096
ALLSTATE SIGNAL & CONSTRUCTION, LLC (4.25)
A BROTHERS MILLING, LLC (1.71)
CEN TEX HYDROSEED, INC. (4.03)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.58)
WILLOW CITY SIGN & RAIL, INC. (4.34)
COWBELL TRAFFIC SERVICES, INC. (0.16)
BEAR CREEK CONSTRUCTION, LLC (0.37)
AREA WIDE PROTECTIVE, INC. (0.53)
AARON CONCRETE CONTRACTORS, L.P. (0.61)
WEST TEXAS ROCK RESOURCES, LLC (0.03)
SCR CIVIL CONSTRUCTION, LLC (0.00)
Contract #06153011
Totals7542870.370.008968800.2299.9

CountyBRAZOS ETC
HighwaySH 6 ETC
FromAT DRAW ON EFR AND WFR
To.
CSJ0049-12-105
Proj IDBR 2020(085)
Work TypeBRIDGE MAINTENANCE
 
1.4911471134.301386572.6694.2
Work Order11-20-19
Work Began03-10-20
Work Completed
Time Computed02-18-20
Contract Working Days152
Addl Days Granted13
Working Days Charged115
Percent Time Used69
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-105
FLASHER EQUIPMENT COMPANY (1.36)
BLACKTOP INDUSTRIES LLC (18.12)
DUSTROL, INC. (0.46)
MOBILE ENTERPRISES, INC. (5.93)
STRIPE LINES, INC. (0.00)
Contract #10193020
Totals1471134.30625.151386572.6694.2

CountyBRAZOS
HighwaySH 6
FromOLD RELIANCE ROAD
ToFM 158 (BOONVILLE ROAD)
CSJ0049-12-115
Proj IDSTP 2019(461)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.4001105702.151144606.1399.9
Work Order10-09-19
Work Began12-06-19
Work Completed
Time Computed11-08-19
Contract Working Days126
Addl Days Granted0
Working Days Charged144
Percent Time Used114
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-115
CEN TEX HYDROSEED, INC. (3.37)
GLENN FUQUA, INC. (5.38)
AREA WIDE PROTECTIVE, INC. (1.12)
STEEL EFFECTS (0.00)
LONE STAR PRODUCTS (WICHITA FALLS) (0.00)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.83)
BRITTEN HYDROSEEDING (0.37)
Contract #08193032
Totals1105702.150.001144606.1399.9

CountyROBERTSON
HighwayFM 46
FromFALLS CO LINE
ToSH 14
CSJ0049-14-011
Proj IDSTP 1702(019)HESG
Work TypePROFILE EDGELINE & CENTERLINE MARKS
 
31.278318695.30248947.0078.1
CountyROBERTSON
HighwayFM 46
FromTHE FALLS COUNTY LINE
ToSH 14
CSJ0049-14-012
Proj IDSTP 2019(497)
Work TypeGRDG,WDN,STRCS,BASE,SURF,SGNS,MRKGS
 
1.3701404401.281476318.0999.9
CountyZERO COUNTIES
Highway
From
To
CSJ0205-02-066
Proj ID
Work Type
 
0.00570411.340.0
Work Order03-18-19
Work Began06-27-19
Work Completed
Time Computed06-16-19
Contract Working Days93
Addl Days Granted0
Working Days Charged91
Percent Time Used97
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-011
AREA WIDE PROTECTIVE, INC. (1.17)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.26)
BEAR CREEK CONSTRUCTION, LLC (22.30)
BROCK CONSTRUCTION, LLC (1.35)
CEN TEX HYDROSEED, INC. (2.34)
STRIPE-A-ZONE, INC. (17.79)
COMEN ENTERPRISE LLC (2.71)
LS HIGHWAY PRODUCTS, INC. (0.00)
D. I. J. CONSTRUCTION, INC. (0.00)
Contract #02193019
Totals1723096.580.002295676.4399.9

CountyROBERTSON ETC
HighwayFM 46 ETC
FromFALLS COUNTY LINE
ToSH 14
CSJ0049-14-013
Proj IDSTP 2021(066)
Work TypeSEAL COAT
 
16.2769071397.842457655.5327.0
Work Order03-18-21
Work Began04-26-21
Work Completed
Time Computed05-01-21
Contract Working Days112
Addl Days Granted0
Working Days Charged24
Percent Time Used21
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-013
BRYDL CONTRACTING, INC. (0.98)
INTERSTATE BARRICADES & MARKINGS, INC. (1.82)
Contract #10203006
Totals9071397.8429941.872457655.5327.0

