Monthly State Let Construction Report For Paris District As Of Jan 10, 2023 Page 1 Of 4

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHUNT ETC
HighwaySH 66 ETC
FromFM 6
ToUS 69
CSJ0009-06-052
Proj IDF 2022(196)
Work TypeSEAL COAT
 
12207435.8511943825.5497.8
Work Order04-06-22
Work Began04-14-22
Work Completed
Time Computed04-01-22
Contract Working Days141
Addl Days Granted0
Working Days Charged141
Percent Time Used100
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-06-052
KITECO PROPERTY SOLUTIONS INC. (0.89)
STRIPE-A-ZONE, LLC (10.60)
INNOVATIVE ROADWAY SOLUTIONS, LLC (8.06)
BRYDL CONTRACTING, LLC (0.71)
Contract #12213004
Totals12207435.850.0011943825.5497.8

CountyHUNT
HighwaySH 66
FromSH 66
ToAT FM 1570
CSJ0009-06-054
Proj IDF 2022(549)
Work TypeTRAFFIC CONTROL DEVICES
 
0.100408232.20240642.5058.9
CountyHUNT
HighwaySH 34
From645' N OF FM 1570 INTERSECTION
To1050' S OF FM 1570 INTERSECTION
CSJ0173-07-061
Proj IDF 2022(389)
Work TypeTRAFFIC CONTROL DEVICES
 
0.322860033.15345473.9540.1
CountyHUNT
HighwayFM 1903
FromAT FM 1903
To.
CSJ1496-02-019
Proj IDF 2022(419)
Work TypeTRAFFIC CONTROL DEVICES
 
0.080373766.15132229.8935.3
Work Order07-14-22
Work Began10-21-22
Work Completed
Time Computed10-12-22
Contract Working Days115
Addl Days Granted0
Working Days Charged31
Percent Time Used26
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0009-06-054
DUSTROL, INC. (1.99)
XROADS, L.P. (1.50)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.62)
TEXAS TRAFFIC CONTROL SYSTEMS, INC. (21.98)
TRP CONSTRUCTION GROUP, LLC (1.58)
JR WEST TEXAS CONCRETE LLC (19.09)
G J SEEDING, LLC (2.15)
Contract #06223243
Totals1642031.50111857.75718346.3443.7

CountyHUNT
HighwaySS 302 ETC
FromSH 34
ToFM 499
CSJ0009-07-043
Proj IDF 2022(421)
Work TypeOVERLAY
 
7.9904906019.960.000.0
Work Order09-01-22
Work Began11-21-22
Work Completed
Time Computed10-03-22
Contract Working Days123
Addl Days Granted0
Working Days Charged13
Percent Time Used10
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-07-043
BAHENA CONSTRUCTION CO.,INC. (3.86)
BARRICADES UNLIMITED (0.53)
DUSTIN ALLEN, INC. (3.41)
DUSTROL, INC. (8.26)
TRP CONSTRUCTION GROUP, LLC (1.98)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.16)
Contract #04223015
Totals4906019.960.000.000.0

CountyHUNT
HighwayIH 30
From1.2 MILES EAST OF FM 1903
To1.0 MILES EAST OF FM 1570
CSJ0009-13-167
Proj IDF 2B22(018)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
0.99064767101.740.000.0
CountyHUNT
HighwayIH 30
From1.0 MILES WEST OF FM 1903
To1.2 MILES EAST OF FM 1903
CSJ0009-13-173
Proj IDF 2B22(018)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
0.85644670226.960.000.0
CountyHUNT
HighwayIH 30
From1.0 MILES EAST OF FM 1570
To0.1 MILES EAST OF MONTY STRATTON
CSJ0009-13-175
Proj IDF 2B22(018)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
0.67818638110.460.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-28-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,033
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-167
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10223002
Totals128075439.160.000.000.0

CountyHUNT ETC
HighwayIH 30 ETC
FromROCKWALL COUNTY LINE (N FR)
ToMONTY STRATTON (N FRONTAGE RD)
CSJ0009-13-176
Proj IDNH 2021(155)
Work TypeSEAL COAT
 
