Monthly Local Let Maintenance Report For San Antonio District As Of Jul 13, 2021 Page 1 Of 4

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS
ToIN BEXAR COUNTY
CSJ6194-73-001
Proj IDRMC - 619473001
Work TypeLITTER PICK UP
 
0.00159313.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GOLDEN ARBOR TEC LLC
SUBCONTRACTOR(S) FOR CCSJ: 6194-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09091505
Totals59313.600.000.000.0

CountyGUADALUPE
HighwayFM0078
FromWEST FORK YOUNG CREEK BRIDGE
ToWEST FORK YOUNG CREEK BRIDGE
CSJ6201-92-001
Proj IDBPM - 620192001
Work TypeSCOUR REPAIR
 
0.10052978.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
C3 ENVIRONMENTAL SPECIALTIES, LP
SUBCONTRACTOR(S) FOR CCSJ: 6201-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01101502
Totals52978.930.000.000.0

CountyBEXAR
HighwayPA1502
FromPA 1502 (WURZBACH PARKWAY)
To(NEW LOCATION)
CSJ6237-07-001
Proj IDRMC - 623707001
Work TypeEXCAVATION
 
0.001455087.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SLACK & CO. CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12111501
Totals455087.600.000.000.0

CountyBEXAR
HighwayFM1957
FromFM1957 AT
ToHEB
CSJ6327-64-001
Proj IDRMC - 632764001
Work TypeINSTALL LOOM TURNAROUND
 
0.001191351.88173517.08100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-09-18
Work Began07-16-18
Work Completed09-03-18
Time Computed07-16-18
Contract Working Days35
Addl Days Granted0
Working Days Charged35
Percent Time Used100
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6327-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05181501
Totals191351.880.00173517.08100.0

CountyBEXAR
HighwayIH0010
FromDISTRICTWIDE
ToVARIOUS ROADWAY
CSJ6342-46-001
Proj IDRMC - 634246001
Work TypeTRAFFIC SIGNAL MAINTENANCE AND REPAIR
 
0.001365445.00549598.0399.9
Work Order06-19-19
Work Began07-01-19
Work Completed
Time Computed07-01-19
Contract Working Days365
Addl Days Granted365
Working Days Charged731
Percent Time Used100
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6342-46-001
ALAMO CRANE SERVICE, INC. (0.70)
FIBERTEL, LLC (2.18)
LOZANO TRUCKING COMPANY, INC. (0.15)
CATO DRILLING COMPANY (0.24)
Contract #04191501
Totals365445.0015483.31549598.0399.9

CountyGUADALUPE
HighwaySH0046
From2024 HWY 46 N
To2024 HWY 46 N
CSJ6347-38-001
Proj IDSUP - 634738001
Work TypeGROUNDS MAINTENANCE
 
0.0018825.203750.7142.5
Work Order07-25-19
Work Began08-01-19
Work Completed
Time Computed08-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged700
Percent Time Used95
Contractor(s)
WORKQUEST
SUBCONTRACTOR(S) FOR CCSJ: 6347-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05191530
Totals8825.20220.633750.7142.5

CountyGUADALUPE
HighwaySH0046
From2024 HWY 46 N
To2024 HWY 46 N
CSJ6347-39-001
Proj IDSUP - 634739001
Work TypeFLOOR MAINTENANCE
 
0.00130180.9663382.0899.9
Work Order07-25-19
Work Began08-01-19
Work Completed
Time Computed08-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged670
Percent Time Used91
Contractor(s)
WORKQUEST
SUBCONTRACTOR(S) FOR CCSJ: 6347-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05191531
Totals30180.963867.5763382.0899.9

CountyMEDINA
HighwayUS0090
FromMEDINA COUNTY
ToMEDINA COUNTY
CSJ6348-48-001
Proj IDRMC - 634848001
Work TypePICNIC AREA MAINTENANCE
 
0.00144300.0035400.0079.9
Work Order10-26-19
Work Began11-04-19
Work Completed
Time Computed11-04-19
Contract Working Days730
Addl Days Granted0
Working Days Charged608
Percent Time Used83
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6348-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08191502
Totals44300.001700.0035400.0079.9

CountyGUADALUPE
HighwaySH0046
From2024 HWY 46 N
To2024 HWY 46 N
CSJ6351-71-001
Proj IDSUP - 635171001
Work TypeJANITORIAL SERVICES
 
0.00122818.9658579.0299.9
Work Order10-01-19
Work Began10-01-19
Work Completed
Time Computed10-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6351-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09191530
Totals22818.963767.8958579.0299.9

CountyKERR
HighwaySH0027
FromSTEEL CREEK
ToAT SH27
CSJ6352-21-001
Proj IDBPM - 635221001
Work TypeBRIDGE PM PROJECT
 
0.001126013.00127854.08100.0
Work Order01-15-21
Work Began01-21-21
Work Completed05-31-21
Time Computed01-21-21
Contract Working Days39
Addl Days Granted7
Working Days Charged31
Percent Time Used67
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6352-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04201501
Totals126013.003698.10127854.08100.0

CountyUVALDE
HighwayUS0090
FromUS0090
ToUS0090
CSJ6354-95-001
Proj IDSUP - 635495001
Work TypeJANITORIAL SERVICES
 