CountyBRAZOS ETC
HighwayBS 6-R ETC
FromAT WALTON DRIVE/NEW MAIN DRIVE
To.WA
CSJ0050-01-087
Proj IDSTP 2021(024)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.6001136623.60340313.7529.9
Work Order11-19-20
Work Began04-20-21
Work Completed
Time Computed02-17-21
Contract Working Days158
Addl Days Granted0
Working Days Charged51
Percent Time Used32
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-087
AREA WIDE PROTECTIVE, INC. (1.66)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (3.47)
LINEAR TRAFFIC MARKINGS LLC (0.48)
PALOMARES CONSTRUCTION, INC. (1.40)
Contract #10203019
Totals1136623.60245337.50340313.7529.9

CountyBRAZOS ETC
HighwaySH 6 ETC
FromSH 6EFR @ SH 40
To.5 MI N OF GRIMES COUNTY LINE
CSJ0050-02-113
Proj IDNH 2021(060)
Work TypeTRAFFIC CONTROL DEVICES
 
222.3482655543.382683764.6099.9
Work Order02-03-21
Work Began03-22-21
Work Completed
Time Computed03-05-21
Contract Working Days64
Addl Days Granted0
Working Days Charged62
Percent Time Used96
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-02-113
BRYDL CONTRACTING, INC. (1.24)
Contract #09203033
Totals2655543.38627088.742683764.6099.9

CountyGRIMES
HighwaySH 6
FromBRAZOS COUNTY LINE
ToWALLER COUNTY LINE
CSJ0050-03-100
Proj IDC 50-3-100
Work TypeOVERLAY
 
14.3835798125.916031857.4699.9
Work Order08-17-18
Work Began08-12-19
Work Completed
Time Computed11-15-18
Contract Working Days72
Addl Days Granted22
Working Days Charged115
Percent Time Used122
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-100
AREA WIDE PROTECTIVE, INC. (0.12)
BATTERSON,LLP (3.03)
CPAVE, INC. (3.60)
DUSTROL, INC. (4.21)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.35)
Contract #07183040
Totals5798125.910.006031857.4699.9

CountyGRIMES ETC
HighwaySH 6 ETC
FromAT FM 1227
To.
CSJ0050-03-107
Proj IDSTP 2B20(204)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.100990316.51515056.7952.0
Work Order10-21-20
Work Began04-13-21
Work Completed
Time Computed01-19-21
Contract Working Days171
Addl Days Granted0
Working Days Charged58
Percent Time Used33
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-107
LONESTAR TRAFFIC SAFETY, LLC (1.15)
PINNACLE GRINDING AND GROOVING LLC (0.32)
CEN TEX HYDROSEED, INC. (1.36)
STRIPE LINES, INC. (0.74)
BRAZOS PAVING, INC. (17.65)
Contract #09203024
Totals990316.51130008.22515056.7952.0

CountyFREESTONE ETC
HighwayUS 84 ETC
FromIH 45
ToSH 75
CSJ0057-03-042
Proj IDC 57-3-42
Work TypeASPHALT RUBBER SEAL
 
187.92113798219.6613996975.8399.9
Work Order03-25-19
Work Began09-04-19
Work Completed
Time Computed07-01-19
Contract Working Days82
Addl Days Granted0
Working Days Charged82
Percent Time Used100
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0057-03-042
INTERSTATE BARRICADES & MARKINGS, INC. (10.21)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.05)
BRYDL CONTRACTING, INC. (0.55)
Contract #01193003
Totals13798219.660.0013996975.8399.9

CountyWALKER
HighwaySH 75
FromAT 2793
To.
CSJ0110-01-049
Proj IDF 2021(717)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.200946421.730.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days47
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0110-01-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213042
Totals946421.730.000.000.0

CountyWASHINGTON
HighwayBU 290F
FromBS 36-J
ToMARKET STREET
CSJ0114-09-077
Proj IDSTP 2B20(105)
Work TypeOVERLAY
 
2.6392697457.95201821.407.4
Work Order11-19-20
Work Began02-08-21
Work Completed
Time Computed02-08-21
Contract Working Days108
Addl Days Granted0
Working Days Charged7
Percent Time Used6
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-077
CITYLYNX, INC. (3.60)
CEN TEX HYDROSEED, INC. (0.09)
A BROTHERS MILLING, LLC (5.83)
STRIPE LINES, INC. (3.43)
WILLOW CITY SIGN & RAIL, INC. (1.69)
Contract #08203030
Totals2697457.9514000.00201821.407.4

