Monthly State Let Construction Report For Brownwood District As Of Nov 10, 2023 Page 1 Of 3

Last Update: Friday, November 10, 2023
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEASTLAND
HighwayIH 20
FromCALLAHAN C/L
To.3 MI E OF FM 570
CSJ0007-03-097
Proj IDSTP 2021(326)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
19.8883143781.393200819.3699.9
CountyEASTLAND
HighwayIH 20
From.3 MI E OF FM 570
To.41 MI W OF FM 2461
CSJ0007-04-133
Proj IDSTP 2021(326)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
992192.751020433.3899.9
CountyEASTLAND
HighwayIH 20
From0.41 MI W OF FM 2461
ToLP 254 (E INTERSECTION)
CSJ0007-06-265
Proj IDSTP 2021(326)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.307856755.58921401.9999.9
Work Order03-18-21
Work Began06-14-21
Work Completed
Time Computed04-17-21
Contract Working Days338
Addl Days Granted23
Working Days Charged420
Percent Time Used116
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-097
AVANZA CONSTRUCTION & EARTHWORKS, LLC (2.40)
CROWDER CONSTRUCTION CO., INC. (EASTLAND) (1.20)
TNT CRANE & RIGGING, INC. (2.40)
Contract #02213210
Totals4992729.7211284.105142654.7399.9

CountyEASTLAND
HighwayIH 20
FromCALLAHAN C/L
To1 MI WEST OF CISCO
CSJ0007-03-108
Proj IDF 2023(093)
Work TypeOVERLAY
 
2010120.001355890.4767.4
Work Order04-25-23
Work Began06-22-23
Work Completed
Time Computed05-25-23
Contract Working Days55
Addl Days Granted0
Working Days Charged48
Percent Time Used87
Contractor(s)
VSS INTERNATIONAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-108
BIG CREEK CONSTRUCTION, LTD. (10.19)
DUSTROL, INC. (19.83)
KING GEORGE TRAFFIC SOLUTIONS LLC (1.74)
LINEAR TRAFFIC MARKINGS LLC (3.83)
PROFESSIONAL TRAFFIC CONTROL LLC (0.82)
HERRING SERVICES (1.50)
HERRING LLC (1.50)
Contract #02233227
Totals2010120.0048165.811355890.4767.4

CountyEASTLAND
HighwayIH 20
From1 MI. WEST OF CISCO
To1.2 MI. WEST OF SH 6
CSJ0007-03-109
Proj IDF 2023(282)
Work TypeOVERLAY
 
8087544.007833307.3996.8
Work Order01-06-23
Work Began07-12-23
Work Completed
Time Computed04-06-23
Contract Working Days68
Addl Days Granted0
Working Days Charged69
Percent Time Used101
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-109
TRP CONSTRUCTION GROUP, LLC (2.80)
WEST TEXAS ROCK RESOURCES, LLC (0.19)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.08)
Contract #12223030
Totals8087544.00265286.557833307.3996.8

CountyEASTLAND
HighwaySH 112
FromAT IH 20 NORTH AND SOUTH FRONTAGE ROADS
To.
CSJ0007-04-134
Proj IDF 2022(486)
Work TypeTRAFFIC CONTROL DEVICES
 
1727088.9236740.002.1
Work Order05-08-23
Work Began00-00-00
Work Completed
Time Computed08-06-23
Contract Working Days109
Addl Days Granted0
Working Days Charged1
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-04-134
D. I. J. CONSTRUCTION, INC. (1.24)
PEACHTREE CONSTRUCTION, LTD. (9.11)
VACA UNDERGROUND UTILITIES INC (43.06)
Contract #04233033
Totals1727088.9236740.0036740.002.1

CountyEASTLAND
HighwayIH 20
FromIH 20 AT CR 235 CROSS
To.
CSJ0007-06-258
Proj IDBR 2022(597)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.394606937.92556568.5999.9
Work Order07-14-22
Work Began08-09-22
Work Completed
Time Computed08-09-22
Contract Working Days17
Addl Days Granted0
Working Days Charged40
Percent Time Used235
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-258
EPCS ENVIRONMENTAL LLC (37.94)
Contract #06223032
Totals606937.920.00556568.5999.9

CountyEASTLAND
HighwayIH 20
From.17 MI W OF SH16 (CRCP)
To.6 MI E OF SH16 (CS)
CSJ0007-06-278
Proj IDF 2B23(241)
Work TypeOVERLAY
 
1536326.91117600.007.6
CountyEASTLAND
HighwayIH 20
From0.6 MI. EAST OF SH 16
To0.26 MI. WEST OF ERATH COUNTY LINE
CSJ0314-05-046
Proj IDBR 2B23(020)
Work TypeBRIDGE REPLACEMENT
 
