Monthly Local Let Maintenance Report For Brownwood District As Of Nov 10, 2024 Page 3 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCCULLOCH
HighwayUS0377
FromMCCULLOCH MAINTENANCE OFFICE, BRADY TX
ToMCCULLOCH MAINTENANCE OFFICE, BRADY TX
CSJ6447-02-001
Proj IDSUP - 644702001
Work TypeJANITORIAL MAINTENANCE
 
0.01029763.7613952.5846.8
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed12-31-25
Contract Working Days735
Addl Days Granted0
Working Days Charged519
Percent Time Used70
Contractor(s)
WORKQUEST
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6447-02-001
CENTRAL TEXAS MHMR CENTER (0.00)
Contract #05232330
Totals29763.76820.7413952.5846.8

CountyCOLEMAN
HighwaySH0206
FromCOLEMAN MAINTENANCE OFFICE
To***
CSJ6449-21-001
Proj IDSUP - 644921001
Work TypeJANITORIAL MAINTENANCE
 
0.01041500.4827312.0165.8
Work Order00-00-00
Work Began07-01-23
Work Completed
Time Computed12-31-25
Contract Working Days735
Addl Days Granted0
Working Days Charged489
Percent Time Used66
Contractor(s)
WORKQUEST
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6449-21-001
CENTRAL TEXAS MHMR CENTER (0.00)
Contract #06232338
Totals41500.481711.7127312.0165.8

CountyCOMANCHE
HighwaySH0016
FromCOMANCHE COUNTY
ToCOMANCHE COUNTY
CSJ6451-59-001
Proj IDMMC - 645159001
Work TypeHOT-MIX COLD-LAID
 
0.010316805.00273731.0786.4
Work Order00-00-00
Work Began10-25-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted180
Working Days Charged373
Percent Time Used103
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6451-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08232301
Totals316805.000.00273731.0786.4

CountyEASTLAND
HighwaySH0112
FromEASTLAND COUNTY
ToEASTLAND COUNTY
CSJ6451-61-001
Proj IDMMC - 645161001
Work TypeHOT-MIX COLD-LAID
 
0.010292000.00532901.0999.9
Work Order00-00-00
Work Began10-08-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted360
Working Days Charged390
Percent Time Used72
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6451-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08232302
Totals292000.000.00532901.0999.9

CountySTEPHENS
HighwayUS0180
FromSTEPHENS COUNTY
ToSTEPHENS COUNTY
CSJ6451-63-001
Proj IDMMC - 645163001
Work TypeHOT MIX
 
0.010202300.00231431.6599.9
Work Order00-00-00
Work Began10-08-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted360
Working Days Charged390
Percent Time Used72
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6451-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08232303
Totals202300.000.00231431.6599.9

CountyCOLEMAN
HighwayUS0084
FromCOLEMAN COUNTY
To***
CSJ6453-99-001
Proj IDRMC - 645399001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010202977.50102376.0050.4
Work Order00-00-00
Work Began07-15-24
Work Completed
Time Computed12-31-28
Contract Working Days60
Addl Days Granted0
Working Days Charged46
Percent Time Used76
Contractor(s)
TRIPLE T MAINTENANCE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12232301
Totals202977.5011425.30102376.0050.4

CountyBROWN
HighwayUS0183
FromDISTRICT-WIDE
ToDISTRICT-WIDE
CSJ6454-01-001
Proj IDMMC - 645401001
Work TypeWINTER WEATHER MATERIAL
 
0.010298050.4097744.9632.7
Work Order00-00-00
Work Began11-11-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted180
Working Days Charged356
Percent Time Used98
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232303
Totals298050.400.0097744.9632.7

CountyCOLEMAN
HighwaySH0206
FromCOLEMAN COUNTY
ToCOLEMAN COUNTY
CSJ6454-03-001
Proj IDMMC - 645403001
Work TypeHOT MIX
 
0.010246770.000.000.0
Work Order00-00-00
Work Began11-04-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted360
Working Days Charged363
Percent Time Used67
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232304
Totals246770.000.000.000.0

CountyCOMANCHE
HighwaySH0016
FromCOMANCHE COUNTY
ToCOMANCHE COUNTY
CSJ6454-07-001
Proj IDMMC - 645407001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010256907.00514635.4399.9
Work Order00-00-00
Work Began11-04-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted360
Working Days Charged363
Percent Time Used67
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232305
Totals256907.000.00514635.4399.9

CountyLAMPASAS
HighwayUS0281
FromLAMPASAS COUNTY
ToLAMPASAS COUNTY
CSJ6454-09-001
Proj IDMMC - 645409001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010253390.00332169.0199.9
Work Order00-00-00
Work Began11-04-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted360
Working Days Charged363
Percent Time Used67
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232306
Totals253390.000.00332169.0199.9

