Monthly State Let Construction Report For Childress District As Of Jan 10, 2023 Page 1 Of 1

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWHEELER
HighwayUS 83
FromCR 15, SOUTH
ToCOLLINGSWORTH C/L
CSJ0031-01-022
Proj IDF 2023(283)
Work TypeSUPER-2 HIGHWAY
 
2011072.010.000.0
CountyCOLLINGSWORTH
HighwayUS 83
FromWHEELER C/L, SOUTH
To7.551 MILES
CSJ0031-02-029
Proj IDF 2023(283)
Work TypeSUPER-2 HIGHWAY
 
6427152.760.000.0
CountyCOLLINGSWORTH
HighwayUS 83
From7.551 MILES SOUTH OF WHEELER C/L, S
ToFM 1439
CSJ0031-03-044
Proj IDF 2023(283)
Work TypeSUPER-2 HIGHWAY
 
3753664.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days237
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0031-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223209
Totals12191889.220.000.000.0

CountyCHILDRESS ETC
HighwayUS 62 ETC
From@ PRAIRIE DOG TOWN FORK RED RIVER
To.
CSJ0031-05-045
Proj IDBR 2021(604)
Work TypeBRIDGE MAINTENANCE
 
4197227.704139659.4398.6
Work Order07-20-21
Work Began09-14-21
Work Completed
Time Computed08-20-21
Contract Working Days348
Addl Days Granted23
Working Days Charged287
Percent Time Used77
Contractor(s)
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0031-05-045
BARRICADES UNLIMITED (5.95)
DUSTROL, INC. (0.24)
HUNTER DEMOLITION & WRECKING CORPORATION (0.78)
S & S BRIDGE PAINTING, INC. (0.60)
GERDAN SLIPFORMING INC (0.60)
SPENCER PIER DRILLING CO (0.66)
KEYSTONE SERVICES, INC. (0.33)
Contract #06213021
Totals4197227.70199080.004139659.4398.6

CountyCHILDRESS
HighwayUS 83
From1440' SOUTH OF US 62, NORTH
To1795' NORTH OF SH 256
CSJ0031-05-046
Proj IDF 2023(052)
Work TypeOVERLAY
 
2152293.050.000.0
CountyCHILDRESS
HighwayUS 62
FromCOTTLE C/L, NORTH
ToFM 164
CSJ0032-01-034
Proj IDF 2023(052)
Work TypeOVERLAY
 
5313966.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days101
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0031-05-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09223007
Totals7466259.690.000.000.0

CountyHALL
HighwayUS 287
From348' SOUTH OF 2ND STREET, SOUTH
To1.718 MILES
CSJ0042-09-124
Proj IDC 42-9-124
Work TypeNEW LOCATION FREEWAY
 
13478722.758325495.9961.7
Work Order06-22-21
Work Began08-23-21
Work Completed
Time Computed07-22-21
Contract Working Days420
Addl Days Granted19
Working Days Charged282
Percent Time Used64
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0042-09-124
BARRICADES UNLIMITED (0.98)
J. H. ODEN CONTRACTING COMPANY (0.82)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36)
URBAN INFRACONSTRUCTION LLC (3.99)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
WILLIS ELECTRIC CO., LP (0.89)
HOLMES CONSTRUCTION CO., L.P. (0.41)
WILLIAMS ROAD, LLC (0.11)
B&B TRUCKING (0.44)
HODGES AND SON CONSTRUCTION COMPANY, INC. (1.78)
TORO BRAVO CONSTRUCTION, LLC (0.08)
TORO BRAVO CONSTRUCTION, LLC (0.37)
MCINTOSH FLOW SERVICE LLC (0.07)
PANHANDLE SWEEPING & MAINTENANCE, LLC (0.02)
A.W. THEIS (0.07)
FUQUAY, INC. (7.35)
TEXAS GUARDRAIL CONTRACTORS LLC (0.27)
POPWELL, INC (0.14)
PINNACLE GRINDING AND GROOVING LLC (0.06)
STRAIGHT LINE SAWING & SEALING, INC. (0.03)
Contract #05213206
Totals13478722.75261945.488325495.9961.7

CountyCHILDRESS
HighwayUS 287
From335' EAST OF FM 2530, EAST
ToHARDEMAN C/L (NBL)
CSJ0043-01-083
Proj IDBR 2023(360)
Work TypeOVERLAY
 