11695232.380.000.0
CountyEASTLAND
HighwayIH 20
From0.26 MI. WEST OF ERATH COUNTY LINE
ToERATH COUNTY LINE
CSJ0314-05-047
Proj IDBR 2B23(020)
Work TypeBRIDGE REPLACEMENT
 
11749841.470.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days265
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-278
A BROTHERS MILLING, LLC (0.42)
C & B SERVICES, INC. (0.17)
GIBSON & ASSOCIATES, INC. (2.13)
G J SEEDING, LLC (0.27)
HJC FARMS, INC. (0.08)
JB PINNACLE GROUP, LLC (2.96)
J. R. (JOE) RAMON & SONS, INC. (0.98)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.46)
NORTHEASTERN PAVERS, LLC (23.82)
SCOTT DERR PAINTING CO, LLC (0.16)
SK CONCRETE SERVICES LLC (0.18)
TEXAS SHAFTS, INC. (4.63)
TEXAS TRAFFIC AND BARRICADE, LLC (0.06)
TORO BRAVO CONSTRUCTION, LLC (1.46)
Contract #08233006
Totals24981400.76117600.00117600.000.4

CountySTEPHENS ETC
HighwayUS 180 ETC
FromFM 3099
ToHARDING STREET
CSJ0011-07-062
Proj IDF 2024(344)
Work TypeSEAL COAT
 
278.26713778329.830.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11233008
Totals13778329.830.000.000.0

CountySTEPHENS ETC
HighwayUS 180 ETC
From.132 MI E OF SH67
To.113 MI E OF FM 207
CSJ0011-09-075
Proj IDF 2023(156)
Work TypeSEAL COAT
 
267.32114954532.7713975225.2093.4
Work Order02-14-23
Work Began05-09-23
Work Completed
Time Computed05-09-23
Contract Working Days105
Addl Days Granted0
Working Days Charged103
Percent Time Used98
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0011-09-075
BARRICADES PLUS, LLC (1.75)
CENTERLINE TECHNOLOGIES, LLC (5.35)
D. I. J. CONSTRUCTION, INC. (0.72)
CDM HOLDINGS, LLC (4.77)
RED SIXTEEN CONSTRUCTION, INC (0.00)
Contract #11223004
Totals14954532.77186101.2013975225.2093.4

CountyCOLEMAN
HighwayUS 67
FromBROWN C/L
ToSANTA ANNA CITY LIMITS
CSJ0054-04-111
Proj IDF 2022(599)
Work TypeWIDEN NON-FREEWAY
 
6.49625640483.256312211.0324.6
CountyBROWN
HighwayUS 67
From1.5 MI E OF COLEMAN COUNTY LINE
ToCOLEMAN COUNTY LINE
CSJ0054-06-103
Proj IDF 2022(598)
Work TypeWIDEN NON-FREEWAY
 
1.5691721723.49155975.839.0
Work Order07-11-22
Work Began10-10-22
Work Completed
Time Computed10-10-22
Contract Working Days572
Addl Days Granted0
Working Days Charged211
Percent Time Used36
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-111
4-WAY HAULERS, LLC (4.31)
CEDAR EATERS OF TEXAS (0.58)
CONTRACTORS SERVICE, LTD. (0.50)
DK CONTRACTING, LLC (0.44)
ROADWAY SPECIALTIES, INC. (2.98)
STRIPING TECHNOLOGY, L.P. (0.05)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.19)
WEST TEXAS ROCK RESOURCES, LLC (0.05)
J. H. ODEN CONTRACTING COMPANY (0.19)
Contract #06223206
Totals27362206.74308549.276468186.8623.6

CountyCOLEMAN
HighwayUS 84
FromAT INTERSECTION OF US 84 AND COLORADO ST
To.
CSJ0054-04-122
Proj IDSTP 2023(905)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
157033.000.000.0
CountyCOLEMAN
HighwayUS 84
From0.098 MI S OF FM 3425
To0.39 MI N OF FM 3425
CSJ0054-04-124
Proj IDSTP 2023(605)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.590168611.8082353.2048.8
CountyMCCULLOCH
HighwayFM 2309
FromAT SH 71 INTERSECTION
To.
CSJ1102-01-049
Proj IDSTP 2023(605)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
495145.200.000.0
Work Order05-17-23
Work Began10-23-23
Work Completed
Time Computed08-15-23
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-122
CONTRACTORS SERVICE, LTD. (2.35)
WILLIS ELECTRIC CO., LP (35.28)
D. I. J. CONSTRUCTION, INC. (1.78)
Contract #04233040
Totals820790.007500.0082353.2010.0

