Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | RUNNELS |
Highway | US 83 |
From | TAYLOR COUNTY LINE |
To | 6.9 MILES S OF TAYLOR COUNTY LINE |
CSJ | 0034-03-019 |
Proj ID | NH 2020(944) |
Work Type | SUPER-2 HIGHWAY |
|
| 17.321 | 24461409.16 | | 14076991.12 | 57.5 |
County | RUNNELS |
Highway | US 83 |
From | 15.4 MI S OF TAYLOR CO LINE |
To | US 67 |
CSJ | 0034-05-040 |
Proj ID | STP 2020(945)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 8.839 | 35702.28 | | 1671.00 | 4.6 |
Work Order | 12-15-20 |
Work Began | 04-12-21 |
Work Completed | |
Time Computed | 03-16-21 |
Contract Working Days | 578 |
Addl Days Granted | 2 |
Working Days Charged | 215 |
Percent Time Used | 37 |
Contractor(s) |
J. H. STRAIN & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0034-03-019 A BROTHERS MILLING, LLC (0.29) CONTRACTORS SERVICE COMPANY (0.66) DOUBLE A CONTRACTING, L.P. (0.26) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36) MAKIN" IT MOVE TRANSPORT,LLC (1.24) D. I. J. CONSTRUCTION, INC. (1.90) STRUCTURAL INTEGRITY GROUP LLC (0.12) SOUTHEAST HIGHWAY GUARDRAIL & ATTENUATORS, LLC (1.44) MARCOM"S MOWING SERVICE, LLC (0.84) FARR FOUNDATION, INC. (1.15) WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.97) BARRICADES UNLIMITED (0.67) CONTRACTORS SERVICE, LTD. (0.66) BEAVER CONTRACTORS, LLC (8.97)
|
Contract # | 11203201 |
| Totals | 24497111.44 | 1977115.99 | 14078662.12 | 57.4 |
|
County | RUNNELS ETC |
Highway | FM 2887 ETC |
From | US 83 |
To | SH 158 |
CSJ | 0034-06-014 |
Proj ID | STP 2022(701)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 102.386 | 4777670.45 | | 611124.95 | 12.7 |
Work Order | 08-02-22 |
Work Began | 11-07-22 |
Work Completed | |
Time Computed | 10-31-22 |
Contract Working Days | 666 |
Addl Days Granted | 0 |
Working Days Charged | 27 |
Percent Time Used | 4 |
Contractor(s) |
RELMCO, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0034-06-014 DIIBS SPECIALISTS, LLC (34.03)
|
Contract # | 06223618 |
| Totals | 4777670.45 | 264314.25 | 611124.95 | 12.7 |
|
County | CONCHO ETC |
Highway | US 83 ETC |
From | 11.429 MI S OF RUNNELS COUNTY LINE |
To | US 87 IN EDEN |
CSJ | 0035-03-054 |
Proj ID | F 2023(233) |
Work Type | SEAL COAT |
|
| | 16983573.32 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 72 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
RONALD R. WAGNER & CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0035-03-054 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12223206 |
| Totals | 16983573.32 | 0.00 | 0.00 | 0.0 |
|
County | MENARD |
Highway | US 83 |
From | AT SAN SABA RIVER |
To | . |
CSJ | 0035-05-061 |
Proj ID | BR 2021(816) |
Work Type | BRIDGE MAINTENANCE |
|
| | 1744176.69 | | 1440899.05 | 87.2 |
County | COKE |
Highway | SH 70 |
From | AT OAK CREEK RESERVOIR |
To | . |
CSJ | 0264-04-055 |
Proj ID | BR 2021(816) |
Work Type | BRIDGE MAINTENANCE |
|
| 0.001 | 401938.00 | | 385561.40 | 95.9 |
Work Order | 09-29-21 |
Work Began | 11-16-21 |
Work Completed | |
Time Computed | 10-29-21 |
Contract Working Days | 108 |
Addl Days Granted | 40 |
Working Days Charged | 242 |
Percent Time Used | 163 |
Contractor(s) |
RELMCO, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0035-05-061 DIIBS SPECIALISTS, LLC (1.36) FLASHER EQUIPMENT COMPANY (1.57) S & S BRIDGE PAINTING, INC. (35.28)
|
Contract # | 08213245 |
| Totals | 2146114.69 | 6208.20 | 1826460.45 | 88.8 |
|
County | STERLING |
Highway | US 87 |
From | 16.488 MI S OF GLASSCOCK CO LINE |
To | SH 163 SOUTH |
CSJ | 0069-03-060 |
