Monthly State Let Construction Report For San Antonio District As Of Jul 13, 2021 Page 1 Of 7

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOMAL
HighwayIH 35
FromGUADALUPE RIVER
ToFM 306
CSJ0016-04-115
Proj IDNH 2019(775)
Work TypeOVERLAY
 
3.3214185078.96452303.2810.8
CountyCOMAL
HighwayIH 35
From1.2 MILES SOUTH OF FM 306
ToFM 306
CSJ0016-04-116
Proj IDNH 2019(775)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
14245900.5312250484.2984.1
Work Order07-17-19
Work Began09-16-19
Work Completed
Time Computed08-16-19
Contract Working Days476
Addl Days Granted210
Working Days Charged442
Percent Time Used64
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-115
TRP CONSTRUCTION GROUP, LLC (2.90)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.87)
ROADWAY SPECIALTIES, INC. (1.61)
JB PINNACLE GROUP, LLC (7.72)
GEOSOURCE, INC. (0.10)
EARTH REINFORCEMENTS LLC (3.85)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06)
THE LEVY COMPANY, INC. (5.57)
AARON CONCRETE CONTRACTORS, L.P. (2.85)
LONE STAR SITEWORK, LLC (0.13)
AUSTIN FORMULA UTILITIES, LIMITED LIABILITY COMPANY (0.00)
Contract #06193001
Totals18430979.49306543.3312702787.5767.5

CountyCOMAL
HighwayIH 35
FromFM 306
ToHAYS/COMAL COUNTY LINE
CSJ0016-04-117
Proj IDNH 1902(057)
Work TypeFOI
 
3.83863795147.3038459569.0860.2
Work Order07-17-19
Work Began03-16-20
Work Completed
Time Computed08-16-19
Contract Working Days659
Addl Days Granted0
Working Days Charged370
Percent Time Used56
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-04-117
TEXAS R & G CONSTRUCTION SERVICES LLC (0.60)
LONE STAR EROSION CONTROL (0.57)
FLASHER EQUIPMENT COMPANY (0.98)
ADCOCK 4 INVESTMENTS, LLC (2.56)
BUYERS BARRICADES SAN ANTONIO, LLC (0.73)
VOGES DRILLING CO. (0.79)
LONE STAR PAVING COMPANY (21.46)
M-CO CONSTRUCTION, INC. (1.13)
ROYAL REBAR (2.84)
AARON CONCRETE CONTRACTORS, L.P. (0.45)
THE LEVY COMPANY, INC. (2.51)
SCOTT DERR PAINTING CO, LLC (0.30)
FRANK JR REINFORCEMENT LLC (0.08)
ANCORTEX, INC. (0.49)
MTAM CORPORATION (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.07)
TEXAS HIGHWAY WALLS (7.45)
HOWELL CRANE & RIGGING, INC. (0.04)
TEXAS CUTTING & CORING GP, INC. (0.12)
PENHALL COMPANY (0.01)
Contract #06193010
Totals63795147.302447307.1038459569.0860.2

CountyCOMAL ETC
HighwayIH 35 ETC
FromGUADALUPE COUNTY LINE
To1.2 MILES SOUTH OF LP 337
CSJ0016-05-118
Proj IDNH 2018(178)
Work TypeSEAL COAT AND PAVEMENT MARKINGS
 
271.72810109086.0214155597.1999.9
Work Order11-10-17
Work Began04-28-18
Work Completed
Time Computed12-10-17
Contract Working Days100
Addl Days Granted42
Working Days Charged122
Percent Time Used85
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-118
INTERSTATE BARRICADES & MARKINGS, INC. (20.54)
COX PAVING COMPANY OF TEXAS, INC. (6.37)
Contract #10173002
Totals10109086.020.0014155597.1999.9

CountyCOMAL
HighwayIH 35
FromFM 2252
ToSCHWAB RD
CSJ0016-05-119
Proj IDNH 2019(507)
Work TypeGRAD, STR, BASE & SURF
 