CountyCOLEMAN
HighwayUS 84
From0.2 MI NORTH OF FM 568
To0.2 MI SOUTH CR 196
CSJ0054-04-123
Proj IDSTP 2023(639)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2976495.111278266.5442.9
Work Order05-17-23
Work Began06-19-23
Work Completed
Time Computed06-19-23
Contract Working Days113
Addl Days Granted0
Working Days Charged84
Percent Time Used74
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-123
CONTRACTORS SERVICE, LTD. (1.08)
HALLIGAN SERVICES LLC (6.87)
WEST TEXAS ROCK RESOURCES, LLC (0.36)
HJC FARMS, INC. (6.35)
WILLIS ELECTRIC CO., LP (0.41)
D. I. J. CONSTRUCTION, INC. (1.89)
Contract #04233043
Totals2976495.11417437.501278266.5442.9

CountyBROWN
HighwayUS 67
FromAT CLEMENTS ST.
To.
CSJ0054-06-105
Proj IDC 54-6-105
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.099854513.1566691.307.8
Work Order05-17-23
Work Began10-02-23
Work Completed
Time Computed08-15-23
Contract Working Days51
Addl Days Granted0
Working Days Charged6
Percent Time Used11
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0054-06-105
JR WEST TEXAS CONCRETE LLC (16.83)
TRP CONSTRUCTION GROUP, LLC (2.53)
Contract #04233231
Totals854513.1566691.3066691.307.8

CountyMILLS ETC
HighwayUS 84 ETC
FromCR 332
ToHAMILTON C/L
CSJ0055-01-031
Proj IDF 2024(565)
Work TypeSEAL COAT
 
26.3434495363.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days53
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0055-01-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11233021
Totals4495363.250.000.000.0

CountyBROWN
HighwayUS 67
FromAT FORT WORTH & WESTERN RAILROAD
To.
CSJ0079-01-038
Proj IDC 79-1-38
Work TypeREHABILITATION OF EXISTING ROAD
 
0.2103046555.053774836.2499.9
Work Order02-16-22
Work Began05-23-22
Work Completed
Time Computed05-17-22
Contract Working Days131
Addl Days Granted82
Working Days Charged216
Percent Time Used101
Contractor(s)
PRATER DIRT WORK LLC
SUBCONTRACTOR(S) FOR CCSJ: 0079-01-038
CONTRACTORS SERVICE, LTD. (0.54)
D. I. J. CONSTRUCTION, INC. (1.50)
HJC FARMS, INC. (2.42)
J. H. ODEN CONTRACTING COMPANY (0.57)
PINNACLE GRINDING AND GROOVING LLC (0.14)
TEX OP CONSTRUCTION, LP (1.15)
GRIDER PAVING LLC (18.19)
J & M CONTRACTING, COMPANY (7.48)
JR WEST TEXAS CONCRETE LLC (2.96)
Contract #01223010
Totals3046555.0526456.993774836.2499.9

CountyCOMANCHE
HighwayUS 67
FromUS 67
ToAT FM 3381
CSJ0079-03-051
Proj IDF 2021(766)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
850894.76718449.8489.1
Work Order09-16-21
Work Began02-07-22
Work Completed
Time Computed12-15-21
Contract Working Days75
Addl Days Granted12
Working Days Charged153
Percent Time Used175
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0079-03-051
NORTHEASTERN PAVERS, LLC (20.73)
JR WEST TEXAS CONCRETE LLC (5.93)
TRP CONSTRUCTION GROUP, LLC (2.00)
L&H ELECTRICAL, LLC (14.41)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.49)
WILLIS ELECTRIC CO., LP (18.21)
FIBER-TEX (0.00)
Contract #08213255
Totals850894.760.00718449.8489.1

CountyEASTLAND
HighwayUS 183
FromRISING STAR NCL
ToNEAR SH 36
CSJ0127-02-142
Proj IDSTP 2018(829)
Work TypeRECONSTRUCT URBAN ROADWAY
 
1.47611116710.5511750360.9699.9
CountyEASTLAND
HighwayUS 183
FromRISING STAR NCL
ToNEAR SH 36
CSJ0127-02-146
Proj IDSTP 2018(212)
Work TypeACQUISITION AND UTILITY ADJUSTMENTS
 
0.8093038242.003045789.4799.9
CountyEASTLAND
HighwayUS 183
FromNEAR SH 36
ToNEAR RISING STAR SCL
CSJ0127-02-147
Proj IDSTP 2018(211)
Work TypeUTILITY ADJUSTMENTS
 
0.6672732059.005292299.8399.9
Work Order06-11-18
Work Began08-17-18
Work Completed
Time Computed08-10-18
Contract Working Days790
Addl Days Granted246
Working Days Charged1,112
Percent Time Used107
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-142
F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (1.37)
TTG UTILITIES, LP (23.02)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.25)
W.S. CONSTRUCTION COMPANY (24.13)
FLASHER EQUIPMENT COMPANY (0.97)
NIXON ENGINEERING (0.00)
DALLAS LITE AND BARRICADE, INC. (0.01)
4-WAY HAULERS, LLC (0.07)
CRUZ HERNANDEZ CONCRETE CONSTRUCTION (13.15)
SOUTHEAST GRINDING AND GROOVING LLC (0.11)
Contract #05183221
Totals16887011.55153907.4620088450.2699.9