Proj ID | F 2021(714) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 341859.05 | | 756807.14 | 99.9 |
County | STERLING |
Highway | US 87 |
From | SH 163 SOUTH |
To | COKE CO LINE |
CSJ | 0069-04-044 |
Proj ID | F 2021(714) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1612307.85 | | 1483964.43 | 92.0 |
County | COKE |
Highway | US 87 |
From | STERLING COUNTY LINE |
To | TOM GREEN COUNTY LINE |
CSJ | 0069-05-030 |
Proj ID | F 2021(714) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 659341.65 | | 372696.63 | 56.5 |
County | TOM GREEN |
Highway | SL 306 |
From | US 87 |
To | US 67 |
CSJ | 0264-07-034 |
Proj ID | F 2021(714) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 881190.35 | | 658419.12 | 74.7 |
Work Order | 08-25-21 |
Work Began | 02-08-22 |
Work Completed | |
Time Computed | 11-23-21 |
Contract Working Days | 178 |
Addl Days Granted | 0 |
Working Days Charged | 168 |
Percent Time Used | 94 |
Contractor(s) |
SCR CIVIL CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0069-03-060 CONTRACTORS SERVICE, LTD. (0.60) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.50)
|
Contract # | 07213222 |
| Totals | 3494698.90 | 484214.93 | 3271887.32 | 93.6 |
|
County | TOM GREEN ETC |
Highway | US 87 ETC |
From | BEN FICKLIN ROAD |
To | END OF FRONTAGE ROADS |
CSJ | 0070-02-097 |
Proj ID | F 2022(238) |
Work Type | SEAL COAT |
|
| 0.001 | 14798190.64 | | 14705348.34 | 99.4 |
Work Order | 01-12-22 |
Work Began | 07-26-22 |
Work Completed | |
Time Computed | 06-08-22 |
Contract Working Days | 72 |
Addl Days Granted | 0 |
Working Days Charged | 86 |
Percent Time Used | 119 |
Contractor(s) |
RONALD R. WAGNER & CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0070-02-097 BARRICADES PLUS, LLC (1.04) VIZCAINO, L.P. (5.12)
|
Contract # | 12213007 |
| Totals | 14798190.64 | 141778.75 | 14705348.34 | 99.4 |
|
County | REAGAN |
Highway | US 67 |
From | SH 137 |
To | UPTON COUNTY LINE |
CSJ | 0076-08-027 |
Proj ID | STP 2020(652) |
Work Type | SUPER-2 HIGHWAY |
|
| 18.516 | 23698271.40 | | 23692359.36 | 99.9 |
Work Order | 04-21-20 |
Work Began | 08-19-20 |
Work Completed | |
Time Computed | 07-20-20 |
Contract Working Days | 469 |
Addl Days Granted | 11 |
Working Days Charged | 457 |
Percent Time Used | 95 |
Contractor(s) |
REECE ALBERT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0076-08-027 BARRICADES UNLIMITED (3.06) H J HENKE, LLC (0.24) RONALD R. WAGNER & CO., LP (3.55) DELGADO"S CONTRACTORS, LLC (4.11) DK CONTRACTING, LLC (0.66) DOUBLE A CONTRACTING, L.P. (0.44) RPV CONSTRUCTION, LLC (0.17) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.61) CONTRACTORS SERVICE COMPANY (0.56) A BROTHERS MILLING, LLC (0.17) D & E LOGISTICS, LLC (0.33) D. I. J. CONSTRUCTION, INC. (0.20) TITAN MILLING INC. (0.05) CONTRACTORS SERVICE, LTD. (0.56) PERFORMANCE EQUIPMENT SERVICE (0.09) TRP CONSTRUCTION GROUP, LLC (0.10)
|
Contract # | 03203002 |
| Totals | 23698271.40 | 270081.80 | 23692359.36 | 99.9 |
|
County | TOM GREEN |
Highway | US 67 |
From | @ US 87 |
To | . |
CSJ | 0077-06-101 |
Proj ID | STP 2020(905)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 0.200 | 1130457.59 | | 1025472.49 | 99.9 |
Work Order | 08-26-20 |
Work Began | 01-07-21 |
Work Completed | |
Time Computed | 11-24-20 |
Contract Working Days | 127 |
Addl Days Granted | 0 |
Working Days Charged | 298 |
Percent Time Used | 234 |
Contractor(s) |
RELMCO, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-101 LIGHT IT UP ELECTRIC (34.69) FLASHER EQUIPMENT COMPANY (3.28) FIBERTEL, LLC (0.00) TRIPLE H FIELD SERVICES, LLC (0.00)
