Monthly State Let Construction Report For Odessa District As Of Jul 13, 2021 Page 1 Of 3

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyREEVES ETC
HighwayIH 20 ETC
FromIH 10
To8.8 MILES NORTH OF IH 10
CSJ0003-05-053
Proj IDNH 2B20(211)
Work TypeSEAL COAT
 
41.2276708265.274353393.2564.8
Work Order10-14-20
Work Began06-14-21
Work Completed
Time Computed06-14-21
Contract Working Days39
Addl Days Granted0
Working Days Charged12
Percent Time Used30
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0003-05-053
DOUBLE A CONTRACTING, L.P. (4.11)
FC TRAFFIC CONTROL, INC. (0.64)
Contract #09203229
Totals6708265.273177587.584353393.2564.8

CountyREEVES
HighwayIH 20
FromIH 10
To9.7 MI NE OF IH 10
CSJ0003-05-054
Proj IDSTP 1902(275)HES
Work TypeSFT
 
8.0299730369.955976242.5961.4
CountyREEVES
HighwayIH 20
From9.7 MI NE OF IH 10
To0.2 MI W OF CR 209
CSJ0003-06-095
Proj IDSTP 1902(275)HES
Work TypeSFT
 
23.1429131020.9514274051.3999.9
CountyREEVES
HighwayIH 20
From0.2 MI W OF CR 209
ToWARD C/L
CSJ0003-07-058
Proj IDSTP 1902(275)HES
Work TypeSFT
 
16.0569097358.159275964.0799.9
Work Order09-16-19
Work Began12-02-19
Work Completed
Time Computed12-02-19
Contract Working Days482
Addl Days Granted0
Working Days Charged358
Percent Time Used74
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0003-05-054
X GOMEZ LOGISTICS LLC (0.55)
4-WAY HAULERS, LLC (0.24)
MARCOM"S MOWING SERVICE, LLC (0.12)
Contract #08193004
Totals27958749.0559478.1829526258.0599.9

CountyREEVES
HighwayIH 20
FromAT BILLINGSLEA DRAW
To.
CSJ0003-06-096
Proj IDBR 2021(627)
Work TypeBRIDGE MAINTENANCE
 
0.047515094.800.000.0
CountyREEVES
HighwayIH 10
FromAT KC DRAW
To.
CSJ0441-09-050
Proj IDBR 2021(628)
Work TypeBRIDGE MAINTENANCE
 
0.168468752.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days125
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0003-06-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213217
Totals983847.250.000.000.0

CountyWARD
HighwayIH 20
FromREEVES C/L
To1.3 MI W OF FM 1927
CSJ0004-02-060
Proj IDSTP 1902(276)HES
Work TypeSFT
 
16.5877858414.8012334657.1199.9
CountyWARD
HighwayIH 20
From1.3 MI W OF FM 1927
ToCRANE C/L
CSJ0004-04-093
Proj IDSTP 1902(276)HES
Work TypeSFT
 
23.9636958414.8014844038.5699.9
CountyCRANE
HighwayIH 20
FromWARD C/L
ToECTOR C/L
CSJ0004-05-030
Proj IDSTP 1902(276)HES
Work TypeSFT
 
1.5346932814.80845545.6412.1
CountyECTOR
HighwayIH 20
FromCRANE C/L
ToFM 1053
CSJ0004-06-039
Proj IDSTP 1902(276)HES
Work TypeSFT
 
2.6326925775.101857347.8026.8
Work Order09-16-19
Work Began04-27-20
Work Completed
Time Computed12-16-19
Contract Working Days482
Addl Days Granted0
Working Days Charged339
Percent Time Used70
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0004-02-060
X GOMEZ LOGISTICS LLC (0.56)
MARCOM"S MOWING SERVICE, LLC (0.09)
4-WAY HAULERS, LLC (0.22)
Contract #08193204
Totals28675419.5053596.0229881589.1199.9

CountyWARD ETC
HighwaySS 57 ETC
FromIH 20
ToBI 20
CSJ0004-03-051
Proj IDSTP 2B20(220)
Work TypeSEAL COAT
 
148.9636643515.596452433.3497.1
Work Order10-21-20
Work Began05-25-21
Work Completed
Time Computed04-26-21
Contract Working Days48
Addl Days Granted0
Working Days Charged26
Percent Time Used54
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0004-03-051
VIZCAINO, L.P. (4.57)
BARRICADES PLUS, LLC (0.00)
Contract #09203210
Totals6643515.592412769.816452433.3497.1