223.57910775428.3610605636.9898.8
Work Order03-19-21
Work Began04-21-21
Work Completed
Time Computed04-08-21
Contract Working Days106
Addl Days Granted0
Working Days Charged140
Percent Time Used132
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-176
BARRICADES PLUS, LLC (1.73)
INNOVATIVE ROADWAY SOLUTIONS, LLC (7.45)
STRIPING TECHNOLOGY, L.P. (21.06)
BRYDL CONTRACTING, INC. (0.00)
L. S. EQUIPMENT CO., INC. (0.00)
Contract #12203005
Totals10775428.360.0010605636.9898.8

CountyHUNT
HighwayIH 30
FromAT SABINE RIVER
To.
CSJ0009-13-183
Proj IDBR 2022(422)
Work TypeBRIDGE MAINTENANCE
 
0.189483971.25538901.5099.9
CountyHUNT
HighwayIH 30
FromAT SABINE RIVER
To.
CSJ0009-13-184
Proj IDBR 2022(422)
Work TypeBRIDGE MAINTENANCE
 
0.189260981.25444636.2599.9
CountyGRAYSON
HighwaySH 56
FromAT POST OAK CREEK
To.
CSJ0045-03-055
Proj IDBR 2022(395)
Work TypeBRIDGE MAINTENANCE
 
0.012668310.00627773.3093.9
CountyLAMAR
HighwayFM 38
FromAT ROWDY CREEK
To.
CSJ0749-02-023
Proj IDBR 2022(396)
Work TypeBRIDGE MAINTENANCE
 
0.033580942.50549688.0094.6
Work Order05-12-22
Work Began00-00-00
Work Completed
Time Computed08-10-22
Contract Working Days335
Addl Days Granted0
Working Days Charged88
Percent Time Used26
Contractor(s)
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-183
BARRICADES UNLIMITED (7.70)
SOUTHERN CROSS CONTRACTORS, LLC (1.70)
KEEPAINTING, LLC (4.44)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.25)
KEYSTONE SERVICES, INC. (0.78)
Contract #04223222
Totals1994205.00353341.502160999.0599.9

CountyHOPKINS
HighwayIH 30
FromSL 301
ToCANEY CREEK
CSJ0010-02-096
Proj IDNH 2021(158)
Work TypeOVERLAY
 
7.4905239464.326728344.5199.9
CountyHOPKINS
HighwayIH 30
FromCANEY CREEK BRIDGE
ToFANKLIN COUNTY LINE
CSJ0610-01-044
Proj IDNH 2021(158)
Work TypeOVERLAY
 
7.9035210463.114600831.8988.2
CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE
ToTITUS COUNTY LINE
CSJ0610-02-058
Proj IDNH 2021(158)
Work TypeOVERLAY
 
10.672448130.71611382.6099.9
Work Order01-14-21
Work Began06-02-21
Work Completed
Time Computed03-15-21
Contract Working Days118
Addl Days Granted14
Working Days Charged126
Percent Time Used95
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-02-096
BARRICADES UNLIMITED (0.12)
TEXOP CONSTRUCTION (10.61)
STRIPING TECHNOLOGY, L.P. (2.23)
WINDING ROAD CONSTRUCTION, INC. (1.90)
WEST TEXAS ROCK RESOURCES, LLC (0.20)
Contract #12203207
Totals10898058.1417500.0011940559.0099.9

CountyGRAYSON
HighwaySH 56
FromUNION STREET
ToCOLLINSVILLE STREET
CSJ0045-02-040
Proj IDSTP 2021(601)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
732932.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-02-040
PANOLA SIGN & BARRICADE, INC. (1.44)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.99)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (19.65)
Contract #10223021
Totals732932.050.000.000.0

CountyLAMAR ETC
HighwayUS 82 ETC
FromUS 271
ToFM 1508
CSJ0045-09-104
Proj IDSTP 2020(829)HES
Work TypeTRAFFIC CONTROL DEVICES
 
