Monthly State Let Maintenance Report For Pharr District As Of Jul 13, 2021 Page 1 Of 3

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
Highway0000000
From600 WEST ESPRESSWAY 83, PHARR, TEXAS
To600 WEST ESPRESSWAY 83, PHARR, TEXAS
CSJ4704-01-684
Proj IDCBC - 470401684
Work TypeLABORATORY HVAC UPGRADE - PHARR DHQ
 
0.001499000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALPHA BUILDING CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-684
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164213
Totals499000.000.000.000.0

CountyHIDALGO
Highway0000000
From600 WEST US EXPRESSWAY 83 PHARR TEXAS
To600 WEST US EXPRESSWAY 83 PHARR TEXAS
CSJ4704-01-775
Proj IDCBC - 470401775
Work TypePHARR DHQ ELECTRICAL AND GENERATOR UPGRA
 
0.001519800.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FSG FACILITY SOLUTIONS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-775
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164227
Totals519800.000.000.000.0

CountyCAMERON
HighwayPR0100
FromCAMERON COUNTY
ToCAMERON COUNTY
CSJ6175-04-001
Proj IDBPM - 617504001
Work TypeBPM QIC BRIDGE DECK REPAIR
 
0.00197702.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6175-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02082103
Totals97702.000.000.000.0

CountyHIDALGO
HighwayUS0083
FromHIDALGO, CAMERON, STARR AND WILLACY
ToVARIOUS LOCATIONS
CSJ6229-70-001
Proj IDRMC - 622970001
Work TypeINSTALLATION OF HIGHWAY TRAFFIC SIGNALS
 
0.010915093.201647473.23100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-06-12
Work Began03-26-12
Work Completed04-30-15
Time Computed03-19-12
Contract Working Days345
Addl Days Granted120
Working Days Charged524
Percent Time Used112
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6229-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01124014
Totals915093.200.001647473.23100.0

CountyCAMERON
HighwayUS0077
FromCAMERON COUNTY
ToUS 77, US 83, US 77/83
CSJ6232-75-001
Proj IDRMC - 623275001
Work TypeCLEANING AND SWEEPING, DEBRIS REMOVAL
 
0.010474624.151038006.2199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-17-11
Work Began12-06-11
Work Completed
Time Computed12-09-11
Contract Working Days378
Addl Days Granted458
Working Days Charged664
Percent Time Used79
Contractor(s)
BENTEX SWEEPING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6232-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10114037
Totals474624.150.001038006.2199.9

CountyCAMERON
HighwayUS0077
FromVARIOUS HIGHWAYS IN DISTRICT 21
ToVARIOUS HIGHWAYS IN DISTRICT 21
CSJ6253-67-001
Proj IDRMC - 625367001
Work TypeCALLOUT DEBRIS REMOVAL AFTER A HURRICANE
 
0.001611800.004491.000.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-13
Work Began08-30-13
Work Completed
Time Computed08-30-13
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04134036
Totals611800.000.004491.000.7

CountyCAMERON
HighwaySH0100
FromSH 100 .15 MILES EAST OF BOSQUES ST
ToSH 100 .4 MILES WEST PALM ST
CSJ6268-29-001
Proj IDRMC - 626829001
Work TypeMETAL BEAM GUARD FENCE INSTALLATION
 
0.010473198.58659312.6299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-24-14
Work Began04-14-14
Work Completed
Time Computed04-14-14
Contract Working Days40
Addl Days Granted49
Working Days Charged68
Percent Time Used76
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6268-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02144033
Totals473198.580.00659312.6299.9

CountyCAMERON
HighwaySH0004
From4,850 FT. EAST OF FM 1419
ToEND OF STATE MAINTENANCE
CSJ6295-93-001
Proj IDRMC - 629593001
Work TypeREHABILITATION ON SH 04
 
0.0103036343.552801842.0192.2
Work Order11-22-16
Work Began01-09-17
Work Completed
Time Computed01-02-17
Contract Working Days120
Addl Days Granted58
Working Days Charged160
Percent Time Used89
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164217
Totals3036343.550.002801842.0192.2

CountyHIDALGO
HighwayFM1015
FromHIDALGO COUNTY
ToZAPATA COUNTY
CSJ6296-79-001
Proj IDRMC - 629679001
Work TypeACP OVERLAY WORK
 
0.0104485273.804699572.2999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-13-17
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted21
Working Days Charged101
Percent Time Used100
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174209
Totals4485273.800.004699572.2999.9

CountyCAMERON
HighwayUS0083
FromVARIOUS HIGHWAYS IN PHARR DISTRICT
ToVARIOUS HIGHWAYS IN PHARR DISTRICT
CSJ6316-29-001
Proj IDRMC - 631629001
Work TypeDEBRIS REMOVAL AND DISPOSAL
 
0.001599300.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
T.F.R. ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174216
Totals599300.000.000.000.0