3.09824566550.7220471648.0383.4
CountyZERO COUNTIES
Highway
From
To
CSJ0016-05-121
Proj ID
Work Type
 
0.007921.800.0
Work Order03-18-19
Work Began07-09-19
Work Completed
Time Computed04-17-19
Contract Working Days441
Addl Days Granted176
Working Days Charged560
Percent Time Used90
Contractor(s)
BRIDGES AND ROADS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-119
TRP CONSTRUCTION GROUP, LLC (1.06)
ADCOCK 4 INVESTMENTS, LLC (2.71)
FLASHER EQUIPMENT COMPANY (1.14)
JB PINNACLE GROUP, LLC (5.24)
AUSTIN MATERIALS, LLC (40.67)
DIAMOND M FIELD SERVICES LLC (0.02)
K. L. DURHAM CONSTRUCTION, L.L.C. (4.90)
THE LEVY COMPANY, INC. (2.44)
GEOSOURCE, INC. (1.11)
ELITECURB & CONCRETE, LLC (1.89)
AREA WIDE PROTECTIVE, INC. (0.16)
DIIBS SPECIALISTS, LLC (0.39)
US CONTRACTING SERVICES (0.29)
JAG PUBLIC SAFETY, LLC (0.50)
SAN ANTONIO SWEEPING SERVICES, INC. (0.10)
AARON CONCRETE CONTRACTORS, L.P. (0.16)
DOMO CONSTRUCTION COMMERCIAL DIVISION LLC (0.29)
Contract #02193201
Totals24566550.722155488.1020479569.8383.5

CountyCOMAL
HighwayIH 35
FromAT FM 725
To.
CSJ0016-05-120
Proj IDC 16-5-120
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
0.2765144829.210.000.0
CountyCOMAL
HighwayIH 35
FromAT FM 725
To.
CSJ0016-05-124
Proj IDROW 0016-05-124
Work TypeRIGHT OF WAY
 
0.276846.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days283
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213209
Totals5145675.210.000.000.0

CountyBEXAR
HighwaySL 368
FromAT SALADO CREEK AND IRA LEE RD.
To.
CSJ0016-08-039
Proj IDBR 2021(485)
Work TypeBRIDGE REPLACEMENT
 
0.1406694601.990.000.0
CountyBEXAR
HighwaySL 368
FromAT SALADO CREEK AND IRA LEE RD.
To.
CSJ0016-08-044
Proj IDROW 16-8-44
Work TypeRIGHT OF WAY
 
0.140280195.000.000.0
Work Order05-20-21
Work Began07-12-21
Work Completed
Time Computed06-21-21
Contract Working Days481
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-08-039
TEXAS ICON CONSTRUCTION, LLC (0.98)
TEXAS MATERIALS GROUP, INC. (4.13)
HB FARMER FOUNDATION, LLC (6.57)
Contract #04213003
Totals6974796.990.000.000.0

CountyBEXAR
HighwayIH 35
From1.8 MI. EAST OF LP 1604 (QUEST RD.)
To0.3 MI. NORTH OF IH 410
CSJ0017-02-080
Proj IDNH 2021(203)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.118146973.348978.626.1
CountyBEXAR
HighwayIH 35
FromLP 1604
To1.8 MI. NORTH OF LP 1604 (QUEST RD.
CSJ0017-03-069
Proj IDNH 2021(203)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.74979024.420.000.0
CountyBEXAR
HighwayIH 35
From0.3 MI. NORTH OF IH 410
ToLP 13 (SW MILITARY)
CSJ0017-09-110
Proj IDNH 2021(203)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.145260981.060.000.0
Work Order04-08-21
Work Began00-00-00
Work Completed
Time Computed07-07-21
Contract Working Days235
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-080
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (3.38)
Contract #03213029
Totals486978.828978.628978.621.8

