Monthly State Let Construction Report For Childress District As Of Nov 10, 2024 Page 1 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWHEELER
HighwayUS 83
From@ SWEETWATER CREEK
To.
CSJ0030-08-038
Proj IDBR 2023(936)
Work TypeBRIDGE REPLACEMENT
 
5746110.504832879.3484.1
CountyWHEELER
HighwayFM 2473
From@ NORTH FORK RED RIVER
To.
CSJ2051-01-013
Proj IDBR 2023(936)
Work TypeBRIDGE REPLACEMENT
 
8517304.001523892.0017.8
Work Order08-03-23
Work Began03-11-24
Work Completed
Time Computed09-03-23
Contract Working Days354
Addl Days Granted0
Working Days Charged149
Percent Time Used42
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0030-08-038
MORRIS COUNTY CONTRACTORS, L.L.C. (0.60)
FC TRAFFIC CONTROL, INC. (0.19)
JB PINNACLE GROUP, LLC (1.76)
LANCO TURF & SEEDING, INC. (0.02)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.76)
PRIMATE CONSTRUCTION, LP (0.14)
TRP CONSTRUCTION GROUP, LLC (0.77)
JVH4 SERVICES, LLC (0.18)
TORO BRAVO CONSTRUCTION, LLC (0.32)
TORO BRAVO CONSTRUCTION, LLC (0.62)
Contract #06233606
Totals14263414.50643998.556356771.3444.5

CountyCOLLINGSWORTH
HighwayUS 83
FromUS 83 @ ELM CREEK
To.
CSJ0031-02-031
Proj IDBR 2025(014)
Work TypeBRIDGE MAINTENANCE
 
2512687.820.000.0
CountyHALL
HighwayUS 287
FromUS 287 SB @ PRAIRIE DOG TOWN FRR
To.
CSJ0042-09-133
Proj IDBR 2B24(472)
Work TypeBRIDGE MAINTENANCE
 
4126090.750.000.0
CountyCOTTLE
HighwayFM 94
FromFM 94 @ NORTH PEASE RIVER
To.
CSJ0704-04-017
Proj IDBR 2025(014)
Work TypeBRIDGE MAINTENANCE
 
638771.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days125
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0031-02-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243221
Totals7277549.570.000.000.0

CountyCHILDRESS
HighwayUS 287
From2732' W OF FM 164 (NBL & SBL) (RAMPS), E
ToCHILDRESS WCL
CSJ0042-12-086
Proj IDF 2024(640)
Work TypeREHABILITATION OF EXISTING ROAD
 
15308760.067371021.5148.1
Work Order03-14-24
Work Began04-22-24
Work Completed
Time Computed03-14-24
Contract Working Days159
Addl Days Granted0
Working Days Charged121
Percent Time Used76
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-086
ALAMO BROTHERS CONCRETE INC (1.52)
DUSTIN ALLEN, INC. (1.34)
TRP CONSTRUCTION GROUP, LLC (0.77)
BARRICADES UNLIMITED (0.15)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.05)
H & F TRUCKING (3.59)
A BROTHERS MILLING, LLC (0.82)
LMSE TRUCKING, LLC (4.59)
Contract #02243212
Totals15308760.06313393.447371021.5148.1

CountyCHILDRESS
HighwayUS 287
From@ BNSF RR
To.
CSJ0042-12-089
Proj IDBR 2025(010)
Work TypeBRIDGE REPLACEMENT
 
2785507.430.000.0
CountyCHILDRESS
HighwayUS 287
From@ BNSF RR
To.
CSJ0042-12-095
Proj IDBR 2025(010)
Work TypeBRIDGE MAINTENANCE
 
1268801.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-31-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days290
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TALBERT COMPANIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243220
Totals4054308.610.000.000.0

CountyCHILDRESS
HighwayUS 287
FromUS 287 NB @ GRASSY CREEK
To.
CSJ0042-12-090
Proj IDBR 2024(847)
Work TypeBRIDGE MAINTENANCE
 
736474.000.000.0
CountyCHILDRESS
HighwayUS 287
FromUS 287 SB @ GRASSY CREEK
To.
CSJ0042-12-091
Proj IDBR 2024(847)
Work TypeBRIDGE MAINTENANCE
 
590315.000.000.0
CountyCHILDRESS
HighwayUS 287
FromUS 287 NB @ BNSF RAILROAD
To.
CSJ0042-12-092
Proj IDBR 2024(847)
Work TypeBRIDGE MAINTENANCE
 