CountyWASHINGTON ETC
HighwayUS 290 ETC
FromAT SS 125
To.
CSJ0114-09-078
Proj IDSTP 2020(798)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.800584899.11580021.0199.1
Work Order07-07-20
Work Began08-10-20
Work Completed
Time Computed08-06-20
Contract Working Days188
Addl Days Granted0
Working Days Charged150
Percent Time Used79
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-078
STRIPE LINES, INC. (3.31)
Contract #05203229
Totals584899.1122537.50580021.0199.1

CountyBRAZOS
HighwaySH 21
FromAT SIMS AVE.
To.
CSJ0116-04-104
Proj IDSTP 2020(787)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200263629.50262376.5699.5
Work Order07-20-20
Work Began12-11-20
Work Completed
Time Computed10-19-20
Contract Working Days68
Addl Days Granted5
Working Days Charged69
Percent Time Used94
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0116-04-104
AREA WIDE PROTECTIVE, INC. (1.50)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.57)
LINEAR TRAFFIC MARKINGS LLC (3.99)
PALOMARES CONSTRUCTION, INC. (6.67)
Contract #05203231
Totals263629.500.00262376.5699.5

CountyMADISON
HighwaySH 21
FromAT IH 45 BRIDGE
To.
CSJ0117-05-054
Proj IDNH 2020(090)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.1443843302.504003843.8399.9
CountyMADISON
HighwayFM 2158
FromAT LARRISON CREEK
To.
CSJ2027-01-013
Proj IDBR 2020(091)
Work TypeBRIDGE MAINTENANCE
 
0.100197018.00242089.3899.9
Work Order12-02-19
Work Began01-28-20
Work Completed
Time Computed01-01-20
Contract Working Days149
Addl Days Granted112
Working Days Charged336
Percent Time Used128
Contractor(s)
FUSED INDUSTRIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0117-05-054
BATTEN DRILLING, INC. (2.79)
THIRD COAST SERVICES LLC (15.32)
WILLOW CITY SIGN & RAIL, INC. (3.90)
GMJ PAVING CO. (6.97)
LONESTAR TRAFFIC SAFETY, LLC (0.28)
STRIPE LINES, INC. (1.53)
SCOTT DERR PAINTING CO, LLC (0.10)
LS HIGHWAY PRODUCTS, INC. (0.00)
AREA WIDE PROTECTIVE, INC. (0.21)
BREDA COMPANY, INC. (0.78)
BRUNDAGE-BONE (2.72)
STRUCTURAL INTEGRITY GROUP LLC (1.71)
CEN TEX HYDROSEED, INC. (0.41)
PRIMATE CONSTRUCTION, LP (0.09)
Contract #10193210
Totals4040320.500.004245933.2199.9

CountyMADISON
HighwaySH 21
FromIH 45
ToHOUSTON CL
CSJ0117-05-057
Proj IDSTP 2B20(198)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.0012031773.751492060.5073.4
Work Order09-18-20
Work Began11-04-20
Work Completed
Time Computed11-04-20
Contract Working Days156
Addl Days Granted0
Working Days Charged125
Percent Time Used80
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0117-05-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08203067
Totals2031773.75226128.001492060.5073.4

CountyFREESTONE
HighwaySH 75
FromCR 490
ToLEON CO. LINE
CSJ0166-03-033
Proj IDSTP 2020(951)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2277381.402097241.7092.0
CountyGRIMES
HighwaySH 90
From0.50 MILES N. OF FM 149
To0.15 MILES S OF CR 444
CSJ0315-03-062
Proj IDSTP 2020(951)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.109807796.26132182.3416.3
CountyBRAZOS
HighwayFM 1687
FromFM 50
ToSH 21
CSJ1560-01-038
Proj IDSTP 2020(951)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.7331006627.5481300.198.0
Work Order08-20-20
Work Began01-04-21
Work Completed
Time Computed11-18-20
Contract Working Days259
Addl Days Granted0
Working Days Charged89
Percent Time Used34
Contractor(s)
BEAR CREEK CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0166-03-033
MOBILE ENTERPRISES, INC. (2.18)
D. I. J. CONSTRUCTION, INC. (0.00)
DALLAS LITE AND BARRICADE, INC. (0.00)
DOUBLE OAK EROSION, INC. (0.00)
FORTSON CONTRACTING, INC. (0.00)
J & M CONTRACTING, COMPANY (0.00)
Contract #07203016
Totals4091805.20503635.542310724.2356.4

page 1 | page 2 | page 3