|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | EASTLAND |
Highway | IH 20 |
From | CALLAHAN C/L |
To | .3 MI E OF FM 570 |
CSJ | 0007-03-097 |
Proj ID | STP 2021(326)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 19.888 | 3143781.39 | | 3165794.24 | 99.9 |
County | EASTLAND |
Highway | IH 20 |
From | .3 MI E OF FM 570 |
To | .41 MI W OF FM 2461 |
CSJ | 0007-04-133 |
Proj ID | STP 2021(326)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 992192.75 | | 712876.35 | 71.8 |
County | EASTLAND |
Highway | IH 20 |
From | 0.41 MI W OF FM 2461 |
To | LP 254 (E INTERSECTION) |
CSJ | 0007-06-265 |
Proj ID | STP 2021(326)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 5.307 | 856755.58 | | 763483.70 | 89.1 |
Work Order | 03-18-21 |
Work Began | 06-14-21 |
Work Completed | |
Time Computed | 04-17-21 |
Contract Working Days | 338 |
Addl Days Granted | 19 |
Working Days Charged | 343 |
Percent Time Used | 96 |
Contractor(s) |
ALTUS CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-097 AVANZA CONSTRUCTION & EARTHWORKS, LLC (2.40) CROWDER CONSTRUCTION CO., INC. (EASTLAND) (1.20) TNT CRANE & RIGGING, INC. (2.40)
|
Contract # | 02213210 |
| Totals | 4992729.72 | 118357.78 | 4642154.29 | 92.9 |
|
County | EASTLAND |
Highway | IH 20 |
From | 1 MI. WEST OF CISCO |
To | 1.2 MI. WEST OF SH 6 |
CSJ | 0007-03-109 |
Proj ID | F 2023(282) |
Work Type | OVERLAY |
|
| | 8087544.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 01-06-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 68 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-109 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12223030 |
| Totals | 8087544.00 | 0.00 | 0.00 | 0.0 |
|
County | EASTLAND |
Highway | SH 112 |
From | AT IH 20 NORTH AND SOUTH FRONTAGE ROADS |
To | . |
CSJ | 0007-04-134 |
Proj ID | F 2022(486) |
Work Type | TRAFFIC CONTROL DEVICES |
|
| | 1693302.70 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 109 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
O. TREVINO CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0007-04-134 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05223023 |
| Totals | 1693302.70 | 0.00 | 0.00 | 0.0 |
|
County | EASTLAND |
Highway | IH 20 |
From | IH 20 AT CR 235 CROSS |
To | . |
CSJ | 0007-06-258 |
Proj ID | BR 2022(597) |
Work Type | BRIDGE WIDENING OR REHABILITATION |
|
| 0.394 | 606937.92 | | 556568.59 | 99.9 |
Work Order | 07-14-22 |
Work Began | 08-09-22 |
Work Completed | |
Time Computed | 08-09-22 |
Contract Working Days | 17 |
Addl Days Granted | 0 |
Working Days Charged | 40 |
Percent Time Used | 235 |
Contractor(s) |
ALTUS CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-258 EPCS ENVIRONMENTAL LLC (37.94)
|
Contract # | 06223032 |
| Totals | 606937.92 | 583.34 | 556568.59 | 99.9 |
|
County | STEPHENS ETC |
Highway | US 180 ETC |
From | .132 MI E OF SH67 |
To | .113 MI E OF FM 207 |
CSJ | 0011-09-075 |