10.877951964.031123684.6599.9
Work Order07-20-20
Work Began11-17-20
Work Completed
Time Computed10-19-20
Contract Working Days270
Addl Days Granted0
Working Days Charged279
Percent Time Used103
Contractor(s)
SIEMENS MOBILITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-09-104
FC TRAFFIC CONTROL, INC. (1.58)
CANNON ASPHALT GROUP LLC (47.89)
J. TUCKER CONSTRUCTION, INC. (0.61)
STRIPING TECHNOLOGY, L.P. (1.00)
Contract #05203026
Totals951964.030.001123684.6599.9

CountyLAMAR
HighwayUS 82
FromAT 1502
To.
CSJ0045-11-044
Proj IDSTP 2023(236)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.4101751101.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-06-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days79
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-11-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223218
Totals1751101.000.000.000.0

CountyRED RIVER ETC
HighwayUS 82 ETC
From0.903 MI W OF SH 37
ToSH 37
CSJ0045-12-087
Proj IDSTP 2B20(147)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
30.3192627582.902462580.0493.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-20
Work Began10-21-20
Work Completed
Time Computed00-00-00
Contract Working Days218
Addl Days Granted14
Working Days Charged223
Percent Time Used96
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-12-087
FLEX SUPPLY, LLC (0.63)
A. E. MOORE CONSTRUCTION, INC. (3.89)
DUSTIN ALLEN, INC. (0.00)
AREA WIDE PROTECTIVE, INC. (0.06)
Contract #08203235
Totals2627582.903676.952462580.0493.7

CountyRED RIVER ETC
HighwayUS 82 ETC
FromSH 37
ToBU 37
CSJ0045-12-091
Proj IDF 2023(231)
Work TypeSEAL COAT
 
19399613.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0045-12-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223003
Totals19399613.070.000.000.0

CountyGRAYSON
HighwayUS 82
FromAT POST OAK CREEK
ToWESTBOUND LANES
CSJ0045-18-039
Proj IDBR 2023(139)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.025151681.000.000.0
CountyGRAYSON
HighwayUS 82
FromAT POST OAK CREEK
ToEASTBOUND LANES
CSJ0045-18-040
Proj IDBR 2023(139)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.025152931.000.000.0
CountyGRAYSON
HighwayUS 82
FromCOOKE COUNTY LINE
ToFM 1417
CSJ0045-18-046
Proj IDSTP 2023(138)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
17.7304127327.500.000.0
CountyGRAYSON
HighwayUS 82
FromFM 1417
ToFM 131
CSJ0045-19-062
Proj IDSTP 2023(138)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.4301549099.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days319
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-18-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11223011
Totals5981039.000.000.000.0

CountyGRAYSON
HighwayUS 82
FromAT SOUTHMAYD ROAD
To.
CSJ0045-18-044
Proj IDSTP 2022(799)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5301669470.7016952.001.0
CountyGRAYSON
HighwayUS 82
FromAT SOUTHMAYD ROAD
To.
CSJ0045-18-045
Proj IDSTP 2022(799)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.199182496.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-28-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days78
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0045-18-044
XROADS, L.P. (0.64)
JR WEST TEXAS CONCRETE LLC (1.96)
DUSTROL, INC. (1.61)
SCR CIVIL CONSTRUCTION, LLC (12.33)
TRP CONSTRUCTION GROUP, LLC (1.45)
SOUTHERN CROSS CONTRACTORS, LLC (0.89)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.46)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.48)
Contract #08223226
Totals1851966.700.0016952.000.9