0.00123269.5861217.3399.9
Work Order00-00-00
Work Began11-23-19
Work Completed
Time Computed11-23-19
Contract Working Days730
Addl Days Granted0
Working Days Charged556
Percent Time Used76
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6354-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11191530
Totals23269.583638.0161217.3399.9

CountyFRIO
HighwayFM0140
FromFM0140
ToFM0140
CSJ6354-96-001
Proj IDSUP - 635496001
Work TypeJANITORIAL SERVICES
 
0.00122836.1839036.1999.9
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed11-23-19
Contract Working Days730
Addl Days Granted0
Working Days Charged586
Percent Time Used80
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6354-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11191531
Totals22836.182220.4939036.1999.9

CountyMEDINA
HighwayUS0090
FromMEDINA, MCMULLEN, ATASCSOSA AND
ToFRIO COUNTIES
CSJ6354-98-001
Proj IDMMC - 635498001
Work TypeMATERIAL ONLY EMULSION
 
0.001128640.00104718.3281.4
Work Order11-24-20
Work Began02-10-21
Work Completed
Time Computed12-02-20
Contract Working Days120
Addl Days Granted120
Working Days Charged211
Percent Time Used87
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6354-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03201504
Totals128640.0015632.44104718.3281.4

CountyBEXAR
HighwayIH0035
FromDISTRICTWIDE
ToVARIOUS HIGHWAYS
CSJ6356-77-001
Proj IDRMC - 635677001
Work TypePREVENTIVE MAINT OF TRAFFIC SIGNALS
 
0.001280140.00324946.5099.9
Work Order07-01-20
Work Began07-08-20
Work Completed
Time Computed04-27-20
Contract Working Days365
Addl Days Granted365
Working Days Charged314
Percent Time Used43
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6356-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03201501
Totals280140.0081560.00324946.5099.9

CountyMEDINA
HighwayUS0090
From2304 AVENUE E
To2304 AVENUE E
CSJ6357-35-001
Proj IDSUP - 635735001
Work TypeJANITORIAL SERVICES
 
0.00112473.0469647.5699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-20-20
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged496
Percent Time Used67
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-35-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #01201530
Totals12473.044704.1469647.5699.9

CountyGUADALUPE
HighwayIH0010
FromSEGUIN
ToMAINTENANCE SECTION
CSJ6357-96-001
Proj IDMMC - 635796001
Work TypePURCHASE AND DELIVER OF LRA
 
0.001220940.00442681.1099.9
Work Order12-21-20
Work Began02-23-21
Work Completed
Time Computed12-28-20
Contract Working Days120
Addl Days Granted120
Working Days Charged185
Percent Time Used77
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6357-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03201505
Totals220940.00110496.54442681.1099.9

CountyKENDALL
HighwayIH0010
FromKENDALL, KERR, BANDERA, AND
ToUVALDE COUNTIES (KERR AREA OFFICE)
CSJ6358-97-001
Proj IDMMC - 635897001
Work TypeMATERIAL ONLY DELIVERY OF EMULSION
 
0.001255420.00158487.2462.0
Work Order10-01-20
Work Began03-01-21
Work Completed
Time Computed10-07-20
Contract Working Days120
Addl Days Granted240
Working Days Charged266
Percent Time Used73
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6358-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04201511
Totals255420.0027408.39158487.2462.0

CountyCOMAL
HighwayIH0035
FromCOMAL, GUADALUPE AND
ToWILSON COUNTIES
CSJ6358-98-001
Proj IDMMC - 635898001
Work TypeMATERIAL ONLY DELIVERY OF EMULSION
 
0.001211320.00113226.7653.5
Work Order10-01-20
Work Began10-14-20
Work Completed
Time Computed10-07-20
Contract Working Days120
Addl Days Granted240
Working Days Charged267
Percent Time Used74
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6358-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04201510
Totals211320.0018894.04113226.7653.5

CountyBEXAR
HighwayIH0410
FromVARIOUS LOCATIONS IN_THE EAST BEXAR
ToMAINTENANCE SECTION
CSJ6359-26-001
Proj IDMMC - 635926001
Work TypeMATERIAL ONLY DELIVERY OF HMA
 
0.001271550.00443030.9399.9
Work Order10-01-20
Work Began11-09-20
Work Completed
Time Computed10-07-20
Contract Working Days120
Addl Days Granted240
Working Days Charged267
Percent Time Used74
Contractor(s)
CENTURY ASPHALT, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6359-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04201512
Totals271550.00146463.82443030.9399.9

CountyBEXAR
HighwayIH0410
FromVARIOUS LOCATIONS IN THE WEST BEXAR
ToMAINTENANCE SECTION
CSJ6359-81-001
Proj IDMMC - 635981001
Work TypeMATERIAL ONLY DELIVERY OF HMA
 
0.001270600.00614980.3299.9
Work Order10-01-20
Work Began01-26-21
Work Completed
Time Computed10-07-20
Contract Working Days120
Addl Days Granted120
Working Days Charged237
Percent Time Used98
Contractor(s)
CENTURY ASPHALT, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6359-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04201513
Totals270600.0023506.82614980.3299.9

page 1 | page 2 | page 3 | page 4