Proj ID | F 2023(156) |
Work Type | SEAL COAT |
|
| 267.321 | 14954532.77 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 105 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
BRANNAN PAVING CO., LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0011-09-075 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11223004 |
| Totals | 14954532.77 | 0.00 | 0.00 | 0.0 |
|
County | COLEMAN |
Highway | US 67 |
From | BROWN C/L |
To | SANTA ANNA CITY LIMITS |
CSJ | 0054-04-111 |
Proj ID | F 2022(599) |
Work Type | WIDEN NON-FREEWAY |
|
| 6.496 | 25640483.25 | | 2163132.57 | 8.4 |
County | BROWN |
Highway | US 67 |
From | 1.5 MI E OF COLEMAN COUNTY LINE |
To | COLEMAN COUNTY LINE |
CSJ | 0054-06-103 |
Proj ID | F 2022(598) |
Work Type | WIDEN NON-FREEWAY |
|
| 1.569 | 1721723.49 | | 155975.83 | 9.0 |
Work Order | 07-11-22 |
Work Began | 10-10-22 |
Work Completed | |
Time Computed | 10-10-22 |
Contract Working Days | 572 |
Addl Days Granted | 0 |
Working Days Charged | 40 |
Percent Time Used | 6 |
Contractor(s) |
DELHUR INDUSTRIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-111 4-WAY HAULERS, LLC (4.31) CEDAR EATERS OF TEXAS (0.58) CONTRACTORS SERVICE, LTD. (0.50) DK CONTRACTING, LLC (0.44) ROADWAY SPECIALTIES, INC. (2.98) STRIPING TECHNOLOGY, L.P. (0.05) TEXAS ALTERNATIVE GRASSER INCORPORATED (0.19) WEST TEXAS ROCK RESOURCES, LLC (0.05)
|
Contract # | 06223206 |
| Totals | 27362206.74 | 716272.69 | 2319108.40 | 8.4 |
|
County | MILLS ETC |
Highway | US 84 ETC |
From | AT LOOP 15 |
To | . |
CSJ | 0054-09-042 |
Proj ID | F 2022(611) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 6.296 | 501967.00 | | 380719.56 | 75.8 |
Work Order | 07-11-22 |
Work Began | 10-31-22 |
Work Completed | |
Time Computed | 10-10-22 |
Contract Working Days | 90 |
Addl Days Granted | 0 |
Working Days Charged | 41 |
Percent Time Used | 45 |
Contractor(s) |
VACA UNDERGROUND UTILITIES INC |
SUBCONTRACTOR(S) FOR CCSJ: 0054-09-042 TOTAL HIGHWAY MAINTENANCE, LLC (2.60)
|
Contract # | 06223031 |
| Totals | 501967.00 | 148810.39 | 380719.56 | 75.8 |
|
County | MCCULLOCH |
Highway | US 87 |
From | BRADY CREEK BRIDGE |
To | .4 MILES WEST OF US 283 |
CSJ | 0070-06-041 |
Proj ID | NH 2B20(071) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 3.547 | 6955456.06 | | 7633257.95 | 99.9 |
County | MCCULLOCH |
Highway | US 87 |
From | AT JACQUELINE RUFFIN ROAD |
To | . |
CSJ | 0070-06-052 |
Proj ID | NH 2B20(071) |
Work Type | LANDSCAPE & SCENIC ENHANCEMENT |
|
| | 100625.00 | | 100625.00 | 99.9 |
Work Order | 01-14-21 |
Work Began | 03-15-21 |
Work Completed | |
Time Computed | 03-15-21 |
Contract Working Days | 298 |
Addl Days Granted | 0 |
Working Days Charged | 286 |
