Monthly Local Let Maintenance Report For Laredo District As Of Jan 10, 2023 Page 1 Of 5

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWEBB
HighwayUS0083
FromVARIOUS
ToVARIOUS
CSJ6183-29-001
Proj IDRMC - 618329001
Work TypeINSTALL TRAFFIC SIGNALS, FLASHING BEACON
 
0.001245601.35276457.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-11-09
Work Began09-21-09
Work Completed
Time Computed09-21-09
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07092201
Totals245601.350.00276457.3899.9

CountyWEBB
HighwayUS0083
FromVARIOUS
ToVARIOUS
CSJ6210-68-001
Proj IDRMC - 621068001
Work TypeINSTALL TRAF SIG, FLASHING BEACONS, PVT.
 
0.001236431.55356107.4699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-10
Work Began08-24-10
Work Completed
Time Computed08-24-10
Contract Working Days365
Addl Days Granted99
Working Days Charged464
Percent Time Used100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6210-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07102202
Totals236431.550.00356107.4699.9

CountyWEBB
HighwayIH0035
FromIH 35
ToIH 35
CSJ6221-66-001
Proj IDSUP - 622166001
Work TypeJANITORIAL/LANDSCAPING/LITTER PICKUP
 
0.001251677.07235015.9593.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-03-11
Work Began01-03-11
Work Completed
Time Computed01-03-11
Contract Working Days731
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6221-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12102231
Totals251677.070.00235015.9593.3

CountyVAL VERDE
HighwayUS0277
From5.00 MI N OF US 90
To5.37 MI N OF US 90
CSJ6235-72-001
Proj IDRMC - 623572001
Work TypeREHABILITATION OF A BRIDGE FACILITY
 
0.371174640.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WESTCHESTER FIRE INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6235-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06122202
Totals174640.000.000.000.0

CountyVAL VERDE
HighwayUS0090
FromUS 90
ToUS 90
CSJ6256-00-001
Proj IDSUP - 625600001
Work TypeJANITORIAL/GROUNDS/LANDSCAPING MAINTENAN
 
0.00156598.4851018.8090.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-13
Work Began04-01-13
Work Completed
Time Computed04-01-13
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6256-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02132231
Totals56598.480.0051018.8090.1

CountyWEBB
HighwayIH0035
FromVARIOUS
To.
CSJ6269-76-001
Proj IDSUP - 626976001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00180486.5677762.1696.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-14
Work Began02-01-14
Work Completed
Time Computed02-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6269-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01142231
Totals80486.560.0077762.1696.6

CountyKINNEY
HighwayUS0277
FromKINNEY
ToVARIOUS
CSJ6341-03-001
Proj IDRMC - 634103001
Work TypeINSTALL TRAFFIC SIGNALS AND FLASH BEACON
 
0.001302620.00420881.15100.0
Work Order03-20-19
Work Began03-20-19
Work Completed05-12-21
Time Computed03-20-19
Contract Working Days365
Addl Days Granted195
Working Days Charged560
Percent Time Used100
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6341-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02192202
Totals302620.002800.00420881.15100.0

CountyVAL VERDE
HighwayUS0277
FromUS 277, ETC.
ToVARIOUS
CSJ6341-55-001
Proj IDRMC - 634155001
Work TypeMOWING OF HIGHWAYS RIGHT OF WAY
 
320.000254740.56407394.8499.9
Work Order06-10-19
Work Began06-20-19
Work Completed
Time Computed06-20-19
Contract Working Days365
Addl Days Granted365
Working Days Charged707
Percent Time Used96
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6341-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04192203
Totals254740.560.00407394.8499.9

CountyMAVERICK
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6343-02-001
Proj IDRMC - 634302001
Work TypeMOWING OF HIGHWAYS RIGHT OF WAY
 
222.000318793.86375184.9599.9
Work Order06-01-20
Work Began06-01-20
Work Completed
Time Computed06-01-20
Contract Working Days730
Addl Days Granted820
Working Days Charged944
Percent Time Used60
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6343-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05192202
Totals318793.860.00375184.9599.9

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6347-89-001
Proj IDSUP - 634789001
Work TypeGUARDRAIL REPAIRS
 
0.001592263.001262142.50100.0
Work Order11-14-19
Work Began11-01-19
Work Completed12-13-22
Time Computed11-18-19
Contract Working Days365
Addl Days Granted456
Working Days Charged821
Percent Time Used100
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6347-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10192232
Totals592263.000.001262142.50100.0

CountyWEBB
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6351-21-001
Proj IDSUP - 635121001
Work TypeLANDSCAPE MAINTENANCE
 
