Monthly State Let Construction Report For San Angelo District As Of Jan 10, 2023 Page 1 Of 2

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyRUNNELS
HighwayUS 83
FromTAYLOR COUNTY LINE
To6.9 MILES S OF TAYLOR COUNTY LINE
CSJ0034-03-019
Proj IDNH 2020(944)
Work TypeSUPER-2 HIGHWAY
 
17.32124461409.1614076991.1257.5
CountyRUNNELS
HighwayUS 83
From15.4 MI S OF TAYLOR CO LINE
ToUS 67
CSJ0034-05-040
Proj IDSTP 2020(945)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.83935702.281671.004.6
Work Order12-15-20
Work Began04-12-21
Work Completed
Time Computed03-16-21
Contract Working Days578
Addl Days Granted2
Working Days Charged215
Percent Time Used37
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-03-019
A BROTHERS MILLING, LLC (0.29)
CONTRACTORS SERVICE COMPANY (0.66)
DOUBLE A CONTRACTING, L.P. (0.26)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36)
MAKIN" IT MOVE TRANSPORT,LLC (1.24)
D. I. J. CONSTRUCTION, INC. (1.90)
STRUCTURAL INTEGRITY GROUP LLC (0.12)
SOUTHEAST HIGHWAY GUARDRAIL & ATTENUATORS, LLC (1.44)
MARCOM"S MOWING SERVICE, LLC (0.84)
FARR FOUNDATION, INC. (1.15)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.97)
BARRICADES UNLIMITED (0.67)
CONTRACTORS SERVICE, LTD. (0.66)
BEAVER CONTRACTORS, LLC (8.97)
Contract #11203201
Totals24497111.441977115.9914078662.1257.4

CountyRUNNELS ETC
HighwayFM 2887 ETC
FromUS 83
ToSH 158
CSJ0034-06-014
Proj IDSTP 2022(701)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
102.3864777670.45611124.9512.7
Work Order08-02-22
Work Began11-07-22
Work Completed
Time Computed10-31-22
Contract Working Days666
Addl Days Granted0
Working Days Charged27
Percent Time Used4
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-06-014
DIIBS SPECIALISTS, LLC (34.03)
Contract #06223618
Totals4777670.45264314.25611124.9512.7

CountyCONCHO ETC
HighwayUS 83 ETC
From11.429 MI S OF RUNNELS COUNTY LINE
ToUS 87 IN EDEN
CSJ0035-03-054
Proj IDF 2023(233)
Work TypeSEAL COAT
 
16983573.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0035-03-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223206
Totals16983573.320.000.000.0

CountyMENARD
HighwayUS 83
FromAT SAN SABA RIVER
To.
CSJ0035-05-061
Proj IDBR 2021(816)
Work TypeBRIDGE MAINTENANCE
 
1744176.691440899.0587.2
CountyCOKE
HighwaySH 70
FromAT OAK CREEK RESERVOIR
To.
CSJ0264-04-055
Proj IDBR 2021(816)
Work TypeBRIDGE MAINTENANCE
 
0.001401938.00385561.4095.9
Work Order09-29-21
Work Began11-16-21
Work Completed
Time Computed10-29-21
Contract Working Days108
Addl Days Granted40
Working Days Charged242
Percent Time Used163
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0035-05-061
DIIBS SPECIALISTS, LLC (1.36)
FLASHER EQUIPMENT COMPANY (1.57)
S & S BRIDGE PAINTING, INC. (35.28)
Contract #08213245
Totals2146114.696208.201826460.4588.8

CountySTERLING
HighwayUS 87
From16.488 MI S OF GLASSCOCK CO LINE
ToSH 163 SOUTH
CSJ0069-03-060
Proj IDF 2021(714)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
341859.05756807.1499.9
CountySTERLING
HighwayUS 87
FromSH 163 SOUTH
ToCOKE CO LINE
CSJ0069-04-044
Proj IDF 2021(714)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1612307.851483964.4392.0
CountyCOKE
HighwayUS 87
FromSTERLING COUNTY LINE
ToTOM GREEN COUNTY LINE
CSJ0069-05-030
Proj IDF 2021(714)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
659341.65372696.6356.5
CountyTOM GREEN
HighwaySL 306
FromUS 87
ToUS 67
CSJ0264-07-034
Proj IDF 2021(714)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
881190.35658419.1274.7
Work Order08-25-21
Work Began02-08-22
Work Completed
Time Computed11-23-21
Contract Working Days178
Addl Days Granted0
Working Days Charged168
Percent Time Used94
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0069-03-060
CONTRACTORS SERVICE, LTD. (0.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.50)
Contract #07213222
Totals3494698.90484214.933271887.3293.6