|
Contract # | 06203025 |
| Totals | 1130457.59 | 0.00 | 1025472.49 | 99.9 |
|
County | TOM GREEN ETC |
Highway | BU 67-H ETC |
From | US 87 |
To | SL 306 |
CSJ | 0077-09-010 |
Proj ID | STP 2022(508)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 46.147 | 1746965.98 | | 1403345.15 | 80.3 |
Work Order | 06-16-22 |
Work Began | 08-15-20 |
Work Completed | |
Time Computed | 08-15-22 |
Contract Working Days | 282 |
Addl Days Granted | 0 |
Working Days Charged | 86 |
Percent Time Used | 30 |
Contractor(s) |
3LW CIVIL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0077-09-010 CONTRACTORS SERVICE, LTD. (3.03) SAFETY COP, LLC (6.01)
|
Contract # | 05223007 |
| Totals | 1746965.98 | 123943.30 | 1403345.15 | 80.3 |
|
County | KIMBLE ETC |
Highway | US 290 ETC |
From | IH 10 |
To | GILLESPIE CO LINE |
CSJ | 0112-01-019 |
Proj ID | STP 2020(906)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 117.978 | 4234053.39 | | 3674682.31 | 86.7 |
Work Order | 07-27-20 |
Work Began | 12-01-20 |
Work Completed | |
Time Computed | 10-26-20 |
Contract Working Days | 235 |
Addl Days Granted | 277 |
Working Days Charged | 468 |
Percent Time Used | 91 |
Contractor(s) |
RELMCO, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0112-01-019 DIIBS SPECIALISTS, LLC (24.78)
|
Contract # | 06203208 |
| Totals | 4234053.39 | 113976.15 | 3674682.31 | 86.7 |
|
County | CROCKETT |
Highway | IH 10 |
From | 15.9 MI E OF PECOS CL |
To | 29.0 MI E OF PECOS CL |
CSJ | 0140-10-034 |
Proj ID | STP 2022(702)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1835737.71 | | 1129541.61 | 61.5 |
County | CROCKETT |
Highway | IH 10 |
From | 38 MI E OF PECOS CL |
To | SUTTON CL |
CSJ | 0141-01-057 |
Proj ID | STP 2022(702)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 14.964 | 488369.08 | | 0.00 | 0.0 |
County | SUTTON |
Highway | IH 10 |
From | CROCKETT CL |
To | 10.179 MI E OF CROCKETT CL |
CSJ | 0141-02-034 |
Proj ID | STP 2022(702)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 2959644.92 | | 537120.16 | 18.1 |
Work Order | 08-02-22 |
Work Began | 10-05-22 |
Work Completed | |
Time Computed | 10-03-22 |
Contract Working Days | 455 |
Addl Days Granted | 0 |
Working Days Charged | 62 |
Percent Time Used | 13 |
Contractor(s) |
VECTOR UTILITIES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0140-10-034 JE CASEY, LLC (6.01)
|
Contract # | 06223413 |
| Totals | 5283751.71 | 243869.66 | 1666661.77 | 31.5 |
|
County | CROCKETT ETC |
Highway | IH 10 |
From | 8.619 MI E OF PECOS CO LINE. |
To | 15.865 MI E OF PECOS CO LINE. |
CSJ | 0140-13-021 |
Proj ID | F 2021(715) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 7780966.90 | | 922689.86 | 11.8 |
Work Order | 08-25-21 |
Work Began | 01-05-22 |
Work Completed | |
Time Computed | 10-24-21 |
Contract Working Days | 400 |
Addl Days Granted | 0 |
Working Days Charged | 205 |
Percent Time Used | 51 |
Contractor(s) |
VECTOR UTILITIES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0140-13-021 TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.05) SCR CIVIL CONSTRUCTION, LLC (12.41)
|
Contract # | 07213009 |
| Totals | 7780966.90 | 2356.72 | 922689.86 | 11.8 |
|
County | CROCKETT |
Highway | IH 10 |
From | PECOS COUNTY LINE |
To | MILE MARKER 337 |
CSJ | 0140-13-025 |
Proj ID | STP 2022(878)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1714801.50 | | 0.00 | 0.0 |
Work Order | 09-20-22 |
Work Began | 01-03-23 |
Work Completed | |
Time Computed | 11-21-22 |
Contract Working Days | 147 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
