Monthly Local Let Maintenance Report For Fort Worth District As Of Jul 13, 2021 Page 1 Of 4

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayFM0156
FromJANITORIAL MAINTENANCE AT
ToSAGINAW MAINTENANCE OFFICE
CSJ6257-39-001
Proj IDSUP - 625739001
Work TypeJANITIORIAL MAINTENANCE
 
0.01010868.0410868.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-02-13
Work Completed
Time Computed07-08-13
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6257-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06130231
Totals10868.040.0010868.0499.9

CountyWISE
HighwayUS0380
FromVARIOUS ROADWAYS WITHIN
ToWISE & JACK COUNTY
CSJ6263-14-001
Proj IDRMC - 626314001
Work TypeGUARDRAIL INSTALLATION/REPAIR
 
0.01076570.00229914.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-13
Work Began11-11-13
Work Completed12-10-14
Time Computed11-14-13
Contract Working Days365
Addl Days Granted0
Working Days Charged352
Percent Time Used96
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10130201
Totals76570.000.00229914.50100.0

CountyTARRANT
HighwayIH0020
FromFORT WORTH
ToDISTRICT COMPLEX
CSJ6291-17-001
Proj IDSUP - 629117001
Work TypeGROUNDS MAINTENANCE
 
0.01063628.1640583.32100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed12-30-16
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged299
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6291-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150237
Totals63628.160.0040583.32100.0

CountyTARRANT
HighwayIH0820
FromNORTH TARRANT ENGINEERS AND
ToMAINTENANCE OFFICES
CSJ6311-89-001
Proj IDSUP - 631189001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.01013081.6811850.91100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-17
Work Began07-11-17
Work Completed06-15-21
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged297
Percent Time Used81
Contractor(s)
WORKQUEST
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6311-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170232
Totals13081.680.0011850.91100.0

CountyTARRANT
HighwayIH0035W
FromVARIOUS LOCATIONS
ToWITHIN SOUTH TARRANT COUNTY
CSJ6312-88-001
Proj IDRMC - 631288001
Work TypeCALLOUT REFLECTORIZED PAVEMENT MARKINGS
 
0.010273472.50285662.5599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-04-17
Work Completed
Time Computed12-04-17
Contract Working Days96
Addl Days Granted0
Working Days Charged64
Percent Time Used66
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6312-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170204
Totals273472.500.00285662.5599.9

CountyTARRANT
HighwayIH0820
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6315-35-001
Proj IDRMC - 631535001
Work TypeCALL-OUT STRIPING & PREFAB HANDWORK
 
0.010218354.44216102.7698.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-27-18
Work Began04-16-18
Work Completed
Time Computed04-16-18
Contract Working Days365
Addl Days Granted150
Working Days Charged503
Percent Time Used97
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02180201
Totals218354.440.00216102.7698.9

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6315-66-001
Proj IDSUP - 631566001
Work TypeLITTER REMOVAL
 
0.010482216.16475289.0598.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-05-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170233
Totals482216.160.00475289.0598.5

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6315-69-001
Proj IDSUP - 631569001
Work TypeLITTER REMOVAL
 
0.010391997.62360136.2691.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began09-15-17
Work Completed
Time Computed09-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged348
Percent Time Used95
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170236
Totals391997.620.00360136.2691.8

CountyJOHNSON
HighwayUS0067
FromJOHNSON COUNTY
ToWITHIN CITY LIMITS
CSJ6315-82-001
Proj IDSUP - 631582001
Work TypeLANDSCAPING MAINTENANCE
 
0.01017700.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-17
Work Began00-00-00
Work Completed
Time Computed12-07-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170231
Totals17700.000.000.000.0

CountySOMERVELL
HighwayUS0067
FromVARIOUS LOCATIONS IN HOO, SOMERVELL
ToAND ERATH COUNTIES
CSJ6318-05-001
Proj IDSUP - 631805001
Work TypePICNIC AREA MAINTENANCE
 
0.010114036.34111851.33100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-02-18
Work Began01-03-18
Work Completed01-01-19
Time Computed01-03-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170232
Totals114036.340.00111851.33100.0

CountyWISE
HighwayUS0380
FromWISE AND JACK COUNTIES
ToWISE AND JACK COUNTIES
CSJ6322-27-001
Proj IDRMC - 632227001
Work TypeCALL OUT REFL PAVE MARKINGS AND MARKERS
 