6175663.870.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223035
Totals6175663.870.000.000.0

CountyKNOX
HighwaySH 6
FromSOUTH WICHITA RIVER BRIDGE, SOUTH
To200' N OF US 82
CSJ0098-04-036
Proj IDF 2023(051)
Work TypeREHABILITATION OF EXISTING ROAD
 
2633873.990.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0098-04-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09223213
Totals2633873.990.000.000.0

CountyKNOX
HighwaySH 6
FromUS 82, SOUTH
ToFM 2534
CSJ0098-05-034
Proj IDF 2023(357)
Work TypeREHABILITATION OF EXISTING ROAD
 
4247603.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days143
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0098-05-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223034
Totals4247603.880.000.000.0

CountyKING
HighwayUS 82
From0.5 MILES WEST OF SH 222, EAST
ToKNOX C/L
CSJ0133-01-049
Proj IDF 2022(352)
Work TypeREHABILITATION OF EXISTING ROAD
 
5768975.82213302.803.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days141
Addl Days Granted0
Working Days Charged25
Percent Time Used17
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-01-049
STRIPING TECHNOLOGY, L.P. (3.44)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.18)
WEST TEXAS ROCK RESOURCES, LLC (0.16)
CONTRACTORS SERVICE, LTD. (0.42)
Contract #01223042
Totals5768975.827000.00213302.803.6

CountyKNOX
HighwayUS 82
From758' WEST OF FM 267 (N INT), EAST
ToBAYLOR C/L
CSJ0133-03-038
Proj IDNH 2020(738)
Work TypeSUPER-2 HIGHWAY
 
11.94112684227.536982905.0055.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-20
Work Began11-04-20
Work Completed
Time Computed00-00-00
Contract Working Days320
Addl Days Granted43
Working Days Charged407
Percent Time Used112
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-03-038
CONTRACTORS SERVICE COMPANY (0.47)
DUSTIN ALLEN, INC. (0.19)
MARCOM"S MOWING SERVICE, LLC (0.24)
W. S. CONSTRUCTION COMPANY (1.44)
BARRICADES UNLIMITED (1.89)
WEST TEXAS ROCK RESOURCES, LLC (0.10)
WILLIS ELECTRIC CO., LP (0.27)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.38)
M.A.R. TRUCKING (0.31)
COLD CREEK CONSTRUCTION, LTD (0.65)
BOBBY ROBERTSON, INC. (0.07)
Contract #07203011
Totals12684227.5316705.006982905.0055.3

CountyKNOX
HighwayUS 82
FromWESTBOUND, EAST OF BENJAMIN
To.
CSJ0133-03-047
Proj IDSTP 2019(772)
Work TypeSAFETY REST AREA
 
0.1012268300.002366107.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted146
Working Days Charged381
Percent Time Used98
Contractor(s)
ANTHONY INMAN CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-03-047
WILSON CONTRACTING (16.43)
FERGUSON-VERESH, INC. (13.97)
BREEGLE BUILDING PRODUCTS, INC. (1.44)
CHENEY ELECTRIC, LLC (5.36)
ARMORED ROOFING COMPANY, INC. (2.19)
BNR CONCRETE POLISHING, LLC (0.17)
W.P. HOWLE MASONRY CONTRACTOR, INC. (1.60)
COMMERCIAL & INDUSTRIAL ELECTRONICS, INC. (2.32)
RHS CONSTRUCTION SERVICES, LLC (0.70)
WICHITA GLASS AND MIRROR COMPANY (5.04)
Contract #05193025
Totals2268300.0021907.212366107.4099.9

CountyBRISCOE ETC
HighwaySH 86 ETC
FromSILVERTON ECL, EAST
To5.325 MILES WEST OF FM 1065
CSJ0303-03-050
Proj IDF 2023(160)
Work TypeSEAL COAT
 
6118097.48462944.007.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days58
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0303-03-050
FLAT LINE, INC. (2.84)
BARRICADES PLUS, LLC (0.75)
Contract #10223013
Totals6118097.48462944.00462944.007.5

CountyCHILDRESS
HighwayFM 268
FromUS 287, EAST
ToFM 1033
CSJ0704-02-022
Proj IDBR 2022(505)
Work TypeWIDEN NON-FREEWAY
 