CountyFANNIN
HighwayUS 82
From0.5 MILES WEST OF SH 121
ToSH 78 (0.478 MI EAST OF SH 78)
CSJ0045-20-018
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
2.03112156062.2412294549.7999.9
CountyFANNIN
HighwayUS 82
From0.478 MI E OF SH 78
ToFM 100
CSJ0045-21-011
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
14.48749116732.2351086699.1599.9
CountyFANNIN
HighwayUS 82
FromFM 100
To0.5 MILES EAST OF SH 56
CSJ0045-21-012
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
2.63610365091.2611227294.2399.9
Work Order08-24-18
Work Began10-18-18
Work Completed
Time Computed09-24-18
Contract Working Days928
Addl Days Granted0
Working Days Charged927
Percent Time Used99
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0045-20-018
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.13)
W.O.E. CONSTRUCTION (0.70)
STRIPING TECHNOLOGY, L.P. (0.83)
LYON BARRICADE AND CONSTRUCTION CO. (0.20)
HAMMETT EXCAVATION, INC. (23.92)
TEXAS SHAFTS, INC. (0.93)
BOWMAN ENGINEERING & CONSULTING, INC. (0.16)
MCL CONTRACTING, LLC (0.06)
RAMBO CONTRACTING, INC. (3.95)
CDM HOLDINGS, LLC (3.64)
GANT CONTRACTORS, INC. (0.11)
SOUTHERN CROSS CONTRACTORS, LLC (0.61)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.50)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.05)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.38)
ALTUS TRAFFIC MANAGEMENT LLC (0.04)
SOUTHEAST GRINDING AND GROOVING LLC (0.00)
TEXOP CONSTRUCTION (0.03)
WOOD WATERING SERVICE LLC (0.00)
WITHERS CONSTRUCTION, LLC (0.37)
O. TREVINO CONSTRUCTION, LLC (0.12)
AIMS COMPANIES (0.18)
Contract #07183002
Totals71637885.735057.6474608543.1799.9

CountyGRAYSON
HighwayUS 75
FromSH 91
To0.651 MI S OF CENTER STREET
CSJ0047-02-150
Proj IDNH 2020(008)
Work TypeWIDEN FREEWAY
 
4.763154683155.29116572078.3575.3
Work Order10-10-19
Work Began01-13-20
Work Completed
Time Computed11-11-19
Contract Working Days827
Addl Days Granted290
Working Days Charged833
Percent Time Used74
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0047-02-150
TOTAL HIGHWAY MAINTENANCE, LLC (1.02)
J. H. ODEN CONTRACTING COMPANY (0.14)
MICA CORPORATION (4.27)
A BROTHERS MILLING, LLC (0.29)
DURABLE SPECIALTIES, INC. (1.89)
PREMIER PAVING, LTD. (9.00)
ANCORTEX, INC. (2.99)
W.O.E. CONSTRUCTION, INC. (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.00)
ANTIGO CONSTRUCTION, INC. (0.00)
ROYAL REBAR (0.00)
SCOTT DERR PAINTING CO, LLC (0.06)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.79)
FORTSON CONTRACTING, INC. (0.31)
SOUTHEAST GRINDING & GROOVING, LLC (0.06)
ACT SAW CUTTING & REMOVAL (0.13)
H TORRES TRUCKING, L.L.C. (0.71)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.08)
PANTHER CREEK TRANSPORTATION, INC. (0.43)
HERMANOS STEEL, LLC (0.09)
HERDEZ TRUCKING, INC. (3.23)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (5.52)
TORO BRAVO CONSTRUCTION, LLC (0.03)
Contract #09193201
Totals154683155.291962964.91116572078.3575.3

CountyGRAYSON
HighwaySH 5
FromNEWPORT DR AT PARTIN ELEMENTARY SCHOOL
To0.645 MI S OF FM 3133 AT MOORE PARK
CSJ0047-03-096
Proj IDSTP 2021(597)TAPS
Work TypeBICYCLE INFRASTRUCTURE IMPROVEMENTS
 
0.427662920.28619652.1193.4
Work Order02-15-22
Work Began04-20-22
Work Completed
Time Computed05-23-22
Contract Working Days93
Addl Days Granted0
Working Days Charged85
Percent Time Used91
Contractor(s)
THE FAIN GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-096
FORTSON CONTRACTING, INC. (2.60)
BUYERS BARRICADES, INC. (4.71)
MASSEY CONTRACTORS, LLC (1.71)
G J SEEDING, LLC (4.90)
SPORTSCAPES CONSTRUCTION, L.L.C. (9.32)
Contract #12213021
Totals662920.282764.45619652.1193.4

