Monthly Local Let Maintenance Report For San Antonio District As Of Nov 10, 2024 Page 1 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS
ToIN BEXAR COUNTY
CSJ6194-73-001
Proj IDRMC - 619473001
Work TypeLITTER PICK UP
 
0.00159313.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GOLDEN ARBOR TEC LLC
SUBCONTRACTOR(S) FOR CCSJ: 6194-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09091505
Totals59313.600.000.000.0

CountyGUADALUPE
HighwayFM0078
FromWEST FORK YOUNG CREEK BRIDGE
ToWEST FORK YOUNG CREEK BRIDGE
CSJ6201-92-001
Proj IDBPM - 620192001
Work TypeSCOUR REPAIR
 
0.10052978.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
C3 ENVIRONMENTAL SPECIALTIES, LP
SUBCONTRACTOR(S) FOR CCSJ: 6201-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01101502
Totals52978.930.000.000.0

CountyBEXAR
HighwayPA1502
FromPA 1502 (WURZBACH PARKWAY)
To(NEW LOCATION)
CSJ6237-07-001
Proj IDRMC - 623707001
Work TypeEXCAVATION
 
0.001455087.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SLACK & CO. CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12111501
Totals455087.600.000.000.0

CountyBEXAR
HighwayFM1957
FromFM1957 AT
ToHEB
CSJ6327-64-001
Proj IDRMC - 632764001
Work TypeINSTALL LOOM TURNAROUND
 
0.001191351.88173517.08100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-09-18
Work Began07-16-18
Work Completed09-03-18
Time Computed07-16-18
Contract Working Days35
Addl Days Granted0
Working Days Charged35
Percent Time Used100
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6327-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05181501
Totals191351.880.00173517.08100.0

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS WITHIN KERRVILLE
ToMAINTENANCE SECTIONS
CSJ6382-98-001
Proj IDMMC - 638298001
Work TypeLIMESTONE ROCK AND ASPHALT
 
0.010213205.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6382-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07211510
Totals213205.000.000.000.0

CountyMEDINA
HighwayUS0090
FromVARIOUS LOCATIONS IN HONDO
ToMAINTENANCE SECTION
CSJ6392-26-001
Proj IDMMC - 639226001
Work TypeHOT MIX
 
0.010237750.001022087.7499.9
Work Order01-25-23
Work Began04-03-23
Work Completed
Time Computed02-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged639
Percent Time Used87
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6392-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221510
Totals237750.00130103.061022087.7499.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN EAST AND WEST BEXAR
ToMAINTENANCE SECTIONS
CSJ6406-26-001
Proj IDMMC - 640626001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010266395.00539012.0199.9
Work Order01-10-23
Work Began06-06-23
Work Completed
Time Computed01-17-23
Contract Working Days365
Addl Days Granted366
Working Days Charged654
Percent Time Used89
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221511
Totals266395.00175652.70539012.0199.9

CountyCOMAL
HighwayIH0035
FromVARIOUS LOCATIONS IN NEW BRAUNFELS
ToMAINTENANCE SECTION
CSJ6406-30-001
Proj IDMMC - 640630001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010104450.00137074.1699.9
Work Order00-00-00
Work Began06-05-23
Work Completed
Time Computed02-02-23
Contract Working Days365
Addl Days Granted366
Working Days Charged638
Percent Time Used87
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221512
Totals104450.000.00137074.1699.9

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS IN PLEASANTON
ToMAINTENANCE SECTION
CSJ6406-32-001
Proj IDMMC - 640632001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010283200.001755836.2399.9
Work Order01-12-23
Work Began01-25-23
Work Completed
Time Computed01-19-23
Contract Working Days365
Addl Days Granted366
Working Days Charged652
Percent Time Used89
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221513
Totals283200.001.091755836.2399.9

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN SEGUIN
ToMAINTENANCE SECTION
CSJ6406-36-001
Proj IDMMC - 640636001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010272500.00898641.5399.9
Work Order00-00-00
Work Began01-23-23
Work Completed
Time Computed01-16-23
Contract Working Days365
Addl Days Granted366
Working Days Charged655
Percent Time Used89
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221514
Totals272500.00334352.37898641.5399.9

CountyCOMAL
HighwayIH0035
FromVARIOUS LOCATIONS IN COMAL
ToAND GUADALUPE COUNTIES
CSJ6413-35-001
Proj IDRMC - 641335001
Work TypePICNIC AREA MAINTENANCE
 
0.010287298.00291623.0099.9
Work Order10-13-22
Work Began11-01-22
Work Completed
Time Computed11-01-22
Contract Working Days730
Addl Days Granted182
Working Days Charged731
Percent Time Used80
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6413-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08221501
Totals287298.009246.00291623.0099.9

