Monthly Local Let Maintenance Report For Laredo District As Of Jul 13, 2021 Page 1 Of 5

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWEBB
HighwayUS0083
FromVARIOUS
ToVARIOUS
CSJ6183-29-001
Proj IDRMC - 618329001
Work TypeINSTALL TRAFFIC SIGNALS, FLASHING BEACON
 
0.001245601.35276457.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-11-09
Work Began09-21-09
Work Completed
Time Computed09-21-09
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07092201
Totals245601.350.00276457.3899.9

CountyLASALLE
HighwayIH0035
FromIH 35 AT FM 468
ToIH 35 AT FM 468
CSJ6207-54-001
Proj IDRMC - 620754001
Work TypeCONST. CONSIST. OF ROADWAY ILLUMINATION
 
0.820127642.50122352.9095.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-10
Work Began09-01-10
Work Completed
Time Computed09-01-10
Contract Working Days80
Addl Days Granted0
Working Days Charged47
Percent Time Used58
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06102202
Totals127642.500.00122352.9095.8

CountyWEBB
HighwayUS0083
FromVARIOUS
ToVARIOUS
CSJ6210-68-001
Proj IDRMC - 621068001
Work TypeINSTALL TRAF SIG, FLASHING BEACONS, PVT.
 
0.001236431.55356107.4699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-10
Work Began08-24-10
Work Completed
Time Computed08-24-10
Contract Working Days365
Addl Days Granted99
Working Days Charged464
Percent Time Used100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6210-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07102202
Totals236431.550.00356107.4699.9

CountyWEBB
HighwayIH0035
FromIH 35
ToIH 35
CSJ6221-66-001
Proj IDSUP - 622166001
Work TypeJANITORIAL/LANDSCAPING/LITTER PICKUP
 
0.001251677.07235015.9593.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-03-11
Work Began01-03-11
Work Completed
Time Computed01-03-11
Contract Working Days731
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6221-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12102231
Totals251677.070.00235015.9593.3

CountyVAL VERDE
HighwayUS0277
From5.00 MI N OF US 90
To5.37 MI N OF US 90
CSJ6235-72-001
Proj IDRMC - 623572001
Work TypeREHABILITATION OF A BRIDGE FACILITY
 
0.371174640.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WESTCHESTER FIRE INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6235-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06122202
Totals174640.000.000.000.0

CountyVAL VERDE
HighwayUS0090
FromUS 90
ToUS 90
CSJ6256-00-001
Proj IDSUP - 625600001
Work TypeJANITORIAL/GROUNDS/LANDSCAPING MAINTENAN
 
0.00156598.4851018.8090.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-13
Work Began04-01-13
Work Completed
Time Computed04-01-13
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6256-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02132231
Totals56598.480.0051018.8090.1

CountyWEBB
HighwayIH0035
FromVARIOUS
To.
CSJ6269-76-001
Proj IDSUP - 626976001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00180486.5677762.1696.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-14
Work Began02-01-14
Work Completed
Time Computed02-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6269-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01142231
Totals80486.560.0077762.1696.6

CountyVAL VERDE
HighwayUS0090
FromVARIOUS
To.
CSJ6271-94-001
Proj IDSUP - 627194001
Work TypeJANITORIAL, GROUNDS, LANDSCAPING
 
0.00123990.4024774.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-14
Work Began00-00-00
Work Completed
Time Computed04-01-14
Contract Working Days153
Addl Days Granted0
Working Days Charged122
Percent Time Used79
Contractor(s)
WORKQUEST
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6271-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03142231
Totals23990.400.0024774.4099.9

CountyVAL VERDE
HighwaySL0025
FromVARIOUS
To.
CSJ6308-23-001
Proj IDSUP - 630823001
Work TypeJANITORIAL AND GROUNDS
 
0.001140119.2023158.5916.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
WORKQUEST
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162203
Totals140119.200.0023158.5916.5

CountyVAL VERDE
HighwaySL0025
FromVARIOUS
To.
CSJ6313-92-001
Proj IDSUP - 631392001
Work TypeJANITORIAL AND GROUNDS
 
0.001116960.61109760.0493.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days601
Addl Days Granted0
Working Days Charged598
Percent Time Used99
Contractor(s)
WORKQUEST
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12162231
Totals116960.610.00109760.0493.8

CountyVAL VERDE
HighwaySL0025
FromVARIOUS
To.
CSJ6315-19-001
Proj IDSUP - 631519001
Work TypeTRASH PICK UP
 
0.0015100.006180.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days210
Addl Days Granted153
Working Days Charged157
Percent Time Used43
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172203
Totals5100.000.006180.0099.9