8319405.00837855.8510.0
CountyHARDEMAN
HighwayFM 268
FromCHILDRESS C/L, SOUTH
ToUS 287
CSJ2533-01-015
Proj IDBR 2022(505)
Work TypeWIDEN NON-FREEWAY
 
6372293.340.000.0
CountyCHILDRESS
HighwayFM 268
FromFM 1033, EAST
ToHARDEMAN C/L
CSJ2533-02-008
Proj IDF 2022(507)
Work TypeWIDEN NON-FREEWAY
 
2490642.56934.200.0
Work Order09-15-22
Work Began10-17-22
Work Completed
Time Computed10-15-22
Contract Working Days443
Addl Days Granted0
Working Days Charged29
Percent Time Used6
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0704-02-022
FC TRAFFIC CONTROL, INC. (0.22)
TEXOP CONSTRUCTION (0.68)
COPPELL CONSTRUCTION CO., INC. (11.10)
BAHENA CONSTRUCTION CO.,INC. (20.81)
WILLIS ELECTRIC CO., LP (0.92)
MARCOM ENGINEERING COMPANY (0.29)
TEXAS PANHANDLE CONSTRUCTION, INC. (0.70)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.21)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.47)
DUSTIN ALLEN, INC. (1.89)
Contract #08223261
Totals17182340.90607158.69838790.054.8

CountyCHILDRESS
HighwayVA
From2023 DISTRICT WIDE STRIPING
To.
CSJ0925-00-079
Proj IDC 925-00-79
Work TypeTRAFFIC CONTROL DEVICES
 
1.0001022717.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233224
Totals1022717.220.000.000.0

CountyCHILDRESS
HighwayVA
FromDISTRICT WIDE
To.
CSJ0925-00-083
Proj IDSTP 2B20(031)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1999216.751723897.1086.2
Work Order09-18-20
Work Began01-21-21
Work Completed
Time Computed10-19-20
Contract Working Days368
Addl Days Granted15
Working Days Charged338
Percent Time Used95
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08203035
Totals1999216.7548628.451723897.1086.2

CountyWHEELER
HighwayFM 1046
FromFM 48, EAST
ToUS 83
CSJ1235-01-012
Proj IDSTP 2022(447)HES
Work TypeWIDEN NON-FREEWAY
 
6062196.881373851.9422.6
Work Order05-12-22
Work Began07-18-22
Work Completed
Time Computed06-12-22
Contract Working Days170
Addl Days Granted20
Working Days Charged103
Percent Time Used54
Contractor(s)
JCCC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1235-01-012
W. S. CONSTRUCTION COMPANY (22.06)
WEST TEXAS ROCK RESOURCES, LLC (0.16)
DIRECT TRAFFIC CONTROL, INC. (3.20)
TEXAS PANHANDLE CONSTRUCTION, INC. (1.15)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.35)
MARCOM"S MOWING SERVICE, LLC (0.81)
Contract #04223008
Totals6062196.8898145.661373851.9422.6

CountyFOARD
HighwayFM 1594
From@ SH 6
To.
CSJ1514-01-013
Proj IDSTP 2022(362)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
91117.600.000.0
CountyHARDEMAN
HighwayFM 2568
From@ SH 6
To.
CSJ3184-01-012
Proj IDSTP 2022(362)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
65436.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROAD SOLUTIONS L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1514-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05223025
Totals156553.600.000.000.0

CountyHALL
HighwayFM 1619
From@ JONAH CREEK
To.
CSJ1650-01-010
Proj IDBR 2022(655)
Work TypeBRIDGE REPLACEMENT
 
1575474.20857704.2054.4
Work Order09-20-22
Work Began10-19-22
Work Completed
Time Computed10-17-22
Contract Working Days115
Addl Days Granted0
Working Days Charged38
Percent Time Used33
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1650-01-010
FC TRAFFIC CONTROL, INC. (0.58)
BARRICADES UNLIMITED (0.70)
LANCO TURF & SEEDING, INC. (0.52)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.37)
SOUTHEAST GRINDING AND GROOVING LLC (0.34)
TORO BRAVO CONSTRUCTION, LLC (0.42)
Contract #08223262
Totals1575474.20285026.20857704.2054.4

page 1