0.0019711.368092.8083.3
Work Order10-01-19
Work Began10-01-19
Work Completed
Time Computed10-01-19
Contract Working Days365
Addl Days Granted1,095
Working Days Charged1,188
Percent Time Used81
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6351-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09192211
Totals9711.36809.288092.8083.3

CountyMAVERICK
HighwayUS0277
FromMAVERICK
ToVARIOUS
CSJ6354-97-001
Proj IDRMC - 635497001
Work TypeINSTALL TRAFFIC SIGNAL AND PAV. MARKINGS
 
300.000308762.25432320.9199.9
Work Order11-06-20
Work Began05-01-21
Work Completed
Time Computed11-06-20
Contract Working Days365
Addl Days Granted365
Working Days Charged693
Percent Time Used94
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6354-97-001
CHEROKEE SERVICES (0.00)
Contract #09202201
Totals308762.252120.00432320.9199.9

CountyWEBB
HighwayIH0035
FromWEBB
ToVARIOUS
CSJ6355-08-001
Proj IDRMC - 635508001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
200.000158600.00156600.00100.0
Work Order09-21-20
Work Began09-16-20
Work Completed12-23-22
Time Computed09-21-20
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6355-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202204
Totals158600.000.00156600.00100.0

CountyDIMMIT
HighwayUS0083
FromDIMMIT
ToVARIOUS
CSJ6359-51-001
Proj IDRMC - 635951001
Work TypeINSTALL TRAFFIC SIGNAL & PAV. MARKINGS
 
300.000308762.25678059.0199.9
Work Order12-14-20
Work Began01-01-21
Work Completed
Time Computed12-14-20
Contract Working Days365
Addl Days Granted365
Working Days Charged729
Percent Time Used99
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6359-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09202202
Totals308762.25260312.50678059.0199.9

CountyVAL VERDE
HighwaySS0239
FromSS 239
ToN/A
CSJ6362-19-001
Proj IDRMC - 636219001
Work TypeLANDSCAPE MAINTENANCE
 
0.1009000.0016900.0099.9
Work Order08-03-20
Work Began08-01-20
Work Completed
Time Computed08-03-20
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6362-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05202203
Totals9000.000.0016900.0099.9

CountyDUVAL
HighwaySH0016
FromDUVAL
ToVARIOUS
CSJ6365-22-001
Proj IDMMC - 636522001
Work TypeAGRREGATE MATERIAL CONT (MATERIAL ONLY)
 
200.00058934.50332422.96100.0
Work Order10-13-20
Work Began03-01-21
Work Completed09-26-22
Time Computed10-13-20
Contract Working Days120
Addl Days Granted240
Working Days Charged359
Percent Time Used99
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6365-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202202
Totals58934.500.00332422.96100.0

CountyKINNEY
HighwayUS0277
FromKINNEY
ToVARIOUS
CSJ6365-26-001
Proj IDRMC - 636526001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
200.000158600.00206325.0099.9
Work Order11-19-20
Work Began11-18-20
Work Completed
Time Computed11-19-20
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6365-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202205
Totals158600.000.00206325.0099.9

CountyDUVAL
HighwayUS0059
FromDUVAL
ToVARIOUS
CSJ6366-22-001
Proj IDRMC - 636622001
Work TypeMOWING OF HIGHWAYS RIGHT OF WAY
 
305.000168462.40337450.83100.0
Work Order10-08-20
Work Began10-15-20
Work Completed11-18-22
Time Computed10-15-20
Contract Working Days365
Addl Days Granted365
Working Days Charged729
Percent Time Used99
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6366-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202203
Totals168462.400.00337450.83100.0

CountyZAVALA
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6366-74-001
Proj IDRMC - 636674001
Work TypeMOWING OF HIGHWAYS RIGHT OF WAY
 
264.000169043.32265871.9699.9
Work Order05-01-21
Work Began05-01-21
Work Completed
Time Computed05-01-21
Contract Working Days365
Addl Days Granted365
Working Days Charged610
Percent Time Used83
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6366-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10202203
Totals169043.320.00265871.9699.9

CountyDIMMIT
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6368-63-001
Proj IDRMC - 636863001
Work TypeMOWING OF HIGHWAYS RIGHT OF WAY
 
250.000264327.04322380.3199.9
Work Order12-09-20
Work Began11-18-20
Work Completed
Time Computed12-14-20
Contract Working Days730
Addl Days Granted730
Working Days Charged748
Percent Time Used51
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6368-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10202204
Totals264327.040.00322380.3199.9

page 1 | page 2 | page 3 | page 4 | page 5