1063900.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days162
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-090
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243232
Totals2390689.000.000.000.0

CountyHARDEMAN
HighwayUS 287
From@ BNSF RR & LP 285
To.
CSJ0043-02-080
Proj IDBR 2024(922)
Work TypeBRIDGE REPLACEMENT
 
28987859.875478042.7518.8
Work Order09-06-24
Work Began09-16-24
Work Completed
Time Computed09-06-24
Contract Working Days539
Addl Days Granted0
Working Days Charged33
Percent Time Used6
Contractor(s)
MORTMARA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-02-080
G & L REBAR (0.66)
JB PINNACLE GROUP, LLC (7.43)
MCRYAN HAULING, INC. (0.40)
MACIAS SPECIALTY CONTRACTING LLC (0.57)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.72)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.19)
CONCRETE CORING COMPANY (0.33)
TEXAS SHAFTS, INC. (5.92)
PENHALL COMPANY (0.11)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.64)
BLACKSMITH VENTURES LLC (10.79)
HIGHPOINT PARTNERS, LLC (11.91)
Contract #06243206
Totals28987859.871766804.635478042.7518.8

CountyHARDEMAN
HighwayUS 287
From65' WEST OF FM 2568, EAST
ToWILBARGER C/L
CSJ0043-04-083
Proj IDF 2024(638)
Work TypeOVERLAY
 
8059390.888692321.8099.9
Work Order02-02-24
Work Began04-29-24
Work Completed
Time Computed02-02-24
Contract Working Days79
Addl Days Granted10
Working Days Charged82
Percent Time Used92
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-04-083
A BROTHERS MILLING, LLC (0.41)
DUSTIN ALLEN, INC. (1.37)
FC TRAFFIC CONTROL, INC. (0.40)
JENNINGS TRUCKING SERVICE, INC. (0.55)
TRP CONSTRUCTION GROUP, LLC (2.12)
MOBILE ENTERPRISES, INC. (1.10)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.56)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.24)
W. S. CONSTRUCTION COMPANY (0.43)
WEST TEXAS ROCK RESOURCES, LLC (0.22)
Contract #01243211
Totals8059390.88207345.688692321.8099.9

CountyDICKENS
HighwayUS 82
From1186' EAST OF DICKENS ECL, EAST
To8.23 MILES (WBL)
CSJ0132-01-055
Proj IDC 132-1-55
Work TypeOVERLAY
 
11319017.7310127359.2489.4
Work Order01-11-24
Work Began08-05-24
Work Completed
Time Computed01-11-24
Contract Working Days99
Addl Days Granted0
Working Days Charged56
Percent Time Used56
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0132-01-055
FLAT LINE, INC. (1.16)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.23)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.24)
W. S. CONSTRUCTION COMPANY (1.90)
DUSTIN ALLEN, INC. (1.86)
FC TRAFFIC CONTROL, INC. (0.22)
Contract #12233009
Totals11319017.732142441.0110127359.2489.4

CountyWHEELER
HighwayIH 40
FromGRAY C/L, EAST
ToUS 83
CSJ0275-12-084
Proj IDC 275-12-84
Work TypeTRANSPORTATION NON-ROADWAY
 
366745.000.000.0
CountyWHEELER
HighwayIH 40
FromUS 83, EAST
ToOKLAHOMA STATE LINE
CSJ0275-13-076
Proj IDC 275-13-76
Work TypeTRANSPORTATION NON-ROADWAY
 
224925.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LIGHT IT UP ELECTRIC
SUBCONTRACTOR(S) FOR CCSJ: 0275-12-084
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243224
Totals591670.500.000.000.0

CountyWHEELER
HighwayIH 40
FromGRAY C/L, EAST
ToUS 83
CSJ0275-12-085
Proj IDF 2024(846)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3449940.402724111.0078.9
Work Order05-22-24
Work Began07-17-24
Work Completed
Time Computed05-22-24
Contract Working Days193
Addl Days Granted0
Working Days Charged66
Percent Time Used34
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-12-085
MACIAS SPECIALTY CONTRACTING LLC (6.51)
BARRICADES UNLIMITED (0.85)
JB PINNACLE GROUP, LLC (13.61)
STRUCTURAL INTEGRITY GROUP LLC (12.72)
KING GEORGE TRAFFIC SOLUTIONS LLC (1.42)
Contract #04243026
Totals3449940.40306491.312724111.0078.9