SCR CIVIL CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0140-13-025 J. H. ODEN CONTRACTING COMPANY (4.04) FC TRAFFIC CONTROL, INC. (1.19)
|
Contract # | 08223237 |
| Totals | 1714801.50 | 0.00 | 0.00 | 0.0 |
|
County | SUTTON |
Highway | IH 10 |
From | CROCKETT COUNTY LINE |
To | 10.2 MI E OF CROCKETT COUNTY LINE |
CSJ | 0141-02-033 |
Proj ID | C 141-2-33 |
Work Type | OVERLAY |
|
| | 21298153.66 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 12-14-22 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 03-14-23 |
Contract Working Days | 221 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
DELHUR INDUSTRIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0141-02-033 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11223206 |
| Totals | 21298153.66 | 0.00 | 0.00 | 0.0 |
|
County | SUTTON |
Highway | IH 10 |
From | 10.2 MI E OF CROCKETT COUNTY LINE |
To | 19.9 MI E OF CROCKETT COUNTY LINE |
CSJ | 0141-03-062 |
Proj ID | C 141-3-62 |
Work Type | OVERLAY |
|
| 9.687 | 11863753.93 | | 0.00 | 0.0 |
Work Order | 07-11-22 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 08-10-22 |
Contract Working Days | 130 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
DELHUR INDUSTRIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0141-03-062 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06223006 |
| Totals | 11863753.93 | 0.00 | 0.00 | 0.0 |
|
County | KIMBLE |
Highway | IH 10 |
From | SUTTON COUNTY LINE |
To | 9.86 MI E OF SUTTON COUNTY LINE |
CSJ | 0141-08-050 |
Proj ID | F 2023(137) |
Work Type | OVERLAY |
|
| | 9718660.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 12-21-22 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 01-20-23 |
Contract Working Days | 154 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ALLEN KELLER COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0141-08-050 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11223007 |
| Totals | 9718660.00 | 0.00 | 0.00 | 0.0 |
|
County | RUNNELS |
Highway | US 67 |
From | AT WILLOW CREEK |
To | . |
CSJ | 0158-01-081 |
Proj ID | BR 2022(652) |
Work Type | BRIDGE REPLACEMENT |
|
| | 5693419.75 | | 1897308.44 | 33.3 |
Work Order | 07-11-22 |
Work Began | 09-19-22 |
Work Completed | |
Time Computed | 09-19-22 |
Contract Working Days | 379 |
Addl Days Granted | 0 |
Working Days Charged | 51 |
Percent Time Used | 13 |
Contractor(s) |
COPPELL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0158-01-081 BARRICADES UNLIMITED (2.21) DK CONTRACTING, LLC (0.19) HJC FARMS, INC. (3.13) HODGES AND SON CONSTRUCTION COMPANY, INC. (4.94) MORRIS COUNTY CONTRACTORS, L.L.C. (1.70) PRATER DIRT WORK LLC (23.09) PRIMATE CONSTRUCTION, LP (0.18) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.54) WEST TEXAS ROCK RESOURCES, LLC (0.06) TORO BRAVO CONSTRUCTION, LLC (0.20) TRP CONSTRUCTION GROUP, LLC (1.40)
|
Contract # | 06223216 |
| Totals | 5693419.75 | 456640.17 | 1897308.44 | 33.3 |
|
County | SUTTON |
Highway | US 277 |
From | DRY DEVILS RIVER |
To | 12.275 MI NORTH OF EDWARDS CO LINE |
CSJ | 0160-01-036 |
Proj ID | F 2021(598) |
Work Type | SUPER-2 HIGHWAY |
|
| 8.413 | 7931238.92 | | 6673247.09 | 85.6 |
County | SUTTON |
Highway | US 277 |
From | SL 467 |
To | 12.3 MI N OF EDWARDS CO LINE |
CSJ | 0160-01-037 |
Proj ID | STP 2021(599)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 9.003 | 127451.60 | | 68644.18 | 53.8 |
County | SUTTON |
Highway | US 277 |
From | ST ANNS ST |
To | 12.5 MI N OF EDWARDS CO LINE |
CSJ | 0160-01-039 |