CountyGRAYSON
HighwayBU 377B
FromUS 377 N
ToUS 377 S
CSJ0081-08-011
Proj IDF 2022(530)
Work TypeOVERLAY
 
4.7991709161.871505671.3388.2
CountyGRAYSON
HighwayFM 84
FromEND OF MAINTENANCE
ToUS 75
CSJ0316-02-026
Proj IDF 2022(530)
Work TypeOVERLAY
 
5.694913381.35993700.1699.9
CountyFANNIN
HighwaySH 11
FromSH 121
ToSH 121 D SOUTH
CSJ2139-02-012
Proj IDF 2022(530)
Work TypeOVERLAY
 
0.30333302.25792.962.3
CountyFANNIN
HighwaySH 11
FromSH 121 D SOUTH
ToSH 78 (BAILEY)
CSJ2139-03-022
Proj IDF 2022(530)
Work TypeOVERLAY
 
6.7331537377.731464511.4395.2
Work Order06-16-22
Work Began07-15-22
Work Completed
Time Computed07-18-22
Contract Working Days63
Addl Days Granted0
Working Days Charged65
Percent Time Used103
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0081-08-011
FLEX SUPPLY, LLC (0.35)
TOTAL HIGHWAY MAINTENANCE, LLC (4.94)
J. H. ODEN CONTRACTING COMPANY (0.51)
JM YANEZ CONSTRUCTION, INC. (0.99)
SOUTHERN CROSS CONTRACTORS, LLC (1.22)
TEXOP CONSTRUCTION (0.34)
S2 RENTALS AND SALES, LLC (0.13)
TRP CONSTRUCTION GROUP, LLC (5.15)
BARRICADES UNLIMITED (5.37)
Contract #05223218
Totals4193223.2011158.753964675.8894.5

CountyHOPKINS
HighwaySH 154
FromRADIO RD
ToSH11
CSJ0083-03-056
Proj IDSTP 2021(409)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.181270345.75269560.9799.9
CountyRAINS
HighwaySH 19
FromAT FM 2324
To.
CSJ0108-11-021
Proj IDSTP 2021(409)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20037317.1441877.2499.9
CountyRAINS
HighwayUS 69
FromSH 276
ToFM 2795
CSJ0203-03-049
Proj IDSTP 2021(409)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.523102472.9783844.3881.8
Work Order04-16-21
Work Began01-31-22
Work Completed
Time Computed07-15-21
Contract Working Days43
Addl Days Granted0
Working Days Charged60
Percent Time Used139
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0083-03-056
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.71)
WG ENGINEERING & CONSTRUCTION, LLC (9.91)
Contract #03213222
Totals410135.860.00395282.5998.8

CountyGRAYSON
HighwayFS 121
FromFM 121
ToCOUNTY LINE ROAD
CSJ0091-10-002
Proj IDF 2021(862)
Work TypeNEW LOCATION NON-FREEWAY
 
4.4769300300.068446237.7590.8
Work Order10-20-21
Work Began11-29-21
Work Completed
Time Computed11-18-21
Contract Working Days328
Addl Days Granted0
Working Days Charged222
Percent Time Used67
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0091-10-002
BARRICADES UNLIMITED (0.10)
PEACHTREE CONSTRUCTION, LTD. (3.26)
TRP CONSTRUCTION GROUP, LLC (0.78)
WEST TEXAS ROCK RESOURCES, LLC (0.07)
FORTSON CONTRACTING, INC. (0.62)
SOUTHERN CROSS CONTRACTORS, LLC (0.51)
RAMBO CONTRACTING, INC. (4.55)
J. H. ODEN CONTRACTING COMPANY (1.76)
Contract #09213220
Totals9300300.0697849.128446237.7590.8

page 1 | page 2 | page 3 | page 4