Monthly State Let Maintenance Report For San Angelo District As Of Nov 10, 2024 Page 1 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKIMBLE
Highway0000000
From2124 NORTH MAIN (LOOP 481), JUNCTION
To.
CSJ4704-01-167
Proj IDCBC - 470401167
Work TypeJIM TATE PROJECT MANAGER
 
0.0011209888.001003145.0082.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted53
Working Days Charged262
Percent Time Used81
Contractor(s)
KENDNEL KASPER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-167
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07144217
Totals1209888.000.001003145.0082.9

CountyTOM GREEN
Highway0000000
From4502 KNICKERBOCKER RD
ToSAN ANGELO TX
CSJ4704-01-685
Proj IDCBC - 470401685
Work TypeRENOVATION AND REPAIR
 
0.001769600.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CS ADVANTAGE USAA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-685
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164223
Totals769600.000.000.000.0

CountySUTTON
HighwayRM1312
FromIRION COUNTY
ToSUTTON COUNTY
CSJ6205-40-001
Proj IDRMC - 620540001
Work TypeINSTALL BRIDGE RAIL & GUARD RAIL END TRE
 
0.001308769.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6205-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04104022
Totals308769.000.000.000.0

CountyCROCKETT
HighwaySH0163
FromVARIOUS LOCATIONS IN CROCKETT COUNTY
ToVARIOUS LOCATIONS IN CROCKETT COUNTY
CSJ6232-09-001
Proj IDRMC - 623209001
Work TypeSTRIP MOWING OF RIGHT OF WAY CROCKETT CO
 
0.001103536.0051768.0050.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-07-12
Work Began06-01-12
Work Completed
Time Computed06-01-12
Contract Working Days44
Addl Days Granted0
Working Days Charged9
Percent Time Used20
Contractor(s)
SPARKLES TRUCKING
SUBCONTRACTOR(S) FOR CCSJ: 6232-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10114005
Totals103536.000.0051768.0050.0

CountyTOM GREEN
HighwayUS0067
FromVARIOUS LOCATIONS IN TOM GREEN URBAN
ToVARIOUS LOCATIONS IN TOM GREEN URBAN
CSJ6245-64-001
Proj IDRMC - 624564001
Work TypeRIGHT OF WAY MOWING FOR TOM GREEN URBAN
 
0.001167384.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days24
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08124031
Totals167384.880.000.000.0

CountyKIMBLE
HighwayIH0010
FromVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6289-21-001
Proj IDRMC - 628921001
Work TypeMETAL BEAM GUARDFENCE
 
0.001319646.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6289-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154210
Totals319646.000.000.000.0

CountyKIMBLE
HighwayIH0010
FromVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6343-31-001
Proj IDRMC - 634331001
Work TypeMETAL BEAM GUARDFENCE
 
0.001632830.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194019
Totals632830.000.000.000.0

CountyTOM GREEN
HighwaySH0208
FromVARIOUS LOCATIONS IN TOM GREEN COUNTY
ToVARIOUS LOCATIONS IN TOM GREEN COUNTY
CSJ6400-98-001
Proj IDRMC - 640098001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010628587.101541338.60100.0
Work Order07-12-22
Work Began07-18-22
Work Completed07-16-24
Time Computed07-18-22
Contract Working Days365
Addl Days Granted365
Working Days Charged710
Percent Time Used97
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6400-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224222
Totals628587.100.001541338.60100.0

CountySUTTON
HighwayUS0277
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6419-89-001
Proj IDRMC - 641989001
Work TypeREHABILITATION OF EXISTING ROADWAY
 
0.0101277999.280.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EMERY SAPP & SON'S INC.
SUBCONTRACTOR(S) FOR CCSJ: 6419-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08244202
Totals1277999.280.000.000.0

CountyCONCHO
HighwayUS0083
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6422-14-001
Proj IDBPM - 642214001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010643690.00504884.0083.4
Work Order02-21-23
Work Began02-27-23
Work Completed
Time Computed02-27-23
Contract Working Days180
Addl Days Granted0
Working Days Charged232
Percent Time Used128
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6422-14-001
S&S BRIDGE PAINTING (2.33)
Contract #10224218
Totals643690.000.00504884.0083.4