CountyVAL VERDE
HighwaySS0239
FromDEL RIO TXDOT COMPLEX
To.
CSJ6322-94-001
Proj IDRMC - 632294001
Work TypeLANDSCAPE MAINTENANCE
 
0.00110450.0017540.00100.0
Work Order06-11-18
Work Began06-11-18
Work Completed08-13-20
Time Computed06-11-18
Contract Working Days365
Addl Days Granted365
Working Days Charged718
Percent Time Used98
Contractor(s)
TEXAS CUTTERS
SUBCONTRACTOR(S) FOR CCSJ: 6322-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05182203
Totals10450.001225.0017540.00100.0

CountyDIMMIT
HighwayUS0083
FromVARIOUS
ToVARIOUS
CSJ6330-68-001
Proj IDRMC - 633068001
Work TypeMOWING OF HIGHWAY RIGHT OF WAY
 
247.000265728.99373075.46100.0
Work Order10-02-18
Work Began10-29-18
Work Completed05-12-21
Time Computed10-29-18
Contract Working Days730
Addl Days Granted365
Working Days Charged792
Percent Time Used72
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6330-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05182202
Totals265728.990.00373075.46100.0

CountyKINNEY
HighwayUS0090
FromUS 90, ETC.
ToVARIOUS
CSJ6338-08-001
Proj IDRMC - 633808001
Work TypeMOWING OF HIGHWAYS RIGHT OF WAY
 
201.000304958.42194587.8763.8
Work Order08-01-19
Work Began12-01-19
Work Completed
Time Computed08-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged700
Percent Time Used95
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6338-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04192201
Totals304958.420.00194587.8763.8

CountyWEBB
HighwayUS0083
FromUS 83, ETC
ToVARIOUS
CSJ6340-57-001
Proj IDRMC - 634057001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
707.000316786.80573516.0099.9
Work Order05-15-19
Work Began05-15-19
Work Completed
Time Computed05-15-19
Contract Working Days365
Addl Days Granted396
Working Days Charged761
Percent Time Used100
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6340-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04192202
Totals316786.8024402.80573516.0099.9

CountyLASALLE
HighwayIH0035
FromDIMMIT
ToVARIOUS
CSJ6341-02-001
Proj IDRMC - 634102001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.001303621.45293653.2596.7
Work Order04-01-19
Work Began04-01-19
Work Completed
Time Computed04-01-19
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6341-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02192201
Totals303621.450.00293653.2596.7

CountyKINNEY
HighwayUS0277
FromKINNEY
ToVARIOUS
CSJ6341-03-001
Proj IDRMC - 634103001
Work TypeINSTALL TRAFFIC SIGNALS AND FLASH BEACON
 
0.001302620.00418081.1599.9
Work Order03-20-19
Work Began03-20-19
Work Completed
Time Computed03-20-19
Contract Working Days365
Addl Days Granted195
Working Days Charged560
Percent Time Used100
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6341-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02192202
Totals302620.000.00418081.1599.9

CountyVAL VERDE
HighwayUS0277
FromUS 277, ETC.
ToVARIOUS
CSJ6341-55-001
Proj IDRMC - 634155001
Work TypeMOWING OF HIGHWAYS RIGHT OF WAY
 
320.000254740.56407394.8499.9
Work Order06-10-19
Work Began06-20-19
Work Completed
Time Computed06-20-19
Contract Working Days365
Addl Days Granted365
Working Days Charged707
Percent Time Used96
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6341-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04192203
Totals254740.560.00407394.8499.9

CountyVAL VERDE
HighwayUS0090
FromVAL VERDE
ToVARIOUS
CSJ6341-85-001
Proj IDSUP - 634185001
Work TypeJANITORIAL SERVICES DEL RIO OFFICES
 
0.00157292.8853639.0493.6
Work Order01-01-19
Work Began01-01-19
Work Completed
Time Computed01-01-19
Contract Working Days365
Addl Days Granted425
Working Days Charged780
Percent Time Used98
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6341-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12182231
Totals57292.880.0053639.0493.6

CountyKINNEY
HighwayUS0090
FromUS 90
ToVARIOUS
CSJ6342-20-001
Proj IDSUP - 634220001
Work TypePICNIC AREA MAINTENANCE KINNEY COUNTY
 
0.00180040.4072750.2090.8
Work Order02-01-19
Work Began02-01-19
Work Completed
Time Computed02-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6342-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01192232
Totals80040.404364.0072750.2090.8

page 1 | page 2 | page 3 | page 4 | page 5