									| Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp | 
								
									
  | 
								
									
										
											| County | HILL | 
										 
											| Highway | SH0171 | 
										 
											| From | STATE MAINTAINED ROADWAYS | 
										 
											| To | HILL COUNTY | 
										 
											| CSJ | 6250-54-001 | 
										 
											| Proj ID | RMC - 625054001 | 
										 
											| Work Type | MOWING ROW & LITTER PICKUP AND DISPOSAL | 
										 
											|   | 
										 
									  | 221.740 | 209531.30 |  | 214580.60 | 99.9 | 
								
									
										
											| NO CURRENT ESTIMATE AT TIME OF THIS RUN | 
										 
											| Work Order | 06-10-13 | 
										 
											| Work Began | 06-18-13 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 06-18-13 | 
										 
											| Contract Working Days | 124 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 68 | 
										 
											| Percent Time Used | 54 | 
										 
											| Contractor(s) | 
										 
											| CEN-TEX IRRIGATION SYSTEMS, INC. | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6250-54-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 12120904 | 
										 
									  | Totals | 209531.30 | 0.00 | 214580.60 | 99.9 | 
								
									
  | 
								
									
										
											| County | CORYELL | 
										 
											| Highway | US0084 | 
										 
											| From | VARIOUS | 
										 
											| To | VARIOUS | 
										 
											| CSJ | 6307-12-001 | 
										 
											| Proj ID | SUP - 630712001 | 
										 
											| Work Type | PICNIC AREA MAINTENANCE | 
										 
											|   | 
										 
									  | 0.010 | 47770.00 |  | 39845.00 | 100.0 | 
								
									
										
											| NO CURRENT ESTIMATE AT TIME OF THIS RUN | 
										 
											| Work Order | 08-26-16 | 
										 
											| Work Began | 09-01-16 | 
										 
											| Work Completed | 08-31-17 | 
										 
											| Time Computed | 09-01-16 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 364 | 
										 
											| Percent Time Used | 99 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST GOODWILL CONTRACT SERVICES, INC. | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6307-12-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 08160942 | 
										 
									  | Totals | 47770.00 | 0.00 | 39845.00 | 100.0 | 
								
									
  | 
								
									
										
											| County | HAMILTON | 
										 
											| Highway | US0281 | 
										 
											| From | VARIOUS | 
										 
											| To | VARIOUS | 
										 
											| CSJ | 6307-13-001 | 
										 
											| Proj ID | SUP - 630713001 | 
										 
											| Work Type | PICNIC AREA MAINTENANCE | 
										 
											|   | 
										 
									  | 0.010 | 44370.00 |  | 32375.00 | 100.0 | 
								
									
										
											| NO CURRENT ESTIMATE AT TIME OF THIS RUN | 
										 
											| Work Order | 08-26-16 | 
										 
											| Work Began | 09-01-16 | 
										 
											| Work Completed | 08-31-17 | 
										 
											| Time Computed | 09-01-16 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 364 | 
										 
											| Percent Time Used | 99 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST GOODWILL CONTRACT SERVICES, INC. | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6307-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 08160943 | 
										 
									  | Totals | 44370.00 | 0.00 | 32375.00 | 100.0 | 
								
									
  | 
								
									
										
											| County | LIMESTONE | 
										 
											| Highway | US0084 | 
										 
											| From | VARIOUS ROADWAYS IN | 
										 
											| To | LIMESTONE COUNTY | 
										 
											| CSJ | 6323-45-001 | 
										 
											| Proj ID | RMC - 632345001 | 
										 
											| Work Type | TREE TRIMMING AND REMOVAL | 
										 
											|   | 
										 
									  | 0.010 | 137009.26 |  | 92425.28 | 100.0 | 
								
									
										
											| NO CURRENT ESTIMATE AT TIME OF THIS RUN | 
										 
											| Work Order | 01-08-18 | 
										 
											| Work Began | 01-08-18 | 
										 
											| Work Completed | 03-26-19 | 
										 
											| Time Computed | 01-08-18 | 
										 
											| Contract Working Days | 70 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 58 | 
										 
