Monthly State Let Construction Report For Brownwood District As Of Jan 10, 2023 Page 1 Of 3

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEASTLAND
HighwayIH 20
FromCALLAHAN C/L
To.3 MI E OF FM 570
CSJ0007-03-097
Proj IDSTP 2021(326)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
19.8883143781.393165794.2499.9
CountyEASTLAND
HighwayIH 20
From.3 MI E OF FM 570
To.41 MI W OF FM 2461
CSJ0007-04-133
Proj IDSTP 2021(326)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
992192.75712876.3571.8
CountyEASTLAND
HighwayIH 20
From0.41 MI W OF FM 2461
ToLP 254 (E INTERSECTION)
CSJ0007-06-265
Proj IDSTP 2021(326)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.307856755.58763483.7089.1
Work Order03-18-21
Work Began06-14-21
Work Completed
Time Computed04-17-21
Contract Working Days338
Addl Days Granted19
Working Days Charged343
Percent Time Used96
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-097
AVANZA CONSTRUCTION & EARTHWORKS, LLC (2.40)
CROWDER CONSTRUCTION CO., INC. (EASTLAND) (1.20)
TNT CRANE & RIGGING, INC. (2.40)
Contract #02213210
Totals4992729.72118357.784642154.2992.9

CountyEASTLAND
HighwayIH 20
From1 MI. WEST OF CISCO
To1.2 MI. WEST OF SH 6
CSJ0007-03-109
Proj IDF 2023(282)
Work TypeOVERLAY
 
8087544.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-06-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-109
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223030
Totals8087544.000.000.000.0

CountyEASTLAND
HighwaySH 112
FromAT IH 20 NORTH AND SOUTH FRONTAGE ROADS
To.
CSJ0007-04-134
Proj IDF 2022(486)
Work TypeTRAFFIC CONTROL DEVICES
 
1693302.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-04-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05223023
Totals1693302.700.000.000.0

CountyEASTLAND
HighwayIH 20
FromIH 20 AT CR 235 CROSS
To.
CSJ0007-06-258
Proj IDBR 2022(597)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.394606937.92556568.5999.9
Work Order07-14-22
Work Began08-09-22
Work Completed
Time Computed08-09-22
Contract Working Days17
Addl Days Granted0
Working Days Charged40
Percent Time Used235
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-258
EPCS ENVIRONMENTAL LLC (37.94)
Contract #06223032
Totals606937.92583.34556568.5999.9

CountySTEPHENS ETC
HighwayUS 180 ETC
From.132 MI E OF SH67
To.113 MI E OF FM 207
CSJ0011-09-075
Proj IDF 2023(156)
Work TypeSEAL COAT
 
267.32114954532.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days105
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0011-09-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11223004
Totals14954532.770.000.000.0

CountyCOLEMAN
HighwayUS 67
FromBROWN C/L
ToSANTA ANNA CITY LIMITS
CSJ0054-04-111
Proj IDF 2022(599)
Work TypeWIDEN NON-FREEWAY
 
6.49625640483.252163132.578.4
CountyBROWN
HighwayUS 67
From1.5 MI E OF COLEMAN COUNTY LINE
ToCOLEMAN COUNTY LINE
CSJ0054-06-103
Proj IDF 2022(598)
Work TypeWIDEN NON-FREEWAY
 
1.5691721723.49155975.839.0
Work Order07-11-22
Work Began10-10-22
Work Completed
Time Computed10-10-22
Contract Working Days572
Addl Days Granted0
Working Days Charged40
Percent Time Used6
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-111
4-WAY HAULERS, LLC (4.31)
CEDAR EATERS OF TEXAS (0.58)
CONTRACTORS SERVICE, LTD. (0.50)
DK CONTRACTING, LLC (0.44)
ROADWAY SPECIALTIES, INC. (2.98)
STRIPING TECHNOLOGY, L.P. (0.05)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.19)
WEST TEXAS ROCK RESOURCES, LLC (0.05)
Contract #06223206
Totals27362206.74716272.692319108.408.4

CountyMILLS ETC
HighwayUS 84 ETC
FromAT LOOP 15
To.
CSJ0054-09-042
Proj IDF 2022(611)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.296501967.00380719.5675.8
Work Order07-11-22
Work Began10-31-22
Work Completed
Time Computed10-10-22
Contract Working Days90
Addl Days Granted0
Working Days Charged41
Percent Time Used45
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0054-09-042
TOTAL HIGHWAY MAINTENANCE, LLC (2.60)
Contract #06223031
Totals501967.00148810.39380719.5675.8