CountyBROWN
HighwayUS 377
FromFM 2524
To18TH ST
CSJ0128-01-111
Proj IDF 2022(487)
Work TypeWIDEN NON-FREEWAY
 
1.5964045900.202933502.1972.5
Work Order08-25-22
Work Began11-28-22
Work Completed
Time Computed11-23-22
Contract Working Days149
Addl Days Granted56
Working Days Charged163
Percent Time Used79
Contractor(s)
PRATER DIRT WORK LLC
SUBCONTRACTOR(S) FOR CCSJ: 0128-01-111
WILLIS ELECTRIC CO., LP (9.05)
FUSION COMMUNICATIONS, LLC (0.00)
D. I. J. CONSTRUCTION, INC. (3.61)
TEXOP CONSTRUCTION (1.80)
JR WEST TEXAS CONCRETE LLC (12.42)
DALLAS LITE AND BARRICADE, INC. (0.02)
CONTRACTORS SERVICE, LTD. (0.84)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.30)
GRIDER PAVING LLC (8.62)
Contract #05223224
Totals4045900.20647618.572933502.1972.5

CountyBROWN
HighwayUS 377
From0.1 MI S. OF FM 45
To0.26 MI. S. CR 554
CSJ0128-01-118
Proj IDSTP 2023(700)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
805046.9317500.002.1
CountyBROWN
HighwayFM 2125
FromSHADY OAKS DR
ToCR 617
CSJ2013-02-013
Proj IDSTP 2023(700)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
724090.30106844.6214.7
CountyBROWN
HighwayFM 2125
FromFM 2632
ToSHADY OAKS DR.
CSJ2013-02-014
Proj IDSTP 2023(700)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.7661143143.56542919.0047.4
Work Order06-14-23
Work Began09-05-23
Work Completed
Time Computed07-14-23
Contract Working Days185
Addl Days Granted0
Working Days Charged64
Percent Time Used34
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0128-01-118
D. I. J. CONSTRUCTION, INC. (3.70)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.91)
JR WEST TEXAS CONCRETE LLC (15.71)
DIIBS SPECIALISTS, LLC (3.05)
WEST TEXAS ROCK RESOURCES, LLC (0.15)
HJC FARMS, INC. (1.52)
D&G ENERGY CORPORATION (3.21)
Contract #05233226
Totals2672280.79510263.62667263.6224.9

CountyEASTLAND
HighwaySH 36
From0.003 MI. W. OF E MILLS ST
ToCOMANCHE C/L
CSJ0182-01-017
Proj IDF 2021(451)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.924290281.85478782.8699.9
CountyCOMANCHE
HighwaySH 36
FromEASTLAND C/L
To0.322 MI. NW OF BARNES AVE
CSJ0182-02-043
Proj IDF 2021(451)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
20.421818111.091074430.9899.9
CountyCOMANCHE
HighwaySH 36
FromUS 67
ToHAMILTON C/L
CSJ0183-01-044
Proj IDF 2021(451)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
22.272989791.081598214.0699.9
Work Order05-14-21
Work Began11-15-21
Work Completed
Time Computed06-13-21
Contract Working Days176
Addl Days Granted33
Working Days Charged165
Percent Time Used78
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0182-01-017
SAFETY COP, LLC (5.70)
Contract #04213221
Totals2098184.020.003151427.9099.9

CountyCOMANCHE
HighwaySH 36
From0.3 MILES NORTH OF FM 1702
To0.34 MILES SOUTH OF FM 1702
CSJ0183-01-053
Proj IDF 2021(767)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.650999893.621055900.3199.9
CountyCOMANCHE
HighwaySH 36
From1.87 MI N OF FM 1702
To.4 MI S OF FM 1702
CSJ0183-01-055
Proj IDF 2021(767)
Work TypeOVERLAY
 
2.140557701.88510596.1091.5
Work Order09-16-21
Work Began02-09-22
Work Completed
Time Computed10-16-21
Contract Working Days114
Addl Days Granted3
Working Days Charged125
Percent Time Used106
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-053
D. I. J. CONSTRUCTION, INC. (1.91)
JR WEST TEXAS CONCRETE LLC (3.68)
NORTHEASTERN PAVERS, LLC (47.82)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.29)
WILLIS ELECTRIC CO., LP (2.76)
PINNACLE GRINDING AND GROOVING LLC (0.43)
Contract #08213047
Totals1557595.500.001566496.4199.9

page 1 | page 2 | page 3