CountyBEXAR
HighwayIH 35
FromAT BENTON CITY RD
To.
CSJ0017-03-066
Proj IDNH 2020(401)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
0.514319940.00288210.0090.0
Work Order01-06-20
Work Began03-09-20
Work Completed
Time Computed02-05-20
Contract Working Days62
Addl Days Granted0
Working Days Charged36
Percent Time Used58
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-03-066
AREA WIDE PROTECTIVE, INC. (1.07)
Contract #12193233
Totals319940.001000.00288210.0090.0

CountyATASCOSA
HighwayIH 35
FromATASCOSA/BEXAR COUNTY LINE
ToATASCOSA/MEDINA COUNTY LINE
CSJ0017-04-042
Proj IDNH 2019(646)
Work TypeBSE, SURF, PAV'T MRKINGS
 
2.5063383807.084902353.7299.9
CountyZERO COUNTIES
Highway
From
To
CSJ0017-04-047
Proj ID
Work Type
 
0.00101193.200.0
CountyMEDINA
HighwayIH 35
FromFRIO/MEDINA COUNTY LINE
ToMEDINA/ATASCOSA COUNTY LINE
CSJ0017-05-094
Proj IDNH 2019(646)
Work TypeBSE, SURF, PAV'T MRKINGS
 
12.6849526910.409940711.5599.9
CountyZERO COUNTIES
Highway
From
To
CSJ0017-05-098
Proj ID
Work Type
 
0.00834984.550.0
Work Order04-25-19
Work Began07-10-19
Work Completed
Time Computed05-25-19
Contract Working Days345
Addl Days Granted0
Working Days Charged295
Percent Time Used85
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-042
DEPENDABLE FENCE & WELDING CO. INC. (5.02)
RELMCO, INC. (8.01)
FLASHER EQUIPMENT COMPANY (5.81)
PERFORMANCE EQUIPMENT SERVICE (3.99)
ALL AMERICAN TRUCKING, INC. (1.47)
BUYERS BARRICADES SAN ANTONIO, LLC (0.02)
ROADWAY SPECIALTIES, INC. (12.48)
WEST TEXAS ROCK RESOURCES, LLC (0.15)
CHEROKEE SERVICES (1.35)
G 6 CONSTRUCTION, INC. (1.28)
Contract #03193204
Totals12910717.48739853.3615779243.0299.9

CountyATASCOSA ETC
HighwayIH 35 ETC
FromMEDINA COUNTY LINE (WFR)
ToATASCOSA RIVER (NORTH PRONG)
CSJ0017-04-043
Proj IDNH 2020(104)
Work TypeSEAL COAT
 
309.42714999998.3116466883.4699.9
Work Order12-06-19
Work Began01-06-20
Work Completed
Time Computed01-05-20
Contract Working Days205
Addl Days Granted0
Working Days Charged203
Percent Time Used99
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-043
INTERSTATE BARRICADES & MARKINGS, INC. (26.85)
COX PAVING OF TEXAS, INC. (7.10)
Contract #10193205
Totals14999998.31206956.4316466883.4699.9

CountyATASCOSA ETC
HighwayIH 35 ETC
FromATASCOSA / MEDINA COUNTY LINE
ToFM 3175
CSJ0017-04-045
Proj IDNH 2021(065)
Work TypeSEAL COAT
 
322.16015948518.982474613.1415.5
Work Order11-19-20
Work Began00-00-00
Work Completed
Time Computed02-17-21
Contract Working Days277
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0017-04-045
VIZCAINO, L.P. (29.89)
FLASHER EQUIPMENT COMPANY (1.31)
COX PAVING OF TEXAS, INC. (14.40)
TOTAL HIGHWAY MAINTENANCE, LLC (0.33)
Contract #10203010
Totals15948518.98317204.842474613.1415.5

