Monthly State Let Maintenance Report For Odessa District As Of Jan 10, 2023 Page 1 Of 2

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyREEVES
Highway0000000
From1202 S. IH-20 FRONTAGE ROAD, PECOS, TX 7
To1202 S. IH-20 FRONTAGE ROAD, PECOS, TX 7
CSJ4704-01-413
Proj IDCBC - 470401413
Work TypeNEW FACILITY
 
0.0013225000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRIDE GENERAL CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07154213
Totals3225000.000.000.000.0

CountyREEVES
Highway0000000
FromIH10 & IH20 SPLIT / EAST BOUND IH20
ToIH10 & IH20 SPLIT / EAST BOUND IH20
CSJ4704-02-993
Proj IDCBC - 470402993
Work TypeRENOVATION OR REPAIR
 
0.001990000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRIDE GENERAL CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 4704-02-993
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164222
Totals990000.000.000.000.0

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6341-92-001
Proj IDRMC - 634192001
Work TypeROADSIDE MOWING
 
0.001623818.801204928.0099.9
Work Order05-21-19
Work Began06-19-19
Work Completed
Time Computed06-01-19
Contract Working Days731
Addl Days Granted731
Working Days Charged1,307
Percent Time Used89
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6341-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03194020
Totals623818.80109549.301204928.0099.9

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6374-47-001
Proj IDRMC - 637447001
Work TypeROUTINE MAINTENANCE PROJECT
 
545204.10526513.1096.5
Work Order05-27-21
Work Began06-14-21
Work Completed
Time Computed06-01-21
Contract Working Days366
Addl Days Granted366
Working Days Charged576
Percent Time Used78
Contractor(s)
J-MEN CONCRETE CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6374-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01214223
Totals545204.100.00526513.1096.5

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6376-27-001
Proj IDRMC - 637627001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010454727.00578631.6999.9
Work Order06-23-21
Work Began07-01-21
Work Completed
Time Computed07-01-21
Contract Working Days366
Addl Days Granted366
Working Days Charged546
Percent Time Used74
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6376-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214215
Totals454727.0052516.54578631.6999.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6376-39-001
Proj IDRMC - 637639001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010592612.50668634.1499.9
Work Order06-18-21
Work Began07-01-21
Work Completed
Time Computed07-01-21
Contract Working Days366
Addl Days Granted366
Working Days Charged549
Percent Time Used75
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6376-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214216
Totals592612.5050091.35668634.1499.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6376-42-001
Proj IDRMC - 637642001
Work TypeMILL AND INLAY
 
0.0101687005.804799995.7299.9
Work Order08-09-21
Work Began08-09-21
Work Completed
Time Computed08-09-21
Contract Working Days80
Addl Days Granted0
Working Days Charged75
Percent Time Used93
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05214217
Totals1687005.800.004799995.7299.9

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6383-65-001
Proj IDRMC - 638365001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010626436.00213952.0034.1
Work Order04-28-22
Work Began07-05-22
Work Completed
Time Computed05-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged245
Percent Time Used33
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6383-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224216
Totals626436.000.00213952.0034.1

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6388-05-001
Proj IDRMC - 638805001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010388050.00284170.0973.2
Work Order01-18-22
Work Began04-04-22
Work Completed
Time Computed02-01-22
Contract Working Days366
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6388-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214220
Totals388050.000.00284170.0973.2

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6389-06-001
Proj IDRMC - 638906001
Work TypeMILL AND INLAY
 
0.0101381358.002707248.9899.9
Work Order03-01-22
Work Began03-01-22
Work Completed
Time Computed03-01-22
Contract Working Days40
Addl Days Granted30
Working Days Charged59
Percent Time Used84
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6389-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11214221
Totals1381358.000.002707248.9899.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6390-87-001
Proj IDRMC - 639087001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010309566.32152277.4449.1
Work Order04-01-22
Work Began06-08-22
Work Completed
Time Computed04-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged275
Percent Time Used37
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6390-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214213
Totals309566.320.00152277.4449.1

CountyREEVES
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6390-88-001
Proj IDRMC - 639088001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010344486.1286121.5325.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged214
Percent Time Used29
Contractor(s)
ABESCAPE GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 6390-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224217
Totals344486.120.0086121.5325.0

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6393-58-001
Proj IDRMC - 639358001
Work TypeILLUMINATION MAINTENANCE
 
0.010650166.69113242.0417.7
Work Order07-11-22
Work Began07-28-22
Work Completed
Time Computed06-13-22
Contract Working Days365
Addl Days Granted0
Working Days Charged163
Percent Time Used44
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224218
Totals650166.692298.72113242.0417.7

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6397-80-001
Proj IDRMC - 639780001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010466895.00246122.9052.7
Work Order06-01-22
Work Began06-06-22
Work Completed
Time Computed06-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
AJ COMMERCIAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-80-001
K-BAR SERVICES, INC. (0.10)
Contract #04224221
Totals466895.000.00246122.9052.7

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6398-27-001
Proj IDRMC - 639827001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010481605.00162704.0036.4
Work Order05-09-22
Work Began06-14-22
Work Completed
Time Computed06-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged211
Percent Time Used57
Contractor(s)
AJ COMMERCIAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6398-27-001
K-BAR SERVICES, INC. (0.10)
Contract #04224220
Totals481605.0018164.00162704.0036.4

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6398-28-001
Proj IDRMC - 639828001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010506040.00242222.5047.8
Work Order06-01-22
Work Began06-07-22
Work Completed
Time Computed06-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
AJ COMMERCIAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6398-28-001
K-BAR SERVICES, INC. (0.09)
Contract #04224219
Totals506040.005240.00242222.5047.8

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6400-01-001
Proj IDRMC - 640001001
Work TypeCABLE MEDIAN BARRIER SYSTEM REPAIR
 
0.010355600.0059110.0016.6
Work Order11-15-22
Work Began12-13-22
Work Completed
Time Computed12-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged28
Percent Time Used7
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6400-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224214
Totals355600.0059110.0059110.0016.6

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6400-02-001
Proj IDRMC - 640002001
Work TypeCABLE MEDIAN BARRIER SYSTEM REPAIR
 
0.010356600.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-08-22
Work Began00-00-00
Work Completed
Time Computed12-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6400-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224215
Totals356600.000.000.000.0

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6402-05-001
Proj IDRMC - 640205001
Work TypeBRIDGE REPAIR
 
0.010549625.00574711.6999.9
Work Order09-01-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6402-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224612
Totals549625.00126456.00574711.6999.9

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6403-22-001
Proj IDRMC - 640322001
Work TypeMILL AND INLAY
 
0.0101273278.992800015.2899.9
Work Order08-16-22
Work Began08-17-22
Work Completed
Time Computed08-17-22
Contract Working Days40
Addl Days Granted0
Working Days Charged14
Percent Time Used35
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6403-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224212
Totals1273278.990.002800015.2899.9

page 1 | page 2