CountyKENDALL
HighwayIH0010
From1375 N MAIN
To1375 N MAIN
CSJ6424-78-001
Proj IDSUP - 642478001
Work TypeJANITORIAL MAINTENANCE
 
0.01035349.7230605.0586.5
Work Order10-02-22
Work Began10-08-22
Work Completed
Time Computed10-08-22
Contract Working Days730
Addl Days Granted0
Working Days Charged755
Percent Time Used103
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6424-78-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #10221530
Totals35349.721298.1730605.0586.5

CountyBEXAR
HighwayIH0410
From3500 NW LOOP 410
To3500 NW LOOP 410
CSJ6424-96-001
Proj IDSUP - 642496001
Work TypeJANITORIAL MAINTENANCE
 
0.01074943.8436746.8849.0
Work Order09-25-22
Work Began10-01-22
Work Completed
Time Computed10-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged702
Percent Time Used96
Contractor(s)
WORKQUEST
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6424-96-001
ENDEAVORS UNLIMITED, INC. (0.00)
Contract #10221531
Totals74943.841531.1236746.8849.0

CountyATASCOSA
HighwayIH0037
FromIH0035 NB
ToSM MAINLANES
CSJ6425-20-001
Proj IDSUP - 642520001
Work TypeSTATE USE CONTRACT
 
0.01056653.8053461.8094.3
Work Order10-31-22
Work Began11-01-22
Work Completed
Time Computed11-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
SAN ANTONIO STATE SUPPORTED LIVING CENTER
SAN ANTONIO STATE SUPPORTED LIVING CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6425-20-001
SAN ANTONIO STATE SUPPORTED LIVING CENTER (0.00)
Contract #10221532
Totals56653.802436.0053461.8094.3

CountyBEXAR
HighwayIH0410
From9320 SE LOOP 410
To9320 SE LOOP 410
CSJ6426-36-001
Proj IDSUP - 642636001
Work TypeJANITORIAL MAINTENANCE
 
0.010165245.2083613.0050.5
Work Order10-31-22
Work Began11-01-22
Work Completed
Time Computed11-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
WORKQUEST
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6426-36-001
ENDEAVORS UNLIMITED, INC. (0.00)
Contract #10221533
Totals165245.202922.0083613.0050.5

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS
ToIN THE SAN ANTONIO DISTRICT
CSJ6427-41-001
Proj IDRMC - 642741001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.010259900.00269711.0099.9
Work Order04-04-23
Work Began04-10-23
Work Completed
Time Computed04-10-23
Contract Working Days365
Addl Days Granted365
Working Days Charged557
Percent Time Used76
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6427-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01231502
Totals259900.007880.00269711.0099.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN EAST AND WEST BEXAR
ToMAINTENANCE SECTIONS
CSJ6428-50-001
Proj IDMMC - 642850001
Work TypeHOT-MIX COLD-LAID
 
0.01065700.0020283.4230.8
Work Order01-10-23
Work Began01-26-23
Work Completed
Time Computed01-17-23
Contract Working Days365
Addl Days Granted366
Working Days Charged654
Percent Time Used89
Contractor(s)
BRAUNTEX MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6428-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221515
Totals65700.000.0020283.4230.8

CountyBANDERA
HighwaySH0016
FromVARIOUS LOCATIONS IN BANDERA
ToMAINTENANCE SECTION
CSJ6428-54-001
Proj IDMMC - 642854001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010271992.001130996.1799.9
Work Order01-09-23
Work Began02-15-23
Work Completed
Time Computed01-23-23
Contract Working Days365
Addl Days Granted365
Working Days Charged654
Percent Time Used89
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6428-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221516
Totals271992.000.001130996.1799.9

CountyMCMULLEN
HighwaySH0072
FromSH0016
ToSH0072
CSJ6440-24-001
Proj IDSUP - 644024001
Work TypeJANITORIAL MAINTENANCE
 
0.01028304.3612518.2244.2
Work Order04-09-23
Work Began05-23-23
Work Completed
Time Computed04-23-23
Contract Working Days730
Addl Days Granted0
Working Days Charged566
Percent Time Used77
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-24-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #03231530
Totals28304.361441.2412518.2244.2

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6445-70-001
Proj IDRMC - 644570001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.010332180.00340776.0699.9
Work Order00-00-00
Work Began09-15-23
Work Completed
Time Computed09-22-23
Contract Working Days180
Addl Days Granted550
Working Days Charged413
Percent Time Used56
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07231504
Totals332180.000.00340776.0699.9

page 1 | page 2 | page 3