											| Percent Time Used | 82 | 
										 
											| Contractor(s) | 
										 
											| C.E.S. CONTRACTOR | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6323-45-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 11170901 | 
										 
									  | Totals | 137009.26 | 0.00 | 92425.28 | 100.0 | 
								
									
  | 
								
									
										
											| County | MCLENNAN | 
										 
											| Highway | SS0299 | 
										 
											| From | WACO DISTRICTG | 
										 
											| To | COMPLEX | 
										 
											| CSJ | 6354-83-001 | 
										 
											| Proj ID | SUP - 635483001 | 
										 
											| Work Type | JANITOIRLA | 
										 
											|   | 
										 
									  | 0.010 | 59039.80 |  | 40490.78 | 100.0 | 
								
									
										
											| Work Order | 12-19-19 | 
										 
											| Work Began | 01-01-20 | 
										 
											| Work Completed | 08-31-20 | 
										 
											| Time Computed | 01-01-20 | 
										 
											| Contract Working Days | 234 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 243 | 
										 
											| Percent Time Used | 103 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST RELIEF ENTERPRISES | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6354-83-001 RELIEF ENTERPRISES (100.00)
  | 
										 
											| Contract # | 12190930 | 
										 
									  | Totals | 59039.80 | 5150.25 | 40490.78 | 100.0 | 
								
									
  | 
								
									
										
											| County | CORYELL | 
										 
											| Highway | FM1113 | 
										 
											| From | CORYELL, BOSQUE, AND HAMILTON COUNTIES | 
										 
											| To | CORYELL, BOSQUE, AND HAMILTON COUNTIES | 
										 
											| CSJ | 6401-06-001 | 
										 
											| Proj ID | RMC - 640106001 | 
										 
											| Work Type | TREE TRIMMING AND BRUSH REMOVAL | 
										 
											|   | 
										 
									  | 0.010 | 185095.00 |  | 239607.35 | 100.0 | 
								
									
										
											| Work Order | 09-01-22 | 
										 
											| Work Began | 09-06-22 | 
										 
											| Work Completed | 10-31-24 | 
										 
											| Time Computed | 07-30-22 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 365 | 
										 
											| Working Days Charged | 730 | 
										 
											| Percent Time Used | 100 | 
										 
											| Contractor(s) | 
										 
											| BUSHWACKERS CONTRACTING, LLC | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6401-06-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 06220902 | 
										 
									  | Totals | 185095.00 | 0.00 | 239607.35 | 100.0 | 
								
									
  | 
								
									
										
											| County | BOSQUE | 
										 
											| Highway | SH0006 | 
										 
											| From | VARIOUS ROADWAYS | 
										 
											| To | IN BOSQUE COUNTY | 
										 
											| CSJ | 6418-19-001 | 
										 
											| Proj ID | MMC - 641819001 | 
										 
											| Work Type | HOT MIX | 
										 
											|   | 
										 
									  | 0.010 | 299980.00 |  | 202315.98 | 100.0 | 
								
									
										
											| Work Order | 10-04-22 | 
										 
											| Work Began | 10-03-22 | 
										 
											| Work Completed | 02-06-23 | 
										 
											| Time Computed | 10-10-22 | 
										 
											| Contract Working Days | 120 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 83 | 
										 
											| Percent Time Used | 69 | 
										 
											| Contractor(s) | 
										 
											| KNIFE RIVER CORPORATION - SOUTH | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6418-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 08220930 | 
										 
									  | Totals | 299980.00 | 5415.87 | 202315.98 | 100.0 | 
								
									
  | 
								
									
										
											| County | HAMILTON | 
										 
											| Highway | FM0219 | 
										 
											| From | VARIOUS LOCATIONS | 
										 
											| To | IN HAMILTON COUNTY | 
										 
											| CSJ | 6420-91-001 | 
										 
											| Proj ID | RMC - 642091001 | 
										 
											| Work Type | MOWING HIGHWAY RIGHT OF WAY | 
										 
											|   | 
										 
									  | 0.010 | 221141.26 |  | 338453.37 | 99.9 | 
								
									
										