CountyHALL
HighwaySH 70
From@ MULBERRY CREEK
To.
CSJ0311-02-033
Proj IDBR 2023(938)
Work TypeBRIDGE REPLACEMENT
 
0.1919334727.257558850.2180.9
Work Order07-26-23
Work Began11-08-23
Work Completed
Time Computed07-26-23
Contract Working Days468
Addl Days Granted0
Working Days Charged199
Percent Time Used42
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0311-02-033
JB PINNACLE GROUP, LLC (1.60)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.05)
PENHALL COMPANY (0.15)
TRP CONSTRUCTION GROUP, LLC (0.82)
FC TRAFFIC CONTROL, INC. (0.19)
LANCO TURF & SEEDING, INC. (0.46)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.53)
TORO BRAVO CONSTRUCTION, LLC (0.22)
TORO BRAVO CONSTRUCTION, LLC (0.42)
Contract #06233609
Totals9334727.252500.007558850.2180.9

CountyCHILDRESS
HighwayUS 62
From@ BUCK CREEK
To.
CSJ0381-01-017
Proj IDBR 2024(641)
Work TypeBRIDGE REPLACEMENT
 
6310485.591986450.8831.4
Work Order03-14-24
Work Began07-24-24
Work Completed
Time Computed03-14-24
Contract Working Days249
Addl Days Granted0
Working Days Charged57
Percent Time Used22
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0381-01-017
TORO BRAVO CONSTRUCTION, LLC (0.88)
S & S BRIDGE PAINTING, INC. (0.59)
TRP CONSTRUCTION GROUP, LLC (0.00)
SQUARE CONTRACTING INC (14.04)
Contract #02243010
Totals6310485.59234175.501986450.8831.4

CountyCOLLINGSWORTH
HighwayFM 338
FromUS 83, EAST
ToCR Z
CSJ0449-01-022
Proj IDC 449-1-22
Work TypeWIDEN NON-FREEWAY
 
4582258.604829542.4399.9
CountyCOLLINGSWORTH
HighwayFM 338
FromCR Z, EAST
ToCR 270
CSJ0449-01-023
Proj IDF 2023(686)
Work TypeWIDEN NON-FREEWAY
 
2540318.002698449.6699.9
Work Order06-14-23
Work Began08-01-23
Work Completed
Time Computed07-14-23
Contract Working Days182
Addl Days Granted3
Working Days Charged166
Percent Time Used89
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0449-01-022
TRP CONSTRUCTION GROUP, LLC (2.20)
HJC FARMS, INC. (4.26)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.30)
FC TRAFFIC CONTROL, INC. (0.37)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.30)
H & F TRUCKING (4.01)
Contract #05233212
Totals7122576.6084182.007527992.0999.9

CountyCOLLINGSWORTH
HighwayFM 338
FromCR 270, EAST
ToOKLAHOMA STATE LINE
CSJ0449-01-024
Proj IDSTP 2024(639)HES
Work TypeWIDEN NON-FREEWAY
 
4695146.204727341.2799.9
Work Order03-21-24
Work Began05-15-24
Work Completed
Time Computed03-21-24
Contract Working Days109
Addl Days Granted0
Working Days Charged112
Percent Time Used102
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0449-01-024
TRP CONSTRUCTION GROUP, LLC (1.08)
HJC FARMS, INC. (2.72)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.00)
FC TRAFFIC CONTROL, INC. (0.43)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.15)
ALAMO BROTHERS CONCRETE INC (3.07)
W. S. CONSTRUCTION COMPANY (11.34)
Contract #02243024
Totals4695146.20291488.524727341.2799.9

CountyKNOX
HighwayFM 267
FromUS 82, SOUTH
ToSH 222
CSJ0538-01-027
Proj IDSTP 2023(580)HES
Work TypeWIDEN NON-FREEWAY
 
6913833.356724948.8397.2
Work Order05-17-23
Work Began07-17-23
Work Completed
Time Computed05-17-23
Contract Working Days177
Addl Days Granted0
Working Days Charged143
Percent Time Used80
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0538-01-027
CONTRACTORS SERVICE, LTD. (0.48)
DUSTIN ALLEN, INC. (0.59)
LINEAR TRAFFIC MARKINGS LLC (1.24)
WEST TEXAS ROCK RESOURCES, LLC (0.24)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.42)
W. S. CONSTRUCTION COMPANY (5.35)
Contract #04233016
Totals6913833.3520195.936724948.8397.2