CountyECTOR ETC
HighwayBI 20-E ETC
FromSL 338
ToMIDLAND C/L
CSJ0005-01-114
Proj IDSTP 1902(277)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
56.5129595982.128126183.3784.6
Work Order09-25-19
Work Began12-02-19
Work Completed
Time Computed10-28-19
Contract Working Days318
Addl Days Granted72
Working Days Charged342
Percent Time Used87
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-01-114
BARRICADES UNLIMITED (1.45)
BLACK JACK ENERGY SERVICES, LLC (1.86)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.23)
Contract #08193208
Totals9595982.12172329.458126183.3784.6

CountyMIDLAND
HighwayBI 20-E
FromSL 250
ToSL 268
CSJ0005-02-118
Proj IDNH 2020(570)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.1935859308.546243988.0099.9
CountyMIDLAND
HighwayBI 20-E
FromWALL ST
ToFAIRGROUNDS
CSJ0005-03-076
Proj IDNH 2020(570)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.3302030930.481772770.3687.2
CountyMIDLAND
HighwayBI 20-E
FromSL 268
ToWALL ST
CSJ0005-09-022
Proj IDNH 2020(570)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.4894127985.843529638.4485.5
Work Order04-27-20
Work Began05-27-20
Work Completed
Time Computed05-27-20
Contract Working Days347
Addl Days Granted0
Working Days Charged233
Percent Time Used67
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-02-118
DK CONTRACTING, LLC (1.60)
DOUBLE A CONTRACTING, L.P. (1.62)
BARRICADES UNLIMITED (1.44)
PERFORMANCE EQUIPMENT SERVICE (2.95)
WILLIS ELECTRIC CO., LP (0.29)
TITAN MILLING INC. (1.93)
Contract #02203203
Totals12018224.8683024.6411546396.8096.0

CountyMIDLAND
HighwayBI 20-E
FromAT SS 588
To.
CSJ0005-02-126
Proj IDSTP 2021(751)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
129250.250.000.0
CountyECTOR
HighwayFM 2020
FromKNOX AVE
ToSL 338
CSJ1870-01-035
Proj IDSTP 2021(751)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8212894.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days232
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-02-126
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213210
Totals8342144.900.000.000.0

CountyMIDLAND
HighwayBI 20-E
FromFAIRGROUNDS RD
ToIH 20
CSJ0005-03-078
Proj IDC 5-3-78
Work TypeREHABILITATION OF EXISTING ROAD
 
10390240.992301218.4122.1
CountyMIDLAND
HighwayBI 20-E
From@ E SL 250
To.
CSJ0005-03-079
Proj IDNH 2B20(214)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
772468.04212209.5927.4
Work Order03-01-21
Work Began04-19-21
Work Completed
Time Computed04-19-21
Contract Working Days230
Addl Days Granted0
Working Days Charged31
Percent Time Used13
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-03-078
WILLIS ELECTRIC CO., LP (5.15)
DK CONTRACTING, LLC (2.09)
DOUBLE A CONTRACTING, L.P. (1.92)
FC TRAFFIC CONTROL, INC. (0.45)
HJC FARMS, INC. (4.19)
K. L. DURHAM CONSTRUCTION, L.L.C. (2.54)
R.E.B.D. TRUCKING LLC (0.00)
REECE CONSTRUCTION CO., INC. (2.41)
Contract #10203210
Totals11162709.031472221.352513428.0022.5

CountyMARTIN
HighwayIH 20
FromBI 20-F WEST
ToSH 137
CSJ0005-04-076
Proj IDNH 2020(476)
Work TypeBRIDGE REPLACEMENT
 
3.03329939040.8626234461.4287.6
CountyMARTIN
HighwayIH 20
FromAT SH 137
To.
CSJ0005-04-081
Proj IDSTP 2020(477)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
695063.60653160.0093.9
Work Order02-13-20
Work Began05-14-20
Work Completed
Time Computed05-14-20
Contract Working Days494
Addl Days Granted0
Working Days Charged262
Percent Time Used53
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-04-076
A BROTHERS MILLING, LLC (0.70)
SPEEDY PAVING (0.24)
SCOTT DERR PAINTING CO, LLC (0.17)
BARRICADES UNLIMITED (1.09)
HJC FARMS, INC. (1.89)
DOUBLE A CONTRACTING, L.P. (1.04)
PENHALL COMPANY (0.03)
WILLIS ELECTRIC CO., LP (3.55)
AZ GRADEMAKER INC (0.86)
FUSION COMMUNICATIONS, LLC (0.12)
SLATON BROTHERS, INC. (2.60)
TEXAS SHAFTS, INC. (1.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19)
BRUNDAGE-BONE (0.10)
CRANE SERVICES, INC. (0.16)
PERFORMANCE EQUIPMENT SERVICE (0.17)
TORO BRAVO CONSTRUCTION, LLC (0.04)
DTM TRUCKING, INC. (5.02)
KLP COMMERCIAL, L.L.C. (1.65)
AARON CONCRETE CONTRACTORS, L.P. (0.29)
LONE STAR PRODUCTS (WICHITA FALLS) (0.21)
LONE STAR PRODUCTS (WICHITA FALLS) (0.55)
TEXAS ROAD RECYCLERS, L.L.C. (0.13)
TORO BRAVO CONSTRUCTION, LLC (0.11)
Contract #01203002
Totals30634104.46978323.3726887621.4287.7