											| Work Order | 03-01-23 | 
										 
											| Work Began | 05-30-23 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 03-01-23 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 365 | 
										 
											| Working Days Charged | 611 | 
										 
											| Percent Time Used | 83 | 
										 
											| Contractor(s) | 
										 
											| MARLANE CONSTRUCTION, LLC | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6420-91-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 12220952 | 
										 
									  | Totals | 221141.26 | 18506.62 | 338453.37 | 99.9 | 
								
									
  | 
								
									
										
											| County | BOSQUE | 
										 
											| Highway | SH0006 | 
										 
											| From | VARIOUS ROADWAYS | 
										 
											| To | ACROSS BOSQUE, CORYELL AND HAMILTON CO. | 
										 
											| CSJ | 6459-09-001 | 
										 
											| Proj ID | RMC - 645909001 | 
										 
											| Work Type | CLEANING AND SWEEPING HIGHWAYS | 
										 
											|   | 
										 
									  | 0.010 | 97379.32 |  | 11466.16 | 11.7 | 
								
									
										
											| Work Order | 02-10-24 | 
										 
											| Work Began | 04-10-24 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 03-01-24 | 
										 
											| Contract Working Days | 366 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 245 | 
										 
											| Percent Time Used | 66 | 
										 
											| Contractor(s) | 
										 
											| PROFESSIONAL TRAFFIC CONTROL LLC | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6459-09-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 01240901 | 
										 
									  | Totals | 97379.32 | 0.00 | 11466.16 | 11.7 | 
								
									
  | 
								
									
										
											| County | MCLENNAN | 
										 
											| Highway | US0077 | 
										 
											| From | VARIOUS LOCATIONS | 
										 
											| To | IN MCLENNAN COUNTY | 
										 
											| CSJ | 6469-36-001 | 
										 
											| Proj ID | RMC - 646936001 | 
										 
											| Work Type | TREE TRIMMING AND BRUSH REMOVAL | 
										 
											|   | 
										 
									  | 0.010 | 92300.00 |  | 15305.00 | 16.5 | 
								
									
										
											| Work Order | 00-00-00 | 
										 
											| Work Began | 00-00-00 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 09-20-24 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 16 | 
										 
											| Percent Time Used | 4 | 
										 
											| Contractor(s) | 
										 
											| BUSHWACKERS CONTRACTING, LLC | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6469-36-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 07240951 | 
										 
									  | Totals | 92300.00 | 15305.00 | 15305.00 | 16.5 | 
								
									
  | 
								
									
										
											| County | BELL | 
										 
											| Highway | FM1670 | 
										 
											| From | VARIOUS LOCATIONS | 
										 
											| To | ACROSS BELL COUNTY | 
										 
											| CSJ | 6469-37-001 | 
										 
											| Proj ID | RMC - 646937001 | 
										 
											| Work Type | TREE TRIMMING AND BRUSH REMOVAL | 
										 
											|   | 
										 
									  | 0.010 | 148201.96 |  | 0.00 | 0.0 | 
								
									
										
											| Work Order | 00-00-00 | 
										 
											| Work Began | 00-00-00 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 10-01-24 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 31 | 
										 
											| Percent Time Used | 8 | 
										 
											| Contractor(s) | 
										 
											| ALLIES LAND CLEARING | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6469-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
  | 
										 
											| Contract # | 07240953 | 
										 
									  | Totals | 148201.96 | 0.00 | 0.00 | 0.0 | 
								
									
  | 
								
									
										
											| County | CORYELL | 
										 
											| Highway | US0084 | 
										 
											| From | VARIOUS LOCATIONS ACROSS | 
										 
											| To | CORYELL, BOSQUE, HAMILTON AND FALLS CO. | 
										 
											| CSJ | 6470-04-001 | 
										 
											| Proj ID | EMC - 647004001 | 
										 
											| Work Type | EMERGENCY BRIDGE REPAIR | 
										 
											|   | 
										 
									  | 0.010 | 3465801.00 |  | 1987232.00 | 57.4 | 
								
									
										
