Monthly State Let Maintenance Report For Maintenance Division District As Of Nov 10, 2024 Page 3 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTITUS
HighwayIH0030
FromNORTH EAST TXDOT REGION
ToNORTH EAST TXDOT REGION
CSJ6453-89-001
Proj IDMMC - 645389001
Work TypeDE-ICING SALT
 
0.0101112080.0021774.801.9
Work Order01-10-24
Work Began01-17-24
Work Completed
Time Computed01-17-24
Contract Working Days365
Addl Days Granted0
Working Days Charged289
Percent Time Used79
Contractor(s)
THE BARGAIN SOURCE
SUBCONTRACTOR(S) FOR CCSJ: 6453-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234211
Totals1112080.000.0021774.801.9

CountyGARZA
HighwayUS0084
FromRDC
ToRDC
CSJ6462-87-001
Proj IDMMC - 646287001
Work TypeDE-ICING SALT
 
0.010255645.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-24
Work Began11-01-24
Work Completed
Time Computed11-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244217
Totals255645.000.000.000.0

CountyGARZA
HighwayUS0084
FromRDC
ToRDC
CSJ6462-93-001
Proj IDMMC - 646293001
Work TypeHERBICIDE/INSECTICIDE
 
0.0103433047.1593836.402.7
Work Order08-20-24
Work Began08-27-24
Work Completed
Time Computed08-27-24
Contract Working Days356
Addl Days Granted0
Working Days Charged66
Percent Time Used18
Contractor(s)
NUTRIEN AG SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244201
Totals3433047.1551302.4093836.402.7

CountyHENDERSON
HighwaySH0031
FromRDC
ToRDC
CSJ6462-94-001
Proj IDMMC - 646294001
Work TypeHERBICIDE/INSECTICIDE
 
0.0104115798.151554939.0437.7
Work Order08-20-24
Work Began08-27-24
Work Completed
Time Computed08-27-24
Contract Working Days365
Addl Days Granted0
Working Days Charged66
Percent Time Used18
Contractor(s)
NUTRIEN AG SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244202
Totals4115798.151480822.241554939.0437.7

CountyGUADALUPE
HighwayIH0010
FromRDC
ToRDC
CSJ6462-95-001
Proj IDMMC - 646295001
Work TypeHERBICIDE/INSECTICIDE
 
0.0102807579.851308369.2046.6
Work Order08-20-24
Work Began08-27-24
Work Completed
Time Computed08-27-24
Contract Working Days365
Addl Days Granted0
Working Days Charged66
Percent Time Used18
Contractor(s)
NUTRIEN AG SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244203
Totals2807579.85341741.361308369.2046.6

CountyHARRIS
HighwayIH0010
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6466-12-001
Proj IDRMC - 646612001
Work TypeDEBRIS REMOVAL
 
0.0101710940.412136216.0099.9
Work Order00-00-00
Work Began07-17-24
Work Completed
Time Computed07-17-24
Contract Working Days730
Addl Days Granted0
Working Days Charged101
Percent Time Used13
Contractor(s)
GLOBAL EMERGENCY SERVICES, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6466-12-001
D&T MARRIOTT ENTERPRISE LLC (0.00)
GJS TREES LLC (0.00)
R. BAKER, INC. (0.00)
Contract #05244201
Totals1710940.410.002136216.0099.9

CountyCAMERON
HighwayUS0077
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6466-13-001
Proj IDRMC - 646613001
Work TypeDEBRIS REMOVAL
 
0.0101106030.410.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GLOBAL EMERGENCY SERVICES, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6466-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05244202
Totals1106030.410.000.000.0