CountyMEDINA ETC
HighwayIH 35 ETC
FromAT FM 471
To.
CSJ0017-05-095
Proj IDSTP 1802(614)HES
Work TypeINTERSECTION FLASHING BEACON
 
3.8002442867.711906926.9978.0
Work Order09-24-18
Work Began06-03-19
Work Completed
Time Computed10-24-18
Contract Working Days466
Addl Days Granted6
Working Days Charged399
Percent Time Used84
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-05-095
FLASHER EQUIPMENT COMPANY (1.50)
JT UNDERGROUND AND UTILITY CONSTRUCTION INC (1.62)
G 6 CONSTRUCTION, INC. (1.31)
Contract #08183051
Totals2442867.7134284.601906926.9978.0

CountyFRIO
HighwayIH 35
FromFM 3352
ToFM 462
CSJ0017-06-084
Proj IDNH 2018(910)
Work TypeGR, BASE, SURF, PVMT MRKINGS
 
6.42813995985.0214360735.4999.9
Work Order06-14-18
Work Began07-14-18
Work Completed
Time Computed07-14-18
Contract Working Days358
Addl Days Granted0
Working Days Charged353
Percent Time Used98
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-06-084
EGGEMEYER LAND CLEARING, LLC (0.58)
FLASHER EQUIPMENT COMPANY (2.12)
SAECO ELECTRIC & UTILITY, LTD. (0.10)
DELGADO"S CONTRACTORS, LLC (6.67)
ALL AMERICAN TRUCKING, INC. (3.57)
K. L. DURHAM CONSTRUCTION, L.L.C. (2.02)
J & P PAVING CO. (0.15)
DEPENDABLE FENCE & WELDING CO. INC. (0.67)
WEST TEXAS ROCK RESOURCES, LLC (0.03)
G 6 CONSTRUCTION, INC. (0.90)
RELMCO, INC. (0.07)
Contract #05183056
Totals13995985.020.0014360735.4999.9

CountyFRIO
HighwayIH 35
FromFM 140
ToUS 57
CSJ0017-06-085
Proj IDNH 2019(900)
Work TypeOVERLAY
 
9.7827715069.157880461.1299.9
CountyFRIO
HighwayIH 35
FromLA SALLE/FRIO COUNTY LINE
ToFM 140
CSJ0017-07-135
Proj IDNH 2019(900)
Work TypeOVERLAY
 
18.78715405952.9915040775.6697.6
CountyATASCOSA
HighwayIH 37
From1.1 MILES SOUTH OF US 281
To0.5 MI SOUTH OF FM 541
CSJ0073-05-072
Proj IDNH 2019(900)
Work TypeOVERLAY
 
4.7392195399.312148486.9497.8
CountyATASCOSA
HighwayIH 37
From0.7 MI SOUTH OF US 281
To1.1 MILES SOUTH OF US 281
CSJ0073-10-052
Proj IDNH 2019(900)
Work TypeOVERLAY
 
0.390215684.62260468.4499.9
Work Order06-17-19
Work Began10-21-19
Work Completed
Time Computed07-17-19
Contract Working Days303
Addl Days Granted0
Working Days Charged283
Percent Time Used93
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-06-085
INTERSTATE BARRICADES & MARKINGS, INC. (3.52)
ROADWAY SPECIALTIES, INC. (10.17)
LONE STAR EROSION CONTROL (1.28)
PRIMATE CONSTRUCTION, LP (1.99)
TEXAS R & G CONSTRUCTION SERVICES LLC (4.45)
WEST TEXAS ROCK RESOURCES, LLC (0.15)
FLASHER EQUIPMENT COMPANY (0.19)
CONCAN SERVICES LLC (0.09)
C AND H PAVING INC (2.43)
RELMCO, INC. (0.04)
ANGEL BROTHERS ENTERPRISES, LTD. (7.28)
RPV CONSTRUCTION, LLC (0.00)
Contract #05193204
Totals25532106.07516054.1925330192.1699.2