											| Work Order | 06-26-24 | 
										 
											| Work Began | 06-26-24 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 06-26-24 | 
										 
											| Contract Working Days | 45 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 48 | 
										 
											| Percent Time Used | 106 | 
										 
											| Contractor(s) | 
										 
											| BK FIELD OPERATIONS LLC | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6470-04-001 W-TEX SERVICES LLC (30.00)
  | 
										 
											| Contract # | 06240911 | 
										 
									  | Totals | 3465801.00 | 13340.00 | 1987232.00 | 57.4 | 
								
									
  | 
								
									
										
											| County | FALLS | 
										 
											| Highway | US0077 | 
										 
											| From | VARIOUS LOCATIONS | 
										 
											| To | IN FALLS COUNTY | 
										 
											| CSJ | 6470-96-001 | 
										 
											| Proj ID | EMC - 647096001 | 
										 
											| Work Type | BRIDGE REPAIR | 
										 
											|   | 
										 
									  | 0.010 | 3072072.00 |  | 624165.00 | 20.3 | 
								
									
										
											| Work Order | 09-24-24 | 
										 
											| Work Began | 00-00-00 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 09-30-24 | 
										 
											| Contract Working Days | 120 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 20 | 
										 
											| Percent Time Used | 16 | 
										 
											| Contractor(s) | 
										 
											| JAMES CONSTRUCTION GROUP, LLC | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6470-96-001 LONE STAR PAVING COMPANY (0.00) BEAIRD DRILLING SERVICES, INC. (0.00) HERMANOS STEEL, LLC (0.00) WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.00)
  | 
										 
											| Contract # | 08240901 | 
										 
									  | Totals | 3072072.00 | 624165.00 | 624165.00 | 20.3 | 
								
									
  | 
								
									
										
											| County | BOSQUE | 
										 
											| Highway | SH0006 | 
										 
											| From | VARIOUS LOCATIONS | 
										 
											| To | IN BOSQUE COUNTY | 
										 
											| CSJ | 6471-38-001 | 
										 
											| Proj ID | SUP - 647138001 | 
										 
											| Work Type | PICNIC AREA MAINTENANCE | 
										 
											|   | 
										 
									  | 0.010 | 110760.00 |  | 14400.00 | 13.0 | 
								
									
										
											| Work Order | 00-00-00 | 
										 
											| Work Began | 09-01-24 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 09-02-24 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 55 | 
										 
											| Percent Time Used | 15 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST SPANGLISH FOUNDATION | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6471-38-001 SPANGLISH FOUNDATION (100.00)
  | 
										 
											| Contract # | 08240932 | 
										 
									  | Totals | 110760.00 | 8520.00 | 14400.00 | 13.0 | 
								
									
  | 
								
									
										
											| County | BOSQUE | 
										 
											| Highway | SH0006 | 
										 
											| From | TXDOT COMPLEX @ 9167 SH 6 | 
										 
											| To | IN MERIDIAN, TX 76665 | 
										 
											| CSJ | 6471-44-001 | 
										 
											| Proj ID | SUP - 647144001 | 
										 
											| Work Type | GROUNDS MAINTENANCE | 
										 
											|   | 
										 
									  | 0.010 | 28070.00 |  | 1225.00 | 4.3 | 
								
									
										
											| Work Order | 08-31-24 | 
										 
											| Work Began | 09-01-24 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 09-02-24 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 55 | 
										 
											| Percent Time Used | 15 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST SPANGLISH FOUNDATION | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6471-44-001 SPANGLISH FOUNDATION (100.00)
  | 
										 
											| Contract # | 08240931 | 
										 
									  | Totals | 28070.00 | 612.50 | 1225.00 | 4.3 | 
								
									
  | 
								
									
										
											| County | HAMILTON | 
										 
											| Highway | US0281 | 
										 
											| From | VARIOUS LOCATIONS | 
										 
											| To | ACROSS HAMILTON COUNTY | 
										 
											| CSJ | 6471-46-001 | 
										 
											| Proj ID | SUP - 647146001 | 
										 
											| Work Type | PICNIC AREA MAINTENANCE | 
										 
											|   | 
										 
									  | 0.010 | 92300.00 |  | 12000.00 | 13.0 | 
								
									
										