Percent Time Used | 95 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0070-06-041 JR WEST TEXAS CONCRETE LLC (10.63) L&H ELECTRICAL, LLC (3.87) D. I. J. CONSTRUCTION, INC. (2.97) DALLAS LITE AND BARRICADE, INC. (0.60) TIGHT LINE CONSTRUCTION, LLC (0.51) MPB, INC. (0.67) 1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.03) WEST TEXAS ROCK RESOURCES, LLC (0.25) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.08) K. L. DURHAM CONSTRUCTION, L.L.C. (0.33) CHEROKEE SERVICES (0.67) HJC FARMS, INC. (0.09)
|
Contract # | 12203209 |
| Totals | 7056081.06 | 3500.00 | 7733882.95 | 99.9 |
|
County | BROWN |
Highway | US 67 |
From | AT FORT WORTH & WESTERN RAILROAD |
To | . |
CSJ | 0079-01-038 |
Proj ID | C 79-1-38 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 0.210 | 3046555.05 | | 1834281.64 | 60.2 |
Work Order | 02-16-22 |
Work Began | 05-23-22 |
Work Completed | |
Time Computed | 05-17-22 |
Contract Working Days | 131 |
Addl Days Granted | 40 |
Working Days Charged | 116 |
Percent Time Used | 67 |
Contractor(s) |
PRATER DIRT WORK LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0079-01-038 CONTRACTORS SERVICE, LTD. (0.54) D. I. J. CONSTRUCTION, INC. (1.50) HJC FARMS, INC. (2.42) J. H. ODEN CONTRACTING COMPANY (0.57) PINNACLE GRINDING AND GROOVING LLC (0.14) TEX OP CONSTRUCTION, LP (1.15) GRIDER PAVING LLC (18.19) J & M CONTRACTING, COMPANY (7.48)
|
Contract # | 01223010 |
| Totals | 3046555.05 | 366585.90 | 1834281.64 | 60.2 |
|
County | COMANCHE |
Highway | US 67 |
From | US 67 |
To | AT FM 3381 |
CSJ | 0079-03-051 |
Proj ID | F 2021(766) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 850894.76 | | 628254.26 | 75.1 |
Work Order | 09-16-21 |
Work Began | 02-07-22 |
Work Completed | |
Time Computed | 12-15-21 |
Contract Working Days | 75 |
Addl Days Granted | 0 |
Working Days Charged | 94 |
Percent Time Used | 125 |
Contractor(s) |
JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 0079-03-051 NORTHEASTERN PAVERS, LLC (20.73) JR WEST TEXAS CONCRETE LLC (5.93) TRP CONSTRUCTION GROUP, LLC (2.00) L&H ELECTRICAL, LLC (14.41) TEXAS ALTERNATIVE GRASSER INCORPORATED (0.49) WILLIS ELECTRIC CO., LP (18.21) FIBER-TEX (0.00)
|
Contract # | 08213255 |
| Totals | 850894.76 | 0.00 | 628254.26 | 75.1 |
|
County | COLEMAN |
Highway | US 283 |
From | CR 256 |
To | DRY CREEK |
CSJ | 0099-01-035 |
Proj ID | STP 2022(260)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 3.126 | 3177408.86 | | 1124246.20 | 35.3 |
Work Order | 02-16-22 |
Work Began | 05-17-22 |
Work Completed | |
Time Computed | 05-17-22 |
Contract Working Days | 199 |
Addl Days Granted | 0 |
Working Days Charged | 135 |
Percent Time Used | 67 |
Contractor(s) |
J. H. STRAIN & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0099-01-035 DELGADO"S CONTRACTORS, LLC (5.76) DIIBS SPECIALISTS, LLC (3.35) PINNACLE GRINDING AND GROOVING LLC (0.29) CONTRACTORS SERVICE, LTD. (0.75) D. I. J. CONSTRUCTION, INC. (1.40) HJC FARMS, INC. (3.42)
|
Contract # | 01223214 |
| Totals | 3177408.86 | 91484.50 | 1124246.20 | 35.3 |
|
County | EASTLAND |
Highway | US 183 |
From | RISING STAR NCL |
