Monthly Local Let Maintenance Report For El Paso District As Of Nov 10, 2024 Page 2 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBREWSTER
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6437-97-001
Proj IDRMC - 643797001
Work TypePICNIC AREA MAINTENANCE
 
0.01074729.0098895.0199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged489
Percent Time Used66
Contractor(s)
C&C SOSA COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6437-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05232401
Totals74729.006183.0098895.0199.9

CountyEL PASO
HighwaySL0375
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6443-62-001
Proj IDMMC - 644362001
Work TypeFLEXIBLE BASE
 
0.01046400.0021919.2947.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-29-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged430
Percent Time Used79
Contractor(s)
JOBE MATERIALS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6443-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08232401
Totals46400.000.0021919.2947.2

CountyEL PASO
HighwayUS0054
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6443-94-001
Proj IDMMC - 644394001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010235500.0066127.8028.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-05-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged452
Percent Time Used83
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6443-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06232402
Totals235500.000.0066127.8028.0

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6444-32-001
Proj IDMMC - 644432001
Work TypeDE-ICING SALT
 
0.010250657.0025600.4810.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-07-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted120
Working Days Charged299
Percent Time Used99
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6444-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06232403
Totals250657.000.0025600.4810.2

CountyBREWSTER
HighwaySH0118
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6446-08-001
Proj IDMMC - 644608001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010180375.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-12-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged288
Percent Time Used80
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232403
Totals180375.000.000.000.0

CountyBREWSTER
HighwayUS0067
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6446-14-001
Proj IDRMC - 644614001
Work TypeJANITORIAL MAINTENANCE
 
0.010209950.00195150.0092.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged366
Percent Time Used50
Contractor(s)
RWCS JANITORIAL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232405
Totals209950.0019950.00195150.0092.9

CountyHUDSPETH
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6446-16-001
Proj IDRMC - 644616001
Work TypePICNIC AREA MAINTENANCE
 
0.01051705.6050878.0098.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-20-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged373
Percent Time Used51
Contractor(s)
C&C SOSA COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232406
Totals51705.604258.8050878.0098.3

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6446-24-001
Proj IDRMC - 644624001
Work TypePICNIC AREA MAINTENANCE
 
0.01060012.0061074.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-23-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged365
Percent Time Used50
Contractor(s)
C&C SOSA COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232404
Totals60012.004901.0061074.0099.9

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-79-001
Proj IDMMC - 645179001
Work TypeFLEXIBLE BASE
 
0.010196958.0059802.5730.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-04-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged302
Percent Time Used55
Contractor(s)
JOBE MATERIALS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6451-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11232425
Totals196958.000.0059802.5730.3

CountyEL PASO
HighwaySL0375
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6457-83-001
Proj IDRMC - 645783001
Work TypePICNIC AREA MAINTENANCE
 
0.01038400.0019200.0050.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
C&C SOSA COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03242401
Totals38400.003200.0019200.0050.0

CountyPRESIDIO
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6461-96-001
Proj IDRMC - 646196001
Work TypePICNIC AREA MAINTENANCE
 
0.01054321.0025356.0046.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
LUKEDA SANDBLASTING & SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6461-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03242402
Totals54321.004230.0025356.0046.6

CountyJEFF DAVIS
HighwaySH0017
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6461-97-001
Proj IDRMC - 646197001
Work TypePICNIC AREA MAINTENANCE
 
0.01036201.0018040.0049.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
LUKEDA SANDBLASTING & SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6461-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03242403
Totals36201.003000.0018040.0049.8

CountyBREWSTER
HighwayFM0170
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6462-00-001
Proj IDMMC - 646200001
Work TypeAGGREGATE
 
0.010148200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged163
Percent Time Used45
Contractor(s)
JOBE MATERIALS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6462-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04242405
Totals148200.000.000.000.0

CountyBREWSTER
HighwayFM0170
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6462-01-001
Proj IDMMC - 646201001
Work TypeEMULSION
 
0.010299520.0047926.9516.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged163
Percent Time Used45
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04242404
Totals299520.0023771.4947926.9516.0

CountyEL PASO
HighwaySL0375
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6466-83-001
Proj IDMMC - 646683001
Work TypeAGGREGATE
 
0.010126300.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-09-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged84
Percent Time Used46
Contractor(s)
JOBE MATERIALS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6466-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06242406
Totals126300.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6467-49-001
Proj IDMMC - 646749001
Work TypeHOT MIX
 
0.010815710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6467-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08244017
Totals815710.000.000.000.0

CountyEL PASO
HighwayFM3380
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6469-02-001
Proj IDMMC - 646902001
Work TypeAGGREGATE
 
0.010919927.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6469-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09242407
Totals919927.000.000.000.0

CountyEL PASO
HighwaySL0375
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6475-32-001
Proj IDMMC - 647532001
Work TypeWINTER WEATHER MATERIAL
 
0.010278887.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6475-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11242409
Totals278887.000.000.000.0

page 1 | page 2