CountyMCCULLOCH
HighwayUS 87
FromBRADY CREEK BRIDGE
To.4 MILES WEST OF US 283
CSJ0070-06-041
Proj IDNH 2B20(071)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.5476955456.067633257.9599.9
CountyMCCULLOCH
HighwayUS 87
FromAT JACQUELINE RUFFIN ROAD
To.
CSJ0070-06-052
Proj IDNH 2B20(071)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
100625.00100625.0099.9
Work Order01-14-21
Work Began03-15-21
Work Completed
Time Computed03-15-21
Contract Working Days298
Addl Days Granted0
Working Days Charged286
Percent Time Used95
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0070-06-041
JR WEST TEXAS CONCRETE LLC (10.63)
L&H ELECTRICAL, LLC (3.87)
D. I. J. CONSTRUCTION, INC. (2.97)
DALLAS LITE AND BARRICADE, INC. (0.60)
TIGHT LINE CONSTRUCTION, LLC (0.51)
MPB, INC. (0.67)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.03)
WEST TEXAS ROCK RESOURCES, LLC (0.25)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.08)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.33)
CHEROKEE SERVICES (0.67)
HJC FARMS, INC. (0.09)
Contract #12203209
Totals7056081.063500.007733882.9599.9

CountyBROWN
HighwayUS 67
FromAT FORT WORTH & WESTERN RAILROAD
To.
CSJ0079-01-038
Proj IDC 79-1-38
Work TypeREHABILITATION OF EXISTING ROAD
 
0.2103046555.051834281.6460.2
Work Order02-16-22
Work Began05-23-22
Work Completed
Time Computed05-17-22
Contract Working Days131
Addl Days Granted40
Working Days Charged116
Percent Time Used67
Contractor(s)
PRATER DIRT WORK LLC
SUBCONTRACTOR(S) FOR CCSJ: 0079-01-038
CONTRACTORS SERVICE, LTD. (0.54)
D. I. J. CONSTRUCTION, INC. (1.50)
HJC FARMS, INC. (2.42)
J. H. ODEN CONTRACTING COMPANY (0.57)
PINNACLE GRINDING AND GROOVING LLC (0.14)
TEX OP CONSTRUCTION, LP (1.15)
GRIDER PAVING LLC (18.19)
J & M CONTRACTING, COMPANY (7.48)
Contract #01223010
Totals3046555.05366585.901834281.6460.2

CountyCOMANCHE
HighwayUS 67
FromUS 67
ToAT FM 3381
CSJ0079-03-051
Proj IDF 2021(766)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
850894.76628254.2675.1
Work Order09-16-21
Work Began02-07-22
Work Completed
Time Computed12-15-21
Contract Working Days75
Addl Days Granted0
Working Days Charged94
Percent Time Used125
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0079-03-051
NORTHEASTERN PAVERS, LLC (20.73)
JR WEST TEXAS CONCRETE LLC (5.93)
TRP CONSTRUCTION GROUP, LLC (2.00)
L&H ELECTRICAL, LLC (14.41)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.49)
WILLIS ELECTRIC CO., LP (18.21)
FIBER-TEX (0.00)
Contract #08213255
Totals850894.760.00628254.2675.1

CountyCOLEMAN
HighwayUS 283
FromCR 256
ToDRY CREEK
CSJ0099-01-035
Proj IDSTP 2022(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.1263177408.861124246.2035.3
Work Order02-16-22
Work Began05-17-22
Work Completed
Time Computed05-17-22
Contract Working Days199
Addl Days Granted0
Working Days Charged135
Percent Time Used67
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0099-01-035
DELGADO"S CONTRACTORS, LLC (5.76)
DIIBS SPECIALISTS, LLC (3.35)
PINNACLE GRINDING AND GROOVING LLC (0.29)
CONTRACTORS SERVICE, LTD. (0.75)
D. I. J. CONSTRUCTION, INC. (1.40)
HJC FARMS, INC. (3.42)
Contract #01223214
Totals3177408.8691484.501124246.2035.3

CountyEASTLAND
HighwayUS 183
FromRISING STAR NCL
ToNEAR SH 36
CSJ0127-02-142
Proj IDSTP 2018(829)
Work TypeRECONSTRUCT URBAN ROADWAY
 
1.47611116710.5510814117.1797.3
CountyEASTLAND
HighwayUS 183
FromRISING STAR NCL
ToNEAR SH 36
CSJ0127-02-146
Proj IDSTP 2018(212)
Work TypeACQUISITION AND UTILITY ADJUSTMENTS
 