CountyMIDLAND
HighwayIH 20
FromSL 250
To0.5 MILES EAST OF MIDKIFF RD
CSJ0005-14-067
Proj IDNH 2020(863)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
2.73936305216.0010576.250.0
Work Order03-25-21
Work Began00-00-00
Work Completed
Time Computed06-23-21
Contract Working Days597
Addl Days Granted0
Working Days Charged3
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-14-067
FC TRAFFIC CONTROL, INC. (0.35)
WILLIS ELECTRIC CO., LP (3.67)
BARRICADES UNLIMITED (1.27)
LONE STAR PAVING COMPANY (19.97)
SCOTT DERR PAINTING CO, LLC (0.19)
TEXAS SHAFTS, INC. (0.42)
SPEEDY PAVING (0.41)
Contract #02213002
Totals36305216.0010576.2510576.250.0

CountyMIDLAND
HighwayIH 20
FromAT CR 1250
To.
CSJ0005-14-084
Proj IDC 5-14-84
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.00059101873.574991012.318.4
Work Order03-01-21
Work Began05-24-21
Work Completed
Time Computed04-30-21
Contract Working Days459
Addl Days Granted0
Working Days Charged18
Percent Time Used3
Contractor(s)
PULICE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-14-084
FC TRAFFIC CONTROL, INC. (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19)
ALAVA INTERNATIONAL, INC. (0.90)
PMI PAVEMENT MARKING, LLC (0.44)
BARRICADES UNLIMITED (0.35)
DUSTROL, INC. (0.54)
REECE ALBERT, INC. (14.23)
WILLIS ELECTRIC CO., LP (1.70)
Contract #01213201
Totals59101873.573582418.524991012.318.4

CountyMIDLAND ETC
HighwayIH 20 ETC
From@ SL 250
To.
CSJ0005-15-090
Proj IDSTP 2020(910)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5851043835.00821401.2678.6
Work Order07-21-20
Work Began05-10-21
Work Completed
Time Computed08-20-20
Contract Working Days224
Addl Days Granted0
Working Days Charged84
Percent Time Used37
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0005-15-090
BARRICADES UNLIMITED (1.88)
DESERT PAVING, INC. (0.62)
DOUBLE A CONTRACTING, L.P. (5.17)
FUSION COMMUNICATIONS, LLC (3.19)
REECE ALBERT, INC. (13.73)
Contract #06203220
Totals1043835.00275032.73821401.2678.6

CountyPECOS
HighwayUS 67
From16.8 MI SOUTH OF IH 10
ToBREWSTER COUNTY LINE
CSJ0075-02-026
Proj IDC 75-2-26
Work TypeSUPER-2 HIGHWAY
 
27.49435754470.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days525
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0075-02-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213204
Totals35754470.170.000.000.0

CountyPECOS
HighwayUS 67
From0.5 MI. N. OF IH 10
ToCROCKETT COUNTY LINE
CSJ0076-01-029
Proj IDNH 1802(325)
Work TypeROADWAY WIDEN TO A MODIFIED SUPER 2
 
31.66248936556.3011496756.8323.4
Work Order05-14-19
Work Began08-26-19
Work Completed
Time Computed08-13-19
Contract Working Days798
Addl Days Granted0
Working Days Charged420
Percent Time Used52
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0076-01-029
RELMCO, INC. (12.55)
MARCOM"S MOWING SERVICE, LLC (0.20)
PMI PAVEMENT MARKING, LLC (2.39)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.76)
DTM TRUCKING, INC. (3.30)
TAKCO, INC. (9.00)
HERITAGE MATERIALS, LLC (2.89)
FLR OILFIELD SERVICES, LLC (1.79)
RPV CONSTRUCTION, LLC (0.91)
STURGEON SERVICES OF TEXAS, INC. (5.85)
FLASHER EQUIPMENT COMPANY (2.21)
DIAMOND C LOGISTICS TX LLC (0.00)
Contract #04193201
Totals48936556.30100.5011496756.8323.4