To | NEAR SH 36 |
CSJ | 0127-02-142 |
Proj ID | STP 2018(829) |
Work Type | RECONSTRUCT URBAN ROADWAY |
|
| 1.476 | 11116710.55 | | 10814117.17 | 97.3 |
County | EASTLAND |
Highway | US 183 |
From | RISING STAR NCL |
To | NEAR SH 36 |
CSJ | 0127-02-146 |
Proj ID | STP 2018(212) |
Work Type | ACQUISITION AND UTILITY ADJUSTMENTS |
|
| 0.809 | 3038242.00 | | 3045789.47 | 99.9 |
County | EASTLAND |
Highway | US 183 |
From | NEAR SH 36 |
To | NEAR RISING STAR SCL |
CSJ | 0127-02-147 |
Proj ID | STP 2018(211) |
Work Type | UTILITY ADJUSTMENTS |
|
| 0.667 | 2732059.00 | | 5292299.83 | 99.9 |
Work Order | 06-11-18 |
Work Began | 08-17-18 |
Work Completed | |
Time Computed | 08-10-18 |
Contract Working Days | 790 |
Addl Days Granted | 246 |
Working Days Charged | 1,044 |
Percent Time Used | 100 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-142 F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (1.37) TTG UTILITIES, LP (23.02) WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.25) W.S. CONSTRUCTION COMPANY (24.13) FLASHER EQUIPMENT COMPANY (0.97) NIXON ENGINEERING (0.00) DALLAS LITE AND BARRICADE, INC. (0.01) 4-WAY HAULERS, LLC (0.07) CRUZ HERNANDEZ CONCRETE CONSTRUCTION (13.15)
|
Contract # | 05183221 |
| Totals | 16887011.55 | 55985.00 | 19152206.47 | 99.9 |
|
County | BROWN |
Highway | US 377 |
From | FM 2524 |
To | 18TH ST |
CSJ | 0128-01-111 |
Proj ID | F 2022(487) |
Work Type | WIDEN NON-FREEWAY |
|
| 1.596 | 4045900.20 | | 122095.00 | 3.0 |
Work Order | 08-25-22 |
Work Began | 11-28-22 |
Work Completed | |
Time Computed | 11-23-22 |
Contract Working Days | 149 |
Addl Days Granted | 0 |
Working Days Charged | 13 |
Percent Time Used | 8 |
Contractor(s) |
PRATER DIRT WORK LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0128-01-111 WILLIS ELECTRIC CO., LP (9.05) FUSION COMMUNICATIONS, LLC (0.00) D. I. J. CONSTRUCTION, INC. (3.61) TEXOP CONSTRUCTION (1.80) JR WEST TEXAS CONCRETE LLC (12.42)
|
Contract # | 05223224 |
| Totals | 4045900.20 | 88110.00 | 122095.00 | 3.0 |
|
County | EASTLAND |
Highway | SH 36 |
From | 0.003 MI. W. OF E MILLS ST |
To | COMANCHE C/L |
CSJ | 0182-01-017 |
Proj ID | F 2021(451)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 3.924 | 290281.85 | | 415875.86 | 99.9 |
County | COMANCHE |
Highway | SH 36 |
From | EASTLAND C/L |
To | 0.322 MI. NW OF BARNES AVE |
CSJ | 0182-02-043 |
Proj ID | F 2021(451)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 20.421 | 818111.09 | | 1056975.98 | 99.9 |
County | COMANCHE |
Highway | SH 36 |
From | US 67 |
To | HAMILTON C/L |
CSJ | 0183-01-044 |
Proj ID | F 2021(451)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 22.272 | 989791.08 | | 1598214.06 | 99.9 |
Work Order | 05-14-21 |
Work Began | 11-15-21 |
Work Completed | |
Time Computed | 06-13-21 |
Contract Working Days | 176 |
Addl Days Granted | 33 |
Working Days Charged | 165 |
Percent Time Used | 78 |