0.8093038242.003045789.4799.9
CountyEASTLAND
HighwayUS 183
FromNEAR SH 36
ToNEAR RISING STAR SCL
CSJ0127-02-147
Proj IDSTP 2018(211)
Work TypeUTILITY ADJUSTMENTS
 
0.6672732059.005292299.8399.9
Work Order06-11-18
Work Began08-17-18
Work Completed
Time Computed08-10-18
Contract Working Days790
Addl Days Granted246
Working Days Charged1,044
Percent Time Used100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-142
F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (1.37)
TTG UTILITIES, LP (23.02)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.25)
W.S. CONSTRUCTION COMPANY (24.13)
FLASHER EQUIPMENT COMPANY (0.97)
NIXON ENGINEERING (0.00)
DALLAS LITE AND BARRICADE, INC. (0.01)
4-WAY HAULERS, LLC (0.07)
CRUZ HERNANDEZ CONCRETE CONSTRUCTION (13.15)
Contract #05183221
Totals16887011.5555985.0019152206.4799.9

CountyBROWN
HighwayUS 377
FromFM 2524
To18TH ST
CSJ0128-01-111
Proj IDF 2022(487)
Work TypeWIDEN NON-FREEWAY
 
1.5964045900.20122095.003.0
Work Order08-25-22
Work Began11-28-22
Work Completed
Time Computed11-23-22
Contract Working Days149
Addl Days Granted0
Working Days Charged13
Percent Time Used8
Contractor(s)
PRATER DIRT WORK LLC
SUBCONTRACTOR(S) FOR CCSJ: 0128-01-111
WILLIS ELECTRIC CO., LP (9.05)
FUSION COMMUNICATIONS, LLC (0.00)
D. I. J. CONSTRUCTION, INC. (3.61)
TEXOP CONSTRUCTION (1.80)
JR WEST TEXAS CONCRETE LLC (12.42)
Contract #05223224
Totals4045900.2088110.00122095.003.0

CountyEASTLAND
HighwaySH 36
From0.003 MI. W. OF E MILLS ST
ToCOMANCHE C/L
CSJ0182-01-017
Proj IDF 2021(451)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.924290281.85415875.8699.9
CountyCOMANCHE
HighwaySH 36
FromEASTLAND C/L
To0.322 MI. NW OF BARNES AVE
CSJ0182-02-043
Proj IDF 2021(451)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
20.421818111.091056975.9899.9
CountyCOMANCHE
HighwaySH 36
FromUS 67
ToHAMILTON C/L
CSJ0183-01-044
Proj IDF 2021(451)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
22.272989791.081598214.0699.9
Work Order05-14-21
Work Began11-15-21
Work Completed
Time Computed06-13-21
Contract Working Days176
Addl Days Granted33
Working Days Charged165
Percent Time Used78
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0182-01-017
SAFETY COP, LLC (5.70)
Contract #04213221
Totals2098184.0220327.003071065.9099.9

CountyCOMANCHE
HighwaySH 36
FromAT US 67
To.
CSJ0183-01-049
Proj IDF 2021(452)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
68732.9363370.5099.9
CountyEASTLAND
HighwaySH 16
FromAT FM 8
To.
CSJ0288-03-033
Proj IDF 2021(452)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
130520.81104618.8180.1
Work Order05-27-21
Work Began11-30-21
Work Completed
Time Computed08-25-21
Contract Working Days51
Addl Days Granted1
Working Days Charged69
Percent Time Used132
Contractor(s)
SEFBO PIPELINE BRIDGE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-049
SERVICES UNLIMITED (10.61)
WG ENGINEERING & CONSTRUCTION, LLC (43.07)
Contract #04213028
Totals199253.745006.35167989.3189.3

CountyCOMANCHE
HighwaySH 36
From0.3 MILES NORTH OF FM 1702
To0.34 MILES SOUTH OF FM 1702
CSJ0183-01-053
Proj IDF 2021(767)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.650999893.621049222.8199.9
CountyCOMANCHE
HighwaySH 36
From1.87 MI N OF FM 1702
To.4 MI S OF FM 1702
CSJ0183-01-055
Proj IDF 2021(767)
Work TypeOVERLAY
 
2.140557701.88510596.1091.5
Work Order09-16-21
Work Began02-09-22
Work Completed
Time Computed10-16-21
Contract Working Days114
Addl Days Granted0
Working Days Charged124
Percent Time Used108
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-053
D. I. J. CONSTRUCTION, INC. (1.91)
JR WEST TEXAS CONCRETE LLC (3.68)
NORTHEASTERN PAVERS, LLC (47.82)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.29)
WILLIS ELECTRIC CO., LP (2.76)
PINNACLE GRINDING AND GROOVING LLC (0.43)
Contract #08213047
Totals1557595.500.001559818.9199.9