CountyREEVES
HighwayUS 285
FromRM 652
ToCR 232
CSJ0139-03-047
Proj IDNH 2B20(021)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.8065198387.005258266.5599.9
Work Order07-21-20
Work Began12-15-20
Work Completed
Time Computed10-20-20
Contract Working Days79
Addl Days Granted0
Working Days Charged105
Percent Time Used132
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0139-03-047
SIBONEY CONTRACTING CO. (4.52)
FLASHER EQUIPMENT COMPANY (0.49)
HERITAGE MATERIALS, LLC (1.99)
PERFORMANCE EQUIPMENT SERVICE (0.72)
FLAT LINE, INC. (1.94)
Contract #06203239
Totals5198387.000.005258266.5599.9

CountyREEVES
HighwayUS 285
FromSH 302
ToFM 1216
CSJ0139-04-045
Proj IDNH 2018(882)
Work TypeRECONSTRUCT AND WIDEN
 
16.85531638493.3828420223.0990.4
Work Order06-14-18
Work Began09-12-18
Work Completed
Time Computed09-12-18
Contract Working Days480
Addl Days Granted91
Working Days Charged653
Percent Time Used114
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0139-04-045
MARCOM"S MOWING SERVICE, LLC (0.21)
PMI PAVEMENT MARKING, INC. (1.13)
HJC FARMS, INC. (0.32)
ALDAY TRUCKING, LLC (0.09)
W. S. CONSTRUCTION COMPANY (7.32)
DTM TRUCKING, INC. (0.08)
FLR OILFIELD SERVICES, LLC (1.46)
STRIPE-A-ZONE, INC. (0.22)
HERITAGE MATERIALS, LLC (2.94)
ROUGH GROUND SERVICES LLC (1.92)
EMERGY (0.25)
WILD WEST TRUCKING, LLC (1.77)
Contract #05183002
Totals31638493.3867419.9528420223.0990.4

CountyREEVES
HighwayUS 285
From2.0 MI SOUTH OF CR 113
ToPECOS COUNTY LINE
CSJ0139-06-021
Proj IDC 139-6-21
Work TypeSUPER-2 HIGHWAY
 
13.93229734403.880.000.0
CountyPECOS
HighwayUS 285
FromREEVES COUNTY LINE
To0.3 MI SOUTH OF FM 1776
CSJ0139-07-025
Proj IDC 139-7-25
Work TypeSUPER-2 HIGHWAY
 
13.99828794096.890.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days805
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0139-06-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213002
Totals58528500.770.000.000.0

CountyANDREWS
HighwayUS 385
FromECTOR COUNTY LINE
ToANDREWS CITY LIMITS
CSJ0228-05-066
Proj IDNH 2020(571)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
15.97849841452.8840050421.1980.3
Work Order03-09-20
Work Began06-01-20
Work Completed
Time Computed06-01-20
Contract Working Days440
Addl Days Granted0
Working Days Charged247
Percent Time Used56
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0228-05-066
W. S. CONSTRUCTION COMPANY (5.94)
V-TECH ENVIRONMENTAL SERVICES (0.05)
A BROTHERS MILLING, LLC (0.13)
BARRICADES UNLIMITED (0.02)
WILLIS ELECTRIC CO., LP (0.03)
PERFORMANCE EQUIPMENT SERVICE (2.13)
DK CONTRACTING, LLC (0.57)
DOUBLE A CONTRACTING, L.P. (0.88)
FERREY TRANSPORT ENERGY LINES LLC (0.57)
PEYSON TRANSPORT, LLC (1.08)
J&M TRUCKING OF TEXAS LLC (0.08)
LEVI THOMPSON CONSTRUCTION, INC. (0.23)
SCR CIVIL CONSTRUCTION, LLC (1.03)
Contract #02203008
Totals49841452.88562090.1740050421.1980.3

CountyECTOR
HighwayUS 385
FromNORTH FM 1882
ToANDREWS COUNTY LINE
CSJ0228-06-086
Proj IDNH 2B20(126)
Work TypeREHABILITATION OF EXISTING ROAD
 
9.43619970002.5812473711.5962.4
CountyECTOR
HighwayUS 385
From@COTTONWOOD RD
To.
CSJ0228-06-089
Proj IDSTP 2B20(154)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.085149997.42420.000.2
Work Order08-14-20
Work Began11-02-20
Work Completed
Time Computed11-02-20
Contract Working Days316
Addl Days Granted0
Working Days Charged148
Percent Time Used46
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0228-06-086
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.35)
DK CONTRACTING, LLC (0.76)
DOUBLE A CONTRACTING, L.P. (1.36)
REECE CONSTRUCTION CO., INC. (1.55)
FC TRAFFIC CONTROL, INC. (0.30)
TEXOP CONSTRUCTION (1.45)
WILLIS ELECTRIC CO., LP (1.37)
LPZ ENTERPRISES, LLC (0.00)
R.E.B.D. TRUCKING LLC (0.00)
Contract #07203012
Totals20120000.0016014.3412474131.5961.9

page 1 | page 2 | page 3