0.100278580.11299806.22100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-18
Work Began06-18-18
Work Completed07-24-19
Time Computed06-18-18
Contract Working Days365
Addl Days Granted0
Working Days Charged355
Percent Time Used97
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180201
Totals278580.110.00299806.22100.0

CountyJOHNSON
HighwayFM0004
FromVARIOUS LOCATIONS WITHIN
ToJOHNSON COUNTY
CSJ6324-66-001
Proj IDRMC - 632466001
Work TypeTREE TRIMMING, TREE AND BRUSH REMOVAL
 
0.010186103.00142963.0076.8
Work Order00-00-00
Work Began12-14-20
Work Completed
Time Computed12-14-20
Contract Working Days86
Addl Days Granted0
Working Days Charged81
Percent Time Used94
Contractor(s)
AZA CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6324-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10200208
Totals186103.0022070.00142963.0076.8

CountyTARRANT
HighwayIH0820
FromLITTER REMOVAL WITHIN
ToNORTH TARRANT COUNTY
CSJ6325-46-001
Proj IDSUP - 632546001
Work TypeLITTER REMOVAL
 
0.010456008.80458843.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-30-18
Work Began09-05-18
Work Completed
Time Computed09-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged361
Percent Time Used98
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08180236
Totals456008.800.00458843.8499.9

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN NORTH TARRANT COUNTY
ToNORTH TARRANT COUNTY
CSJ6325-80-001
Proj IDRMC - 632580001
Work TypeCALL-OUT STRPG, REFLEC PAV MRKGS & MRKS
 
0.010220889.50135854.8161.5
Work Order09-12-19
Work Began09-16-19
Work Completed
Time Computed09-16-19
Contract Working Days180
Addl Days Granted0
Working Days Charged299
Percent Time Used166
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6325-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06190201
Totals220889.500.00135854.8161.5

CountyTARRANT
HighwaySH0010
FromNORTH TARRANT ENGINEERS AND
ToMAINTENANCE OFFICE
CSJ6327-55-001
Proj IDSUP - 632755001
Work TypeJANITORIAL AND GROUNDS MAINTENENACE
 
0.01035320.1630776.12100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-18
Work Completed06-15-21
Time Computed01-02-18
Contract Working Days365
Addl Days Granted0
Working Days Charged359
Percent Time Used98
Contractor(s)
WORKQUEST
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6327-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170234
Totals35320.160.0030776.12100.0

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS IN
ToERATH, HOOD AND SOMERVELL COUNTIES
CSJ6329-74-001
Proj IDRMC - 632974001
Work TypeGUARDRAIL INSTALLATION AND REPAIR
 
0.010268180.00654864.00100.0
Work Order11-26-18
Work Began11-26-18
Work Completed11-05-20
Time Computed11-06-18
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09180201
Totals268180.000.00654864.00100.0

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6331-44-001
Proj IDRMC - 633144001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010154567.00246636.00100.0
Work Order02-01-19
Work Began02-01-19
Work Completed10-29-20
Time Computed02-01-19
Contract Working Days365
Addl Days Granted272
Working Days Charged637
Percent Time Used100
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6331-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11180203
Totals154567.001290.00246636.00100.0

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADSIDES WITHIN
ToSOUTH TARRANT COUNTY
CSJ6332-79-001
Proj IDSUP - 633279001
Work TypeLITTER REMOVAL
 
0.010757757.60732396.2896.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-18
Work Began09-05-18
Work Completed
Time Computed09-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6332-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08180233
Totals757757.600.00732396.2896.6

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS
ToERATH,HOOD AND SOMERVELL COUNTY
CSJ6333-27-001
Proj IDRMC - 633327001
Work TypeCALLOUT REFL PAV MRKING,MRKR,RUMBLE STIP
 
0.010297190.00294638.5599.1
Work Order01-31-19
Work Began02-01-19
Work Completed
Time Computed02-01-19
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6333-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11180202
Totals297190.009500.00294638.5599.1

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS IN
ToERATH,HOOD AND SOMERVELL
CSJ6334-41-001
Proj IDRMC - 633441001
Work TypeCLEANING AND SEALING JOINTS AND CRACKS
 
0.010174906.77180940.36100.0
Work Order11-22-19
Work Began11-23-19
Work Completed01-27-20
Time Computed11-22-19
Contract Working Days30
Addl Days Granted0
Working Days Charged26
Percent Time Used86
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6334-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09190203
Totals174906.77151120.90180940.36100.0

page 1 | page 2 | page 3 | page 4