CountyTOM GREEN ETC
HighwayUS 87 ETC
FromBEN FICKLIN ROAD
ToEND OF FRONTAGE ROADS
CSJ0070-02-097
Proj IDF 2022(238)
Work TypeSEAL COAT
 
0.00114798190.6414705348.3499.4
Work Order01-12-22
Work Began07-26-22
Work Completed
Time Computed06-08-22
Contract Working Days72
Addl Days Granted0
Working Days Charged86
Percent Time Used119
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0070-02-097
BARRICADES PLUS, LLC (1.04)
VIZCAINO, L.P. (5.12)
Contract #12213007
Totals14798190.64141778.7514705348.3499.4

CountyREAGAN
HighwayUS 67
FromSH 137
ToUPTON COUNTY LINE
CSJ0076-08-027
Proj IDSTP 2020(652)
Work TypeSUPER-2 HIGHWAY
 
18.51623698271.4023692359.3699.9
Work Order04-21-20
Work Began08-19-20
Work Completed
Time Computed07-20-20
Contract Working Days469
Addl Days Granted11
Working Days Charged457
Percent Time Used95
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0076-08-027
BARRICADES UNLIMITED (3.06)
H J HENKE, LLC (0.24)
RONALD R. WAGNER & CO., LP (3.55)
DELGADO"S CONTRACTORS, LLC (4.11)
DK CONTRACTING, LLC (0.66)
DOUBLE A CONTRACTING, L.P. (0.44)
RPV CONSTRUCTION, LLC (0.17)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.61)
CONTRACTORS SERVICE COMPANY (0.56)
A BROTHERS MILLING, LLC (0.17)
D & E LOGISTICS, LLC (0.33)
D. I. J. CONSTRUCTION, INC. (0.20)
TITAN MILLING INC. (0.05)
CONTRACTORS SERVICE, LTD. (0.56)
PERFORMANCE EQUIPMENT SERVICE (0.09)
TRP CONSTRUCTION GROUP, LLC (0.10)
Contract #03203002
Totals23698271.40270081.8023692359.3699.9

CountyTOM GREEN
HighwayUS 67
From@ US 87
To.
CSJ0077-06-101
Proj IDSTP 2020(905)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.2001130457.591025472.4999.9
Work Order08-26-20
Work Began01-07-21
Work Completed
Time Computed11-24-20
Contract Working Days127
Addl Days Granted0
Working Days Charged298
Percent Time Used234
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-101
LIGHT IT UP ELECTRIC (34.69)
FLASHER EQUIPMENT COMPANY (3.28)
FIBERTEL, LLC (0.00)
TRIPLE H FIELD SERVICES, LLC (0.00)
Contract #06203025
Totals1130457.590.001025472.4999.9

CountyTOM GREEN ETC
HighwayBU 67-H ETC
FromUS 87
ToSL 306
CSJ0077-09-010
Proj IDSTP 2022(508)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
46.1471746965.981403345.1580.3
Work Order06-16-22
Work Began08-15-20
Work Completed
Time Computed08-15-22
Contract Working Days282
Addl Days Granted0
Working Days Charged86
Percent Time Used30
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0077-09-010
CONTRACTORS SERVICE, LTD. (3.03)
SAFETY COP, LLC (6.01)
Contract #05223007
Totals1746965.98123943.301403345.1580.3

CountyKIMBLE ETC
HighwayUS 290 ETC
FromIH 10
ToGILLESPIE CO LINE
CSJ0112-01-019
Proj IDSTP 2020(906)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
117.9784234053.393674682.3186.7
Work Order07-27-20
Work Began12-01-20
Work Completed
Time Computed10-26-20
Contract Working Days235
Addl Days Granted277
Working Days Charged468
Percent Time Used91
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0112-01-019
DIIBS SPECIALISTS, LLC (24.78)
Contract #06203208
Totals4234053.39113976.153674682.3186.7