Proj ID | STP 2021(599)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 8.118 | 396788.00 | | 386918.00 | 97.5 |
Work Order | 07-20-21 |
Work Began | 09-07-21 |
Work Completed | |
Time Computed | 09-07-21 |
Contract Working Days | 178 |
Addl Days Granted | 40 |
Working Days Charged | 322 |
Percent Time Used | 147 |
Contractor(s) |
ALLEN KELLER COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0160-01-036 DK CONTRACTING, LLC (0.25) DEPENDABLE FENCE (6.02) WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.53) BEAVER CONTRACTORS, LLC (6.13) MPB, INC. (0.40) D. I. J. CONSTRUCTION, INC. (1.46) DOUBLE A CONTRACTING, L.P. (2.33)
|
Contract # | 06213210 |
| Totals | 8455478.52 | 6550.00 | 7128809.27 | 85.6 |
|
County | SUTTON |
Highway | US 277 |
From | 12.275 MI NORTH OF EDWARDS CO LINE |
To | EDWARDS COUNTY LINE |
CSJ | 0160-02-025 |
Proj ID | NH 2020(946) |
Work Type | SUPER-2 HIGHWAY |
|
| 12.275 | 10416011.03 | | 10584864.85 | 99.9 |
County | SUTTON |
Highway | US 277 |
From | 12.3 MI N OF EDWARDS CO LINE |
To | EDWARDS COUNTY LINE |
CSJ | 0160-02-026 |
Proj ID | STP 2020(947)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 12.275 | 106083.00 | | 68711.08 | 64.7 |
County | EDWARDS |
Highway | US 277 |
From | SUTTON COUNTY LINE |
To | VAL VERDE COUNTY LINE |
CSJ | 0160-03-024 |
Proj ID | NH 2020(946) |
Work Type | SUPER-2 HIGHWAY |
|
| 13.570 | 8016674.03 | | 6418592.49 | 80.0 |
County | EDWARDS |
Highway | US 277 |
From | SUTTON CL |
To | VAL VERDE CL |
CSJ | 0160-03-025 |
Proj ID | STP 2020(947)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 13.137 | 812728.77 | | 1596285.45 | 99.9 |
Work Order | 03-18-21 |
Work Began | 04-05-21 |
Work Completed | |
Time Computed | 04-05-21 |
Contract Working Days | 342 |
Addl Days Granted | 0 |
Working Days Charged | 434 |
Percent Time Used | 126 |
Contractor(s) |
ALLEN KELLER COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0160-02-025 BEAVER CONTRACTORS, LLC (6.98) J. H. ODEN CONTRACTING COMPANY (0.80) DK CONTRACTING, LLC (0.41) DOUBLE A CONTRACTING, L.P. (0.20) MPB, INC. (0.10) D. I. J. CONSTRUCTION, INC. (1.53) ERFURT BLASTING COMPANY, INC. (0.58) TEXAS GUARDRAIL CONTRACTORS LLC (3.48) MORALES TRUCKING LLC (0.23) WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.14) LONE STAR PAVING COMPANY (0.65) PIKES PEAK ENERGY SERVICES, LLC (0.23) RONALD R. WAGNER & CO., LP (2.34) RPV CONSTRUCTION, LLC (0.00)
|
Contract # | 02213001 |
| Totals | 19351496.83 | 346958.78 | 18668453.87 | 97.0 |
|
County | TOM GREEN |
Highway | US 277 |
From | COKE COUNTY LINE |
To | US 67 |
CSJ | 0264-06-043 |
Proj ID | F 2022(457) |
Work Type | SUPER-2 HIGHWAY |
|
| 13.716 | 17420245.53 | | 5495560.53 | 31.5 |
Work Order | 06-22-22 |
Work Began | 08-01-22 |
Work Completed | |
Time Computed | 07-28-22 |
Contract Working Days | 387 |
Addl Days Granted | 0 |
Working Days Charged | 94 |
Percent Time Used | 24 |
Contractor(s) |
REECE ALBERT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0264-06-043 BEAVER CONTRACTORS, LLC (6.02) DK CONTRACTING, LLC (0.67) PRIMATE CONSTRUCTION, LP (0.19) TEXAS ALTERNATIVE GRASSER INCORPORATED (0.17) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.74) BRANNAN PAVING COMPANY, INC. (0.00) CONTRACTORS SERVICE, LTD. (0.38) DEPENDABLE FENCE (1.87) D. I. J. CONSTRUCTION, INC. (1.25) K. L. DURHAM CONSTRUCTION, L.L.C. (1.12) PINNACLE GRINDING AND GROOVING LLC (0.17) SCR CIVIL CONSTRUCTION, LLC (0.76) TWIN MOUNTAIN SUPPLY CO. (0.38) BRANNAN PAVING CO., LTD. (3.21)
|
Contract # | 04223003 |
| Totals | 17420245.53 | 2170417.63 | 5495560.53 | 31.5 |
|