CountyBRISCOE ETC
HighwayFM 1065 ETC
From0.439 MILES W OF CR 29, S
ToFLOYD C/L
CSJ0740-03-016
Proj IDC 740-3-16
Work TypeSEAL COAT
 
7724031.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0740-03-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243016
Totals7724031.170.000.000.0

CountyWHEELER
HighwayFM 1547
From@ LONG DRY CREEK
To.
CSJ0761-03-021
Proj IDBR 2B24(267)
Work TypeBRIDGE REPLACEMENT
 
0.0401901152.85292392.6015.3
CountyCOLLINGSWORTH
HighwayFM 1981
From@ COTTONWOOD CREEK
To.
CSJ2165-01-008
Proj IDBR 2B24(267)
Work TypeBRIDGE REPLACEMENT
 
1296211.85404595.0031.2
Work Order08-22-24
Work Began10-01-24
Work Completed
Time Computed08-22-24
Contract Working Days235
Addl Days Granted0
Working Days Charged23
Percent Time Used9
Contractor(s)
SKYLINE BRIDGE LLC
SUBCONTRACTOR(S) FOR CCSJ: 0761-03-021
MORRIS COUNTY CONTRACTORS, L.L.C. (1.99)
TRP CONSTRUCTION GROUP, LLC (0.85)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.25)
FC TRAFFIC CONTROL, INC. (0.83)
CARTHAGE DRILLING, LLC (8.65)
Contract #07243224
Totals3197364.70696987.60696987.6021.7

CountyDONLEY
HighwayFM 1260
From@ SALT FORK OF RED RIVER
To.
CSJ0795-02-017
Proj IDBR 2B24(268)
Work TypeBRIDGE REPLACEMENT
 
5513072.150.000.0
CountyDONLEY
HighwayFM 1260
From@ EAST LELIA LAKE CREEK
To.
CSJ0795-03-010
Proj IDBR 2B24(268)
Work TypeBRIDGE REPLACEMENT
 
1159761.110.000.0
Work Order08-22-24
Work Began00-00-00
Work Completed
Time Computed09-22-24
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
C. E. BARKER, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0795-02-017
BLACKSMITH VENTURES LLC (3.60)
HJC FARMS, INC. (2.26)
HB FARMER FOUNDATION, LLC (16.00)
TORO BRAVO CONSTRUCTION, LLC (1.78)
PROFESSIONAL TRAFFIC CONTROL LLC (0.19)
TRP CONSTRUCTION GROUP, LLC (0.67)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.83)
Contract #07243211
Totals6672833.260.000.000.0

CountyCOLLINGSWORTH
HighwayFM 1547
From@ SALT FORK OF RED RIVER
To.
CSJ0844-03-013
Proj IDBR 2B23(021)
Work TypeBRIDGE REPLACEMENT
 
9441703.709237681.0197.8
CountyHARDEMAN
HighwayFM 2006
From@ DRAW
To.
CSJ1917-01-015
Proj IDBR 2B23(021)
Work TypeBRIDGE REPLACEMENT
 
1430427.601533754.3599.9
Work Order09-07-23
Work Began10-16-23
Work Completed
Time Computed09-07-23
Contract Working Days237
Addl Days Granted0
Working Days Charged225
Percent Time Used94
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0844-03-013
JB PINNACLE GROUP, LLC (1.73)
TORO BRAVO CONSTRUCTION, LLC (0.25)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.08)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.55)
A-CORE CONCRETE CUTTING, INC. (0.12)
FC TRAFFIC CONTROL, INC. (0.18)
SCOTT DERR PAINTING CO, LLC (0.19)
TRP CONSTRUCTION GROUP, LLC (0.45)
Contract #08233213
Totals10872131.30103400.0010771435.3699.0

CountyCHILDRESS
HighwayVA
From2024 DISTRICT WIDE BRIDGE MAINTENANCE
To.
CSJ0925-00-093
Proj IDC 925-00-93
Work TypeBRIDGE MAINTENANCE
 
1520757.501180938.3377.6
Work Order02-05-24
Work Began07-09-24
Work Completed
Time Computed02-05-24
Contract Working Days85
Addl Days Granted0
Working Days Charged81
Percent Time Used95
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-093
BECK-REIT & SONS, LTD. (9.76)
FC TRAFFIC CONTROL, INC. (1.37)
TRP CONSTRUCTION GROUP, LLC (2.35)
Contract #01243237
Totals1520757.50263503.941180938.3377.6

page 1 | page 2