CountyTOM GREEN
HighwaySH0208
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN THE SAN ANGELO DIST
CSJ6437-35-001
Proj IDRMC - 643735001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010661351.451098119.7899.9
Work Order06-02-23
Work Began06-05-23
Work Completed
Time Computed06-05-23
Contract Working Days365
Addl Days Granted365
Working Days Charged475
Percent Time Used65
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6437-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234217
Totals661351.4563120.361098119.7899.9

CountyCOKE
HighwayRM2059
FromTRM 316+0.001
ToTRM 320+1.269
CSJ6439-94-001
Proj IDRMC - 643994001
Work TypeCULVERT
 
0.0101693487.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days231
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STX CIVIL
SUBCONTRACTOR(S) FOR CCSJ: 6439-94-001
BARRICADES UNLIMITED (0.00)
TRP CONSTRUCTION GROUP, LLC (0.00)
Contract #08244203
Totals1693487.250.000.000.0

CountyTOM GREEN
HighwayUS0087
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6442-22-001
Proj IDBPM - 644222001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010659949.00503924.0076.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-05-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged171
Percent Time Used95
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-22-001
TRP CONSTRUCTION GROUP, LLC (0.00)
BARRICADES UNLIMITED (0.00)
Contract #11234027
Totals659949.00113024.00503924.0076.3

CountyKIMBLE
HighwayUS0377
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN THE SAN ANGELO DIST
CSJ6442-66-001
Proj IDRMC - 644266001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010648564.00401150.1861.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-08-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged116
Percent Time Used31
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244004
Totals648564.0072737.25401150.1861.8

CountyKIMBLE
HighwayIH0010
FromPECOS COUNTY LINE
ToKERR COUNTY LINE
CSJ6446-94-001
Proj IDRMC - 644694001
Work TypeDEBRIS REMOVAL
 
0.010643568.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BARRICADE COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6446-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234024
Totals643568.200.000.000.0

CountyKIMBLE
HighwayIH0010
FromPECOS COUNTY LINE
ToKERR COUNTY LINE
CSJ6460-37-001
Proj IDRMC - 646037001
Work TypeDEBRIS REMOVAL
 
0.010491390.46299379.8560.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-06-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged266
Percent Time Used72
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234040
Totals491390.4640929.22299379.8560.9

CountyTOM GREEN
HighwaySL0306
FromUS 87
To0.65 MILES NORTH OF FM 765
CSJ6462-13-001
Proj IDRMC - 646213001
Work TypeASPHALT
 
0.0102383456.903082735.1499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-17-24
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged44
Percent Time Used55
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-13-001
D. I. J. CONSTRUCTION, INC. (0.00)
PERFORMANCE EQUIPMENT SERVICE (0.00)
CONTRACTORS SERVICE, LTD. (0.00)
Contract #04244012
Totals2383456.900.003082735.1499.9

CountyCONCHO
HighwayUS0087
FromTOM GREEN COUNTY LINE
To6.545 MILES SOUTH
CSJ6464-84-001
Proj IDRMC - 646484001
Work TypeASPHALT
 
0.0104696973.484472891.9695.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-05-24
Work Completed
Time Computed00-00-00
Contract Working Days39
Addl Days Granted0
Working Days Charged35
Percent Time Used89
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6464-84-001
K. L. DURHAM CONSTRUCTION, L.L.C. (1.92)
WEST TEXAS ROCK RESOURCES, LLC (1.09)
CONTRACTORS SERVICE, LTD. (2.30)
D. I. J. CONSTRUCTION, INC. (0.77)
SOUTHEAST GRINDING AND GROOVING LLC (0.00)
Contract #05244217
Totals4696973.4849202.384472891.9695.2

CountyTOM GREEN
HighwayUS0087
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6466-30-001
Proj IDRMC - 646630001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101282532.00304663.7723.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-22-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged99
Percent Time Used27
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6466-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05244218
Totals1282532.00115418.01304663.7723.7

CountyTOM GREEN
HighwaySH0208
FromVARIOUS LOCATIONS IN TOM GREEN COUNTY
ToVARIOUS LOCATIONS IN TOM GREEN COUNTY
CSJ6466-68-001
Proj IDRMC - 646668001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010561372.5588152.5015.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged53
Percent Time Used14
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6466-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244041
Totals561372.5535255.5088152.5015.7

page 1 | page 2