CountyEASTLAND
HighwaySH 6
FromIH 20
ToSL 389
CSJ0257-03-033
Proj IDC 257-3-33
Work TypeSUPER-2 HIGHWAY
 
8.04310087854.942042033.2720.2
Work Order02-23-22
Work Began09-06-22
Work Completed
Time Computed05-24-22
Contract Working Days223
Addl Days Granted0
Working Days Charged70
Percent Time Used31
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0257-03-033
4-WAY HAULERS, LLC (6.87)
D. I. J. CONSTRUCTION, INC. (1.50)
DUSTIN ALLEN, INC. (1.43)
PINNACLE GRINDING AND GROOVING LLC (0.18)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.47)
STRUCTURAL INTEGRITY GROUP LLC (0.70)
DALLAS LITE AND BARRICADE, INC. (0.19)
MARCOM"S MOWING SERVICE, LLC (0.23)
FC TRAFFIC CONTROL, INC. (0.36)
Contract #01223035
Totals10087854.94100301.882042033.2720.2

CountyEASTLAND
HighwaySH 6
FromSL 389
To0.18 MI. N. OF CRESSENT ST
CSJ0257-04-029
Proj IDF 2022(007)
Work TypeSUPER-2 HIGHWAY
 
8.94710587368.266147207.2257.9
Work Order10-20-21
Work Began02-23-22
Work Completed
Time Computed12-19-21
Contract Working Days230
Addl Days Granted0
Working Days Charged162
Percent Time Used70
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0257-04-029
COMEN ENTERPRISE LLC (1.51)
PINNACLE GRINDING AND GROOVING LLC (0.21)
TRP CONSTRUCTION GROUP, LLC (1.61)
TEXAS TRAFFIC AND BARRICADE, LLC (0.19)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.54)
4-WAY HAULERS, LLC (6.08)
Contract #09213204
Totals10587368.26532305.036147207.2257.9

CountyCOMANCHE
HighwaySH 6
FromSH 16 NORTH
ToEAST CITY LIMIT OF DELEON
CSJ0257-05-045
Proj IDC 257-5-45
Work TypeWIDEN NON-FREEWAY
 
1.9319728370.406297572.2464.7
CountyCOMANCHE
HighwaySH 6
FromSH 16 NORTH
ToEAST CITY LIMIT OF DELEON
CSJ0257-05-048
Proj IDROW 257-5-48
Work TypeRIGHT OF WAY
 
1.931558860.00716490.2099.9
Work Order07-20-20
Work Began10-05-20
Work Completed
Time Computed09-18-20
Contract Working Days688
Addl Days Granted1
Working Days Charged532
Percent Time Used77
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0257-05-045
SOUTHERN CROSS CONTRACTORS, LLC (0.64)
F & W ELECTRICAL CONTRACTORS, INC. (7.41)
FLASHER EQUIPMENT COMPANY (1.25)
B & L CONSTRUCTION COMPANY (2.33)
SITE BARRICADES (0.00)
BUYERS BARRICADES, INC. (0.04)
B & L MANHOLE SERVICE (0.01)
BCAC UNDERGROUND LLC (0.00)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.03)
4-WAY HAULERS, LLC (3.88)
CRUZ HERNANDEZ CONCRETE CONSTRUCTION (0.82)
Contract #05203204
Totals10287230.405873.377014062.4468.1

CountyCOMANCHE ETC
HighwaySH 6
FromEASTLAND COUNTY LINE
ToSH 16
CSJ0257-05-046
Proj IDNH 2020(457)
Work TypeSUPER-2 HIGHWAY
 
18.16413793112.537210081.1752.4
Work Order06-09-20
Work Began09-08-20
Work Completed
Time Computed08-08-20
Contract Working Days368
Addl Days Granted0
Working Days Charged385
Percent Time Used104
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0257-05-046
BROCK CONSTRUCTION, LLC (1.32)
CONTRACTORS SERVICE COMPANY (0.37)
D. I. J. CONSTRUCTION, INC. (2.43)
STRIPE-A-ZONE, INC. (0.27)
SOUTHERN CROSS CONTRACTORS, LLC (0.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.37)
W. S. CONSTRUCTION COMPANY (5.68)
DIIBS SPECIALISTS, LLC (2.59)
DALLAS LITE AND BARRICADE, INC. (1.44)
BECK-REIT & SONS, LTD. (0.84)
BEAR CREEK CONSTRUCTION, LLC (2.44)
Contract #04203204
Totals13793112.5343806.667210081.1752.4

page 1 | page 2 | page 3