											| Work Order | 00-00-00 | 
										 
											| Work Began | 09-01-24 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 09-02-24 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 55 | 
										 
											| Percent Time Used | 15 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST SPANGLISH FOUNDATION | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6471-46-001 SPANGLISH FOUNDATION (100.00)
  | 
										 
											| Contract # | 08240934 | 
										 
									  | Totals | 92300.00 | 7100.00 | 12000.00 | 13.0 | 
								
									
  | 
								
									
										
											| County | HAMILTON | 
										 
											| Highway | SH0022 | 
										 
											| From | HAMILTON COUNTY FACILITY | 
										 
											| To | HAMILTON COUNTY FACILITY | 
										 
											| CSJ | 6471-68-001 | 
										 
											| Proj ID | SUP - 647168001 | 
										 
											| Work Type | GROUNDS MAINTENANCE | 
										 
											|   | 
										 
									  | 0.010 | 14040.00 |  | 1020.00 | 7.2 | 
								
									
										
											| Work Order | 00-00-00 | 
										 
											| Work Began | 09-01-24 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 09-02-24 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 55 | 
										 
											| Percent Time Used | 15 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST SPANGLISH FOUNDATION | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6471-68-001 SPANGLISH FOUNDATION (100.00)
  | 
										 
											| Contract # | 08240935 | 
										 
									  | Totals | 14040.00 | 1020.00 | 1020.00 | 7.2 | 
								
									
  | 
								
									
										
											| County | BELL | 
										 
											| Highway | SL0121 | 
										 
											| From | BELL COUNTY MAINTENANCE/ENGINEERING COMP | 
										 
											| To | 410 WEST LOOP 121 IN BELTON TEXAS | 
										 
											| CSJ | 6471-70-001 | 
										 
											| Proj ID | SUP - 647170001 | 
										 
											| Work Type | GROUNDS MAINTENANCE | 
										 
											|   | 
										 
									  | 0.010 | 9025.89 |  | 555.17 | 6.1 | 
								
									
										
											| Work Order | 00-00-00 | 
										 
											| Work Began | 09-01-24 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 09-02-24 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 61 | 
										 
											| Percent Time Used | 16 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST TEJAS ROADRUNNERS, NON-PROFIT CORPORATION | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6471-70-001 TEJAS ROADRUNNERS, NON-PROFIT CORPORATION (100.00)
  | 
										 
											| Contract # | 08240933 | 
										 
									  | Totals | 9025.89 | 555.17 | 555.17 | 6.1 | 
								
									
  | 
								
									
										
											| County | BELL | 
										 
											| Highway | SH0095 | 
										 
											| From | VARIOUS LOCATIONS | 
										 
											| To | ACROSS BELL COUNTY | 
										 
											| CSJ | 6471-73-001 | 
										 
											| Proj ID | SUP - 647173001 | 
										 
											| Work Type | PICNIC AREA MAINTENANCE | 
										 
											|   | 
										 
									  | 0.010 | 33630.00 |  | 4361.00 | 12.9 | 
								
									
										
											| Work Order | 00-00-00 | 
										 
											| Work Began | 09-01-24 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 09-02-24 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 61 | 
										 
											| Percent Time Used | 16 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST SPANGLISH FOUNDATION | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6471-73-001 SPANGLISH FOUNDATION (100.00)
  | 
										 
											| Contract # | 08240937 | 
										 
									  | Totals | 33630.00 | 2264.00 | 4361.00 | 12.9 | 
								
									
  | 
								
									
										
											| County | CORYELL | 
										 
											| Highway | US0084 | 
										 
											| From | CORYELL COUNTY MAINTENANCE AND ENGINEER | 
										 
											| To | COMPLEX 3502 E. MAIN, GATESVILLE TEXAS | 
										 
											| CSJ | 6471-78-001 | 
										 
											| