| Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
| County | MCCULLOCH |
| Highway | US0377 |
| From | MCCULLOCH MAINTENANCE OFFICE, BRADY TX |
| To | MCCULLOCH MAINTENANCE OFFICE, BRADY TX |
| CSJ | 6447-02-001 |
| Proj ID | SUP - 644702001 |
| Work Type | JANITORIAL MAINTENANCE |
| |
| 0.010 | 29763.76 | | 13952.58 | 46.8 |
| Work Order | 00-00-00 |
| Work Began | 06-01-23 |
| Work Completed | |
| Time Computed | 12-31-25 |
| Contract Working Days | 735 |
| Addl Days Granted | 0 |
| Working Days Charged | 519 |
| Percent Time Used | 70 |
| Contractor(s) |
WORKQUEST CENTRAL TEXAS MHMR CENTER |
SUBCONTRACTOR(S) FOR CCSJ: 6447-02-001 CENTRAL TEXAS MHMR CENTER (0.00)
|
| Contract # | 05232330 |
| Totals | 29763.76 | 820.74 | 13952.58 | 46.8 |
|
| County | COLEMAN |
| Highway | SH0206 |
| From | COLEMAN MAINTENANCE OFFICE |
| To | *** |
| CSJ | 6449-21-001 |
| Proj ID | SUP - 644921001 |
| Work Type | JANITORIAL MAINTENANCE |
| |
| 0.010 | 41500.48 | | 27312.01 | 65.8 |
| Work Order | 00-00-00 |
| Work Began | 07-01-23 |
| Work Completed | |
| Time Computed | 12-31-25 |
| Contract Working Days | 735 |
| Addl Days Granted | 0 |
| Working Days Charged | 489 |
| Percent Time Used | 66 |
| Contractor(s) |
WORKQUEST CENTRAL TEXAS MHMR CENTER |
SUBCONTRACTOR(S) FOR CCSJ: 6449-21-001 CENTRAL TEXAS MHMR CENTER (0.00)
|
| Contract # | 06232338 |
| Totals | 41500.48 | 1711.71 | 27312.01 | 65.8 |
|
| County | COMANCHE |
| Highway | SH0016 |
| From | COMANCHE COUNTY |
| To | COMANCHE COUNTY |
| CSJ | 6451-59-001 |
| Proj ID | MMC - 645159001 |
| Work Type | HOT-MIX COLD-LAID |
| |
| 0.010 | 316805.00 | | 273731.07 | 86.4 |
| Work Order | 00-00-00 |
| Work Began | 10-25-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 180 |
| Working Days Charged | 373 |
| Percent Time Used | 103 |
| Contractor(s) |
| ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 6451-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08232301 |
| Totals | 316805.00 | 0.00 | 273731.07 | 86.4 |
|
| County | EASTLAND |
| Highway | SH0112 |
| From | EASTLAND COUNTY |
| To | EASTLAND COUNTY |
| CSJ | 6451-61-001 |
| Proj ID | MMC - 645161001 |
| Work Type | HOT-MIX COLD-LAID |
| |
| 0.010 | 292000.00 | | 532901.09 | 99.9 |
| Work Order | 00-00-00 |
| Work Began | 10-08-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 360 |
| Working Days Charged | 390 |
| Percent Time Used | 72 |
| Contractor(s) |
| ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 6451-61-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08232302 |
| Totals | 292000.00 | 0.00 | 532901.09 | 99.9 |
|
| County | STEPHENS |
| Highway | US0180 |
| From | STEPHENS COUNTY |
| To | STEPHENS COUNTY |
| CSJ | 6451-63-001 |
| Proj ID | MMC - 645163001 |
| Work Type | HOT MIX |
| |
| 0.010 | 202300.00 | | 231431.65 | 99.9 |
| Work Order | 00-00-00 |
| Work Began | 10-08-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 360 |
| Working Days Charged | 390 |
| Percent Time Used | 72 |
| Contractor(s) |
| ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 6451-63-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 08232303 |
| Totals | 202300.00 | 0.00 | 231431.65 | 99.9 |
|
| County | COLEMAN |
| Highway | US0084 |
| From | COLEMAN COUNTY |
| To | *** |
| CSJ | 6453-99-001 |
| Proj ID | RMC - 645399001 |
| Work Type | MOWING HIGHWAY RIGHT OF WAY |
| |
| 0.010 | 202977.50 | | 102376.00 | 50.4 |
| Work Order | 00-00-00 |
| Work Began | 07-15-24 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 60 |
| Addl Days Granted | 0 |
| Working Days Charged | 46 |
| Percent Time Used | 76 |
| Contractor(s) |
| TRIPLE T MAINTENANCE INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6453-99-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12232301 |
| Totals | 202977.50 | 11425.30 | 102376.00 | 50.4 |
|
| County | BROWN |
| Highway | US0183 |
| From | DISTRICT-WIDE |
| To | DISTRICT-WIDE |
| CSJ | 6454-01-001 |
| Proj ID | MMC - 645401001 |
| Work Type | WINTER WEATHER MATERIAL |
| |
| 0.010 | 298050.40 | | 97744.96 | 32.7 |
| Work Order | 00-00-00 |
| Work Began | 11-11-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 180 |
| Working Days Charged | 356 |
| Percent Time Used | 98 |
| Contractor(s) |
| SOUTHWEST ENVIROTX PARTNERS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6454-01-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09232303 |
| Totals | 298050.40 | 0.00 | 97744.96 | 32.7 |
|
| County | COLEMAN |
| Highway | SH0206 |
| From | COLEMAN COUNTY |
| To | COLEMAN COUNTY |
| CSJ | 6454-03-001 |
| Proj ID | MMC - 645403001 |
| Work Type | HOT MIX |
| |
| 0.010 | 246770.00 | | 0.00 | 0.0 |
| Work Order | 00-00-00 |
| Work Began | 11-04-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 360 |
| Working Days Charged | 363 |
| Percent Time Used | 67 |
| Contractor(s) |
| VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6454-03-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09232304 |
| Totals | 246770.00 | 0.00 | 0.00 | 0.0 |
|
| County | COMANCHE |
| Highway | SH0016 |
| From | COMANCHE COUNTY |
| To | COMANCHE COUNTY |
| CSJ | 6454-07-001 |
| Proj ID | MMC - 645407001 |
| Work Type | LIMESTONE ROCK ASPHALT |
| |
| 0.010 | 256907.00 | | 514635.43 | 99.9 |
| Work Order | 00-00-00 |
| Work Began | 11-04-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 360 |
| Working Days Charged | 363 |
| Percent Time Used | 67 |
| Contractor(s) |
| VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6454-07-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09232305 |
| Totals | 256907.00 | 0.00 | 514635.43 | 99.9 |
|
| County | LAMPASAS |
| Highway | US0281 |
| From | LAMPASAS COUNTY |
| To | LAMPASAS COUNTY |
| CSJ | 6454-09-001 |
| Proj ID | MMC - 645409001 |
| Work Type | LIMESTONE ROCK ASPHALT |
| |
| 0.010 | 253390.00 | | 332169.01 | 99.9 |
| Work Order | 00-00-00 |
| Work Began | 11-04-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 360 |
| Working Days Charged | 363 |
| Percent Time Used | 67 |
| Contractor(s) |
| VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6454-09-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09232306 |
| Totals | 253390.00 | 0.00 | 332169.01 | 99.9 |
|
| County | BROWN |
| Highway | US0183 |
| From | DISTRICT-WIDE |
| To | DISTRICT-WIDE |
| CSJ | 6454-57-001 |
| Proj ID | MMC - 645457001 |
| Work Type | ROCK/RIPRAP |
| |
| 0.010 | 135360.00 | | 91921.71 | 67.9 |
| Work Order | 00-00-00 |
| Work Began | 11-11-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 180 |
| Working Days Charged | 356 |
| Percent Time Used | 98 |
| Contractor(s) |
| ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 6454-57-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09232307 |
| Totals | 135360.00 | 0.00 | 91921.71 | 67.9 |
|
| County | EASTLAND |
| Highway | IH0020 |
| From | EASTLAND COUNTY |
| To | EASTLAND COUNTY |
| CSJ | 6454-61-001 |
| Proj ID | MMC - 645461001 |
| Work Type | LIMESTONE ROCK ASPHALT |
| |
| 0.010 | 264720.00 | | 317521.05 | 99.9 |
| Work Order | 00-00-00 |
| Work Began | 11-11-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 180 |
| Working Days Charged | 356 |
| Percent Time Used | 98 |
| Contractor(s) |
| MARTIN MARIETTA MATERIALS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6454-61-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09232308 |
| Totals | 264720.00 | 39355.92 | 317521.05 | 99.9 |
|
| County | STEPHENS |
| Highway | US0180 |
| From | STEPHENS COUNTY |
| To | STEPHENS COUNTY |
| CSJ | 6454-63-001 |
| Proj ID | MMC - 645463001 |
| Work Type | LIMESTONE ROCK ASPHALT |
| |
| 0.010 | 274843.75 | | 265520.23 | 96.6 |
| Work Order | 00-00-00 |
| Work Began | 11-11-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 180 |
| Working Days Charged | 356 |
| Percent Time Used | 98 |
| Contractor(s) |
| MARTIN MARIETTA MATERIALS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6454-63-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09232309 |
| Totals | 274843.75 | 0.00 | 265520.23 | 96.6 |
|
| County | MILLS |
| Highway | US0084 |
| From | MILLS COUNTY |
| To | MILLS COUNTY |
| CSJ | 6454-65-001 |
| Proj ID | MMC - 645465001 |
| Work Type | LIMESTONE ROCK ASPHALT |
| |
| 0.010 | 251318.00 | | 559638.47 | 99.9 |
| Work Order | 00-00-00 |
| Work Began | 11-04-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 360 |
| Working Days Charged | 363 |
| Percent Time Used | 67 |
| Contractor(s) |
| VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6454-65-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09232310 |
| Totals | 251318.00 | 0.00 | 559638.47 | 99.9 |
|
| County | SAN SABA |
| Highway | US0190 |
| From | SAN SABA COUNTY |
| To | SAN SABA COUNTY |
| CSJ | 6454-67-001 |
| Proj ID | MMC - 645467001 |
| Work Type | LIMESTONE ROCK ASPHALT |
| |
| 0.010 | 247451.75 | | 558303.10 | 99.9 |
| Work Order | 00-00-00 |
| Work Began | 11-04-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 360 |
| Working Days Charged | 363 |
| Percent Time Used | 67 |
| Contractor(s) |
| VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6454-67-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 09232311 |
| Totals | 247451.75 | 0.00 | 558303.10 | 99.9 |
|
| County | COLEMAN |
| Highway | US0084 |
| From | COLEMAN COUNTY |
| To | COLEMAN COUNTY |
| CSJ | 6455-03-001 |
| Proj ID | SUP - 645503001 |
| Work Type | PICNIC AREA MAINTENANCE |
| |
| 0.010 | 94956.00 | | 43685.20 | 46.0 |
| Work Order | 00-00-00 |
| Work Began | 09-01-23 |
| Work Completed | |
| Time Computed | 09-01-23 |
| Contract Working Days | 735 |
| Addl Days Granted | 0 |
| Working Days Charged | 427 |
| Percent Time Used | 58 |
| Contractor(s) |
WORKQUEST CENTRAL TEXAS MHMR CENTER |
SUBCONTRACTOR(S) FOR CCSJ: 6455-03-001 CENTRAL TEXAS MHMR CENTER (0.00)
|
| Contract # | 08232330 |
| Totals | 94956.00 | 3025.20 | 43685.20 | 46.0 |
|
| County | MCCULLOCH |
| Highway | US0377 |
| From | MCCULLOCH COUNTY |
| To | MCCULLOCH COUNTY |
| CSJ | 6455-05-001 |
| Proj ID | SUP - 645505001 |
| Work Type | PICNIC AREA MAINTENANCE |
| |
| 0.010 | 101473.00 | | 51674.00 | 50.9 |
| Work Order | 00-00-00 |
| Work Began | 09-01-23 |
| Work Completed | |
| Time Computed | 09-01-23 |
| Contract Working Days | 735 |
| Addl Days Granted | 0 |
| Working Days Charged | 427 |
| Percent Time Used | 58 |
| Contractor(s) |
WORKQUEST CENTRAL TEXAS MHMR CENTER |
SUBCONTRACTOR(S) FOR CCSJ: 6455-05-001 CENTRAL TEXAS MHMR CENTER (0.00)
|
| Contract # | 08232331 |
| Totals | 101473.00 | 3072.00 | 51674.00 | 50.9 |
|
| County | MILLS |
| Highway | US0084 |
| From | MILLS COUNTY MAINTENANCE OFFICE |
| To | *** |
| CSJ | 6458-63-001 |
| Proj ID | SUP - 645863001 |
| Work Type | JANITORIAL MAINTENANCE |
| |
| 0.010 | 28052.40 | | 15195.05 | 54.1 |
| Work Order | 00-00-00 |
| Work Began | 10-01-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 730 |
| Addl Days Granted | 0 |
| Working Days Charged | 397 |
| Percent Time Used | 54 |
| Contractor(s) |
WORKQUEST CENTRAL TEXAS MHMR CENTER |
SUBCONTRACTOR(S) FOR CCSJ: 6458-63-001 CENTRAL TEXAS MHMR CENTER (0.00)
|
| Contract # | 10232330 |
| Totals | 28052.40 | 1168.85 | 15195.05 | 54.1 |
|
| County | BROWN |
| Highway | US0377 |
| From | BROWN COUNTY |
| To | *** |
| CSJ | 6459-82-001 |
| Proj ID | MMC - 645982001 |
| Work Type | HOT-MIX COLD-LAID |
| |
| 0.010 | 281800.00 | | 92234.54 | 32.7 |
| Work Order | 00-00-00 |
| Work Began | 02-01-24 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 180 |
| Addl Days Granted | 180 |
| Working Days Charged | 274 |
| Percent Time Used | 76 |
| Contractor(s) |
| ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 6459-82-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # | 12232302 |
| Totals | 281800.00 | 14329.53 | 92234.54 | 32.7 |
|
| County | SAN SABA |
| Highway | US0190 |
| From | SAN SABA COUNTY |
| To | SAN SABA COUNTY |
| CSJ | 6459-85-001 |
| Proj ID | SUP - 645985001 |
| Work Type | PICNIC AREA MAINTENANCE |
| |
| 0.010 | 106505.00 | | 47898.00 | 44.9 |
| Work Order | 00-00-00 |
| Work Began | 11-01-23 |
| Work Completed | |
| Time Computed | 12-31-28 |
| Contract Working Days | 735 |
| Addl Days Granted | 0 |
| Working Days Charged | 366 |
| Percent Time Used | 49 |
| Contractor(s) |
WORKQUEST ALDERSGATE ENRICHMENT CENTER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6459-85-001 ALDERSGATE ENRICHMENT CENTER, INC. (0.00)
|
| Contract # | 10232333 |
| Totals | 106505.00 | 4242.00 | 47898.00 | 44.9 |
|