CountyFRIO ETC
HighwayIH 35 ETC
FromAT FM 1581
To.
CSJ0017-07-136
Proj IDSTP 1902(204)HES
Work TypeSFT
 
13.884952818.04966343.8299.9
Work Order08-13-19
Work Began06-22-20
Work Completed
Time Computed09-12-19
Contract Working Days185
Addl Days Granted0
Working Days Charged165
Percent Time Used89
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-07-136
FLASHER EQUIPMENT COMPANY (14.37)
WEST TEXAS ROCK RESOURCES, LLC (2.46)
ALAMO CRANE SERVICE, INC. (1.63)
LOZANO CONSTRUCTION COMPANY, INC. (2.28)
FIBERTEL, LLC (2.62)
CATO ELECTRIC COMPANY (0.31)
KING DUSTY SWEEPING, LLC (0.34)
TEXAS SITE SERVICES, LLC (0.34)
Contract #07193045
Totals952818.04263.71966343.8299.9

CountyBEXAR
HighwayIH 35
From0.9 MILES N OF IH 410
To0.3 MILES N OF IH 410
CSJ0017-09-105
Proj IDNH 1902(205)
Work TypeLSE
 
0.583641593.00585115.0091.1
Work Order08-15-19
Work Began11-18-19
Work Completed
Time Computed09-14-19
Contract Working Days100
Addl Days Granted0
Working Days Charged75
Percent Time Used75
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-09-105
FLASHER EQUIPMENT COMPANY (1.79)
Contract #07193032
Totals641593.002000.00585115.0091.1

CountyBEXAR
HighwayIH 35
FromPINE ST
ToUNION PACIFIC RAILROAD
CSJ0017-10-286
Proj IDNH 1802(386)
Work TypeLANDSCAPE DEVELOPMENT
 
1.750542994.35563048.5799.9
Work Order08-03-18
Work Began10-01-18
Work Completed
Time Computed09-02-18
Contract Working Days82
Addl Days Granted0
Working Days Charged81
Percent Time Used98
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-286
FLASHER EQUIPMENT COMPANY (1.72)
Contract #07183233
Totals542994.352000.00563048.5799.9

CountyBEXAR ETC
HighwayIH 35 ETC
FromN SANTA ROSA ST
ToN FLORES ST
CSJ0017-10-288
Proj IDSTP 1902(206)HES
Work TypeSFT
 
7.1611477236.881530549.8599.9
Work Order08-13-19
Work Began04-14-20
Work Completed
Time Computed09-12-19
Contract Working Days150
Addl Days Granted0
Working Days Charged136
Percent Time Used90
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-288
ALAMO CRANE SERVICE, INC. (1.57)
LOZANO CONSTRUCTION COMPANY, INC. (2.07)
FLASHER EQUIPMENT COMPANY (7.07)
CATO ELECTRIC COMPANY (0.20)
Contract #07193249
Totals1477236.884140.561530549.8599.9

CountyUVALDE ETC
HighwayUS 90 ETC
FromKINNEY CO LINE
ToFM 481
CSJ0023-05-086
Proj IDSTP 2021(672)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
21.1171296838.290.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days224
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0023-05-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213231
Totals1296838.290.000.000.0

CountyUVALDE ETC
HighwayUS 90 ETC
FromAT FM 2369
To.
CSJ0024-01-105
Proj IDSTP 1902(207)HES
Work TypeSFT
 
4.4001455288.951186105.5581.5
Work Order08-22-19
Work Began04-16-19
Work Completed
Time Computed09-21-19
Contract Working Days120
Addl Days Granted57
Working Days Charged164
Percent Time Used92
Contractor(s)
F & W ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0024-01-105
FLASHER EQUIPMENT COMPANY (3.28)
Contract #07193036
Totals1455288.956045.001186105.5581.5