CountyCROCKETT
HighwayIH 10
From15.9 MI E OF PECOS CL
To29.0 MI E OF PECOS CL
CSJ0140-10-034
Proj IDSTP 2022(702)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1835737.711129541.6161.5
CountyCROCKETT
HighwayIH 10
From38 MI E OF PECOS CL
ToSUTTON CL
CSJ0141-01-057
Proj IDSTP 2022(702)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
14.964488369.080.000.0
CountySUTTON
HighwayIH 10
FromCROCKETT CL
To10.179 MI E OF CROCKETT CL
CSJ0141-02-034
Proj IDSTP 2022(702)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2959644.92537120.1618.1
Work Order08-02-22
Work Began10-05-22
Work Completed
Time Computed10-03-22
Contract Working Days455
Addl Days Granted0
Working Days Charged62
Percent Time Used13
Contractor(s)
VECTOR UTILITIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0140-10-034
JE CASEY, LLC (6.01)
Contract #06223413
Totals5283751.71243869.661666661.7731.5

CountyCROCKETT ETC
HighwayIH 10
From8.619 MI E OF PECOS CO LINE.
To15.865 MI E OF PECOS CO LINE.
CSJ0140-13-021
Proj IDF 2021(715)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7780966.90922689.8611.8
Work Order08-25-21
Work Began01-05-22
Work Completed
Time Computed10-24-21
Contract Working Days400
Addl Days Granted0
Working Days Charged205
Percent Time Used51
Contractor(s)
VECTOR UTILITIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0140-13-021
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.05)
SCR CIVIL CONSTRUCTION, LLC (12.41)
Contract #07213009
Totals7780966.902356.72922689.8611.8

CountyCROCKETT
HighwayIH 10
FromPECOS COUNTY LINE
ToMILE MARKER 337
CSJ0140-13-025
Proj IDSTP 2022(878)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1714801.500.000.0
Work Order09-20-22
Work Began01-03-23
Work Completed
Time Computed11-21-22
Contract Working Days147
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0140-13-025
J. H. ODEN CONTRACTING COMPANY (4.04)
FC TRAFFIC CONTROL, INC. (1.19)
Contract #08223237
Totals1714801.500.000.000.0

CountySUTTON
HighwayIH 10
FromCROCKETT COUNTY LINE
To10.2 MI E OF CROCKETT COUNTY LINE
CSJ0141-02-033
Proj IDC 141-2-33
Work TypeOVERLAY
 
21298153.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-22
Work Began00-00-00
Work Completed
Time Computed03-14-23
Contract Working Days221
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0141-02-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11223206
Totals21298153.660.000.000.0

CountySUTTON
HighwayIH 10
From10.2 MI E OF CROCKETT COUNTY LINE
To19.9 MI E OF CROCKETT COUNTY LINE
CSJ0141-03-062
Proj IDC 141-3-62
Work TypeOVERLAY
 
9.68711863753.930.000.0
Work Order07-11-22
Work Began00-00-00
Work Completed
Time Computed08-10-22
Contract Working Days130
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0141-03-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06223006
Totals11863753.930.000.000.0

CountyKIMBLE
HighwayIH 10
FromSUTTON COUNTY LINE
To9.86 MI E OF SUTTON COUNTY LINE
CSJ0141-08-050
Proj IDF 2023(137)
Work TypeOVERLAY
 
9718660.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-22
Work Began00-00-00
Work Completed
Time Computed01-20-23
Contract Working Days154
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0141-08-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11223007
Totals9718660.000.000.000.0

CountyRUNNELS
HighwayUS 67
FromAT WILLOW CREEK
To.
CSJ0158-01-081
Proj IDBR 2022(652)
Work TypeBRIDGE REPLACEMENT
 
5693419.751897308.4433.3
Work Order07-11-22
Work Began09-19-22
Work Completed
Time Computed09-19-22
Contract Working Days379
Addl Days Granted0
Working Days Charged51
Percent Time Used13
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0158-01-081
BARRICADES UNLIMITED (2.21)
DK CONTRACTING, LLC (0.19)
HJC FARMS, INC. (3.13)
HODGES AND SON CONSTRUCTION COMPANY, INC. (4.94)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.70)
PRATER DIRT WORK LLC (23.09)
PRIMATE CONSTRUCTION, LP (0.18)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.54)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
TORO BRAVO CONSTRUCTION, LLC (0.20)
TRP CONSTRUCTION GROUP, LLC (1.40)
Contract #06223216
Totals5693419.75456640.171897308.4433.3

CountySUTTON
HighwayUS 277
FromDRY DEVILS RIVER
To12.275 MI NORTH OF EDWARDS CO LINE
CSJ0160-01-036
Proj IDF 2021(598)
Work TypeSUPER-2 HIGHWAY
 