CountyBROWN
HighwayUS0183
FromDISTRICT-WIDE
ToDISTRICT-WIDE
CSJ6454-57-001
Proj IDMMC - 645457001
Work TypeROCK/RIPRAP
 
0.010135360.0091921.7167.9
Work Order00-00-00
Work Began11-11-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted180
Working Days Charged356
Percent Time Used98
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6454-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232307
Totals135360.000.0091921.7167.9

CountyEASTLAND
HighwayIH0020
FromEASTLAND COUNTY
ToEASTLAND COUNTY
CSJ6454-61-001
Proj IDMMC - 645461001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010264720.00317521.0599.9
Work Order00-00-00
Work Began11-11-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted180
Working Days Charged356
Percent Time Used98
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232308
Totals264720.0039355.92317521.0599.9

CountySTEPHENS
HighwayUS0180
FromSTEPHENS COUNTY
ToSTEPHENS COUNTY
CSJ6454-63-001
Proj IDMMC - 645463001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010274843.75265520.2396.6
Work Order00-00-00
Work Began11-11-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted180
Working Days Charged356
Percent Time Used98
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232309
Totals274843.750.00265520.2396.6

CountyMILLS
HighwayUS0084
FromMILLS COUNTY
ToMILLS COUNTY
CSJ6454-65-001
Proj IDMMC - 645465001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010251318.00559638.4799.9
Work Order00-00-00
Work Began11-04-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted360
Working Days Charged363
Percent Time Used67
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232310
Totals251318.000.00559638.4799.9

CountySAN SABA
HighwayUS0190
FromSAN SABA COUNTY
ToSAN SABA COUNTY
CSJ6454-67-001
Proj IDMMC - 645467001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010247451.75558303.1099.9
Work Order00-00-00
Work Began11-04-23
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted360
Working Days Charged363
Percent Time Used67
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232311
Totals247451.750.00558303.1099.9

CountyCOLEMAN
HighwayUS0084
FromCOLEMAN COUNTY
ToCOLEMAN COUNTY
CSJ6455-03-001
Proj IDSUP - 645503001
Work TypePICNIC AREA MAINTENANCE
 
0.01094956.0043685.2046.0
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days735
Addl Days Granted0
Working Days Charged427
Percent Time Used58
Contractor(s)
WORKQUEST
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6455-03-001
CENTRAL TEXAS MHMR CENTER (0.00)
Contract #08232330
Totals94956.003025.2043685.2046.0

CountyMCCULLOCH
HighwayUS0377
FromMCCULLOCH COUNTY
ToMCCULLOCH COUNTY
CSJ6455-05-001
Proj IDSUP - 645505001
Work TypePICNIC AREA MAINTENANCE
 
0.010101473.0051674.0050.9
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days735
Addl Days Granted0
Working Days Charged427
Percent Time Used58
Contractor(s)
WORKQUEST
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6455-05-001
CENTRAL TEXAS MHMR CENTER (0.00)
Contract #08232331
Totals101473.003072.0051674.0050.9

CountyMILLS
HighwayUS0084
FromMILLS COUNTY MAINTENANCE OFFICE
To***
CSJ6458-63-001
Proj IDSUP - 645863001
Work TypeJANITORIAL MAINTENANCE
 
0.01028052.4015195.0554.1
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed12-31-28
Contract Working Days730
Addl Days Granted0
Working Days Charged397
Percent Time Used54
Contractor(s)
WORKQUEST
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6458-63-001
CENTRAL TEXAS MHMR CENTER (0.00)
Contract #10232330
Totals28052.401168.8515195.0554.1

CountyBROWN
HighwayUS0377
FromBROWN COUNTY
To***
CSJ6459-82-001
Proj IDMMC - 645982001
Work TypeHOT-MIX COLD-LAID
 
0.010281800.0092234.5432.7
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted180
Working Days Charged274
Percent Time Used76
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6459-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12232302
Totals281800.0014329.5392234.5432.7

CountySAN SABA
HighwayUS0190
FromSAN SABA COUNTY
ToSAN SABA COUNTY
CSJ6459-85-001
Proj IDSUP - 645985001
Work TypePICNIC AREA MAINTENANCE
 
0.010106505.0047898.0044.9
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed12-31-28
Contract Working Days735
Addl Days Granted0
Working Days Charged366
Percent Time Used49
Contractor(s)
WORKQUEST
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6459-85-001
ALDERSGATE ENRICHMENT CENTER, INC. (0.00)
Contract #10232333
Totals106505.004242.0047898.0044.9

page 1 | page 2 | page 3 | page 4