CountyHIDALGO
HighwayFM1015
FromFM 1015
ToI-69E
CSJ6318-29-001
Proj IDBPM - 631829001
Work TypeBPM
 
0.010827634.401340818.87100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed02-29-20
Time Computed00-00-00
Contract Working Days120
Addl Days Granted66
Working Days Charged179
Percent Time Used96
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03184007
Totals827634.40840.001340818.87100.0

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6321-71-001
Proj IDRMC - 632171001
Work TypePAVEMENT REPAIR
 
0.0104016934.134325232.9599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-05-18
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted140
Working Days Charged210
Percent Time Used75
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174219
Totals4016934.1393770.324325232.9599.9

CountyHIDALGO
HighwaySH0107
FromVARIOUS
ToVARIOUS
CSJ6321-85-001
Proj IDRMC - 632185001
Work TypeDISTRICTWIDE OVERLAY
 
0.0105265199.456356243.24100.0
Work Order02-13-19
Work Began05-20-19
Work Completed12-31-20
Time Computed05-20-19
Contract Working Days100
Addl Days Granted100
Working Days Charged180
Percent Time Used90
Contractor(s)
EARTHWORKS ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6321-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194023
Totals5265199.450.006356243.24100.0

CountyHIDALGO
HighwayUS0083
FromHIDALGO, CAMERON, STARR, AND WILLACY
ToVARIOUS LOCATIONS
CSJ6323-90-001
Proj IDRMC - 632390001
Work TypeINSTALLATION OF HIGHWAY TRAFFIC SIGNALS
 
0.010778138.001366419.1599.9
Work Order02-09-18
Work Began05-07-18
Work Completed
Time Computed05-01-18
Contract Working Days220
Addl Days Granted200
Working Days Charged386
Percent Time Used91
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184012
Totals778138.000.001366419.1599.9

CountyHIDALGO
HighwayIH0002
FromIH-2, IH-69C & IH-69E
ToVARIOUS LOCATIONS WITHIN PHARR DISTRICT
CSJ6323-92-001
Proj IDRMC - 632392001
Work TypeINSTALLATION/REMOVAL OF LARGE/SMALL SIGN
 
0.010867629.75901391.6399.9
Work Order05-14-18
Work Began00-00-00
Work Completed
Time Computed08-31-18
Contract Working Days204
Addl Days Granted100
Working Days Charged302
Percent Time Used99
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184024
Totals867629.750.00901391.6399.9

CountySTARR
HighwayUS0083
FromSTARR/ZAPATA COUNTY
ToJIM HOGG/BROOKS COUNTY
CSJ6325-70-001
Proj IDRMC - 632570001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
0.010450285.36716562.3399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-23-18
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted100
Working Days Charged178
Percent Time Used52
Contractor(s)
CTX SPECIAL SERVICES CO LLC
SUBCONTRACTOR(S) FOR CCSJ: 6325-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184216
Totals450285.3618398.00716562.3399.9

CountyHIDALGO
HighwayIH0002
FromHIDALGO
ToCAMERON
CSJ6328-33-001
Proj IDRMC - 632833001
Work TypeINSTALLATION OF CCTV
 
0.010772050.50654195.7084.7
Work Order11-01-18
Work Began00-00-00
Work Completed
Time Computed11-01-18
Contract Working Days180
Addl Days Granted80
Working Days Charged242
Percent Time Used93
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6328-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184012
Totals772050.500.00654195.7084.7

CountyCAMERON
HighwayUS0083
FromVARIOUS HIGHWAYS IN PHARR DISTRICT
ToVARIOUS HIGHWAYS IN PHARR DISTRICT
CSJ6331-98-001
Proj IDRMC - 633198001
Work TypeDEBRIS REMOVAL AND DISPOSAL
 
0.0011168120.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-27-18
Work Began09-01-18
Work Completed
Time Computed09-01-18
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6331-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184024
Totals1168120.000.000.000.0

CountyCAMERON
HighwayFM1847
FromCAMERON_COUNTY
ToWILLACY COUNTY
CSJ6332-58-001
Proj IDRMC - 633258001
Work TypeFM MOWING
 
0.010849302.521698405.2499.9
Work Order09-19-18
Work Began10-26-18
Work Completed
Time Computed10-26-18
Contract Working Days200
Addl Days Granted46
Working Days Charged106
Percent Time Used43
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6332-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184013
Totals849302.52212301.671698405.2499.9

CountyHIDALGO
HighwayFM0490
FromHIDALGO COUNTY
ToVARIOUS ROADWAYS
CSJ6332-59-001
Proj IDRMC - 633259001
Work TypeFM MOWING
 
0.010726084.051070203.1499.9
Work Order09-19-18
Work Began11-08-18
Work Completed
Time Computed11-05-18
Contract Working Days140
Addl Days Granted140
Working Days Charged97
Percent Time Used34
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6332-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184210
Totals726084.0513547.231070203.1499.9

page 1 | page 2 | page 3