8.4137931238.926673247.0985.6
CountySUTTON
HighwayUS 277
FromSL 467
To12.3 MI N OF EDWARDS CO LINE
CSJ0160-01-037
Proj IDSTP 2021(599)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.003127451.6068644.1853.8
CountySUTTON
HighwayUS 277
FromST ANNS ST
To12.5 MI N OF EDWARDS CO LINE
CSJ0160-01-039
Proj IDSTP 2021(599)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.118396788.00386918.0097.5
Work Order07-20-21
Work Began09-07-21
Work Completed
Time Computed09-07-21
Contract Working Days178
Addl Days Granted40
Working Days Charged322
Percent Time Used147
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0160-01-036
DK CONTRACTING, LLC (0.25)
DEPENDABLE FENCE (6.02)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.53)
BEAVER CONTRACTORS, LLC (6.13)
MPB, INC. (0.40)
D. I. J. CONSTRUCTION, INC. (1.46)
DOUBLE A CONTRACTING, L.P. (2.33)
Contract #06213210
Totals8455478.526550.007128809.2785.6

CountySUTTON
HighwayUS 277
From12.275 MI NORTH OF EDWARDS CO LINE
ToEDWARDS COUNTY LINE
CSJ0160-02-025
Proj IDNH 2020(946)
Work TypeSUPER-2 HIGHWAY
 
12.27510416011.0310584864.8599.9
CountySUTTON
HighwayUS 277
From12.3 MI N OF EDWARDS CO LINE
ToEDWARDS COUNTY LINE
CSJ0160-02-026
Proj IDSTP 2020(947)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
12.275106083.0068711.0864.7
CountyEDWARDS
HighwayUS 277
FromSUTTON COUNTY LINE
ToVAL VERDE COUNTY LINE
CSJ0160-03-024
Proj IDNH 2020(946)
Work TypeSUPER-2 HIGHWAY
 
13.5708016674.036418592.4980.0
CountyEDWARDS
HighwayUS 277
FromSUTTON CL
ToVAL VERDE CL
CSJ0160-03-025
Proj IDSTP 2020(947)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
13.137812728.771596285.4599.9
Work Order03-18-21
Work Began04-05-21
Work Completed
Time Computed04-05-21
Contract Working Days342
Addl Days Granted0
Working Days Charged434
Percent Time Used126
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0160-02-025
BEAVER CONTRACTORS, LLC (6.98)
J. H. ODEN CONTRACTING COMPANY (0.80)
DK CONTRACTING, LLC (0.41)
DOUBLE A CONTRACTING, L.P. (0.20)
MPB, INC. (0.10)
D. I. J. CONSTRUCTION, INC. (1.53)
ERFURT BLASTING COMPANY, INC. (0.58)
TEXAS GUARDRAIL CONTRACTORS LLC (3.48)
MORALES TRUCKING LLC (0.23)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.14)
LONE STAR PAVING COMPANY (0.65)
PIKES PEAK ENERGY SERVICES, LLC (0.23)
RONALD R. WAGNER & CO., LP (2.34)
RPV CONSTRUCTION, LLC (0.00)
Contract #02213001
Totals19351496.83346958.7818668453.8797.0

CountyTOM GREEN
HighwayUS 277
FromCOKE COUNTY LINE
ToUS 67
CSJ0264-06-043
Proj IDF 2022(457)
Work TypeSUPER-2 HIGHWAY
 
13.71617420245.535495560.5331.5
Work Order06-22-22
Work Began08-01-22
Work Completed
Time Computed07-28-22
Contract Working Days387
Addl Days Granted0
Working Days Charged94
Percent Time Used24
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0264-06-043
BEAVER CONTRACTORS, LLC (6.02)
DK CONTRACTING, LLC (0.67)
PRIMATE CONSTRUCTION, LP (0.19)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.17)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.74)
BRANNAN PAVING COMPANY, INC. (0.00)
CONTRACTORS SERVICE, LTD. (0.38)
DEPENDABLE FENCE (1.87)
D. I. J. CONSTRUCTION, INC. (1.25)
K. L. DURHAM CONSTRUCTION, L.L.C. (1.12)
PINNACLE GRINDING AND GROOVING LLC (0.17)
SCR CIVIL CONSTRUCTION, LLC (0.76)
TWIN MOUNTAIN SUPPLY CO. (0.38)
BRANNAN PAVING CO., LTD. (3.21)
Contract #04223003
Totals17420245.532170417.635495560.5331.5

page 1 | page 2