Contractor(s) |
3LW CIVIL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0182-01-017 SAFETY COP, LLC (5.70)
|
Contract # | 04213221 |
| Totals | 2098184.02 | 20327.00 | 3071065.90 | 99.9 |
|
County | COMANCHE |
Highway | SH 36 |
From | AT US 67 |
To | . |
CSJ | 0183-01-049 |
Proj ID | F 2021(452) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 68732.93 | | 63370.50 | 99.9 |
County | EASTLAND |
Highway | SH 16 |
From | AT FM 8 |
To | . |
CSJ | 0288-03-033 |
Proj ID | F 2021(452) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 130520.81 | | 104618.81 | 80.1 |
Work Order | 05-27-21 |
Work Began | 11-30-21 |
Work Completed | |
Time Computed | 08-25-21 |
Contract Working Days | 51 |
Addl Days Granted | 1 |
Working Days Charged | 69 |
Percent Time Used | 132 |
Contractor(s) |
SEFBO PIPELINE BRIDGE, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-049 SERVICES UNLIMITED (10.61) WG ENGINEERING & CONSTRUCTION, LLC (43.07)
|
Contract # | 04213028 |
| Totals | 199253.74 | 5006.35 | 167989.31 | 89.3 |
|
County | COMANCHE |
Highway | SH 36 |
From | 0.3 MILES NORTH OF FM 1702 |
To | 0.34 MILES SOUTH OF FM 1702 |
CSJ | 0183-01-053 |
Proj ID | F 2021(767) |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| 0.650 | 999893.62 | | 1049222.81 | 99.9 |
County | COMANCHE |
Highway | SH 36 |
From | 1.87 MI N OF FM 1702 |
To | .4 MI S OF FM 1702 |
CSJ | 0183-01-055 |
Proj ID | F 2021(767) |
Work Type | OVERLAY |
|
| 2.140 | 557701.88 | | 510596.10 | 91.5 |
Work Order | 09-16-21 |
Work Began | 02-09-22 |
Work Completed | |
Time Computed | 10-16-21 |
Contract Working Days | 114 |
Addl Days Granted | 0 |
Working Days Charged | 124 |
Percent Time Used | 108 |
Contractor(s) |
JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-053 D. I. J. CONSTRUCTION, INC. (1.91) JR WEST TEXAS CONCRETE LLC (3.68) NORTHEASTERN PAVERS, LLC (47.82) TEXAS ALTERNATIVE GRASSER INCORPORATED (0.29) WILLIS ELECTRIC CO., LP (2.76) PINNACLE GRINDING AND GROOVING LLC (0.43)
|
Contract # | 08213047 |
| Totals | 1557595.50 | 0.00 | 1559818.91 | 99.9 |
|
County | EASTLAND |
Highway | SH 6 |
From | IH 20 |
To | SL 389 |
CSJ | 0257-03-033 |
Proj ID | C 257-3-33 |
Work Type | SUPER-2 HIGHWAY |
|
| 8.043 | 10087854.94 | | 2042033.27 | 20.2 |
Work Order | 02-23-22 |
Work Began | 09-06-22 |
Work Completed | |
Time Computed | 05-24-22 |
Contract Working Days | 223 |
Addl Days Granted | 0 |
Working Days Charged | 70 |
Percent Time Used | 31 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0257-03-033 4-WAY HAULERS, LLC (6.87) D. I. J. CONSTRUCTION, INC. (1.50) DUSTIN ALLEN, INC. (1.43) PINNACLE GRINDING AND GROOVING LLC (0.18) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.47) STRUCTURAL INTEGRITY GROUP LLC (0.70) DALLAS LITE AND BARRICADE, INC. (0.19) MARCOM"S MOWING SERVICE, LLC (0.23) FC TRAFFIC CONTROL, INC. (0.36)
|
Contract # | 01223035 |
| Totals | 10087854.94 | 100301.88 | 2042033.27 | 20.2 |
|
County | EASTLAND |
Highway | SH 6 |
From | SL 389 |
To | 0.18 MI. N. OF CRESSENT ST |
CSJ | 0257-04-029 |
Proj ID | F 2022(007) |
Work Type | SUPER-2 HIGHWAY |
|
| 8.947 | 10587368.26 | | 6147207.22 | 57.9 |
Work Order | 10-20-21 |
Work Began | 02-23-22 |
Work Completed | |
Time Computed | 12-19-21 |
Contract Working Days | 230 |
Addl Days Granted | 0 |
Working Days Charged | 162 |
Percent Time Used | 70 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0257-04-029 COMEN ENTERPRISE LLC (1.51) PINNACLE GRINDING AND GROOVING LLC (0.21) TRP CONSTRUCTION GROUP, LLC (1.61) TEXAS TRAFFIC AND BARRICADE, LLC (0.19) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.54) 4-WAY HAULERS, LLC (6.08)
|
Contract # | 09213204 |
| Totals | 10587368.26 | 532305.03 | 6147207.22 | 57.9 |
|
County | COMANCHE |
Highway | SH 6 |
From | SH 16 NORTH |
To | EAST CITY LIMIT OF DELEON |
CSJ | 0257-05-045 |
Proj ID | C 257-5-45 |
Work Type | WIDEN NON-FREEWAY |
|
| 1.931 | 9728370.40 | | 6297572.24 | 64.7 |
County | COMANCHE |
Highway | SH 6 |
From | SH 16 NORTH |
To | EAST CITY LIMIT OF DELEON |
CSJ | 0257-05-048 |
Proj ID | ROW 257-5-48 |
Work Type | RIGHT OF WAY |
|
| 1.931 | 558860.00 | | 716490.20 | 99.9 |
Work Order | 07-20-20 |
Work Began | 10-05-20 |
Work Completed | |
Time Computed | 09-18-20 |
Contract Working Days | 688 |
Addl Days Granted | 1 |
Working Days Charged | 532 |
Percent Time Used | 77 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0257-05-045 SOUTHERN CROSS CONTRACTORS, LLC (0.64) F & W ELECTRICAL CONTRACTORS, INC. (7.41) FLASHER EQUIPMENT COMPANY (1.25) B & L CONSTRUCTION COMPANY (2.33) SITE BARRICADES (0.00) BUYERS BARRICADES, INC. (0.04) B & L MANHOLE SERVICE (0.01) BCAC UNDERGROUND LLC (0.00) TEXAS ALTERNATIVE GRASSER INCORPORATED (0.03) 4-WAY HAULERS, LLC (3.88) CRUZ HERNANDEZ CONCRETE CONSTRUCTION (0.82)
|
Contract # | 05203204 |
| Totals | 10287230.40 | 5873.37 | 7014062.44 | 68.1 |
|
County | COMANCHE ETC |
Highway | SH 6 |
From | EASTLAND COUNTY LINE |
To | SH 16 |
CSJ | 0257-05-046 |
Proj ID | NH 2020(457) |
Work Type | SUPER-2 HIGHWAY |
|
| 18.164 | 13793112.53 | | 7210081.17 | 52.4 |
Work Order | 06-09-20 |
Work Began | 09-08-20 |
Work Completed | |
Time Computed | 08-08-20 |
Contract Working Days | 368 |
Addl Days Granted | 0 |
Working Days Charged | 385 |
Percent Time Used | 104 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0257-05-046 BROCK CONSTRUCTION, LLC (1.32) CONTRACTORS SERVICE COMPANY (0.37) D. I. J. CONSTRUCTION, INC. (2.43) STRIPE-A-ZONE, INC. (0.27) SOUTHERN CROSS CONTRACTORS, LLC (0.60) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.37) W. S. CONSTRUCTION COMPANY (5.68) DIIBS SPECIALISTS, LLC (2.59) DALLAS LITE AND BARRICADE, INC. (1.44) BECK-REIT & SONS, LTD. (0.84) BEAR CREEK CONSTRUCTION, LLC (2.44)
|
Contract # | 04203204 |
| Totals | 13793112.53 | 43806.66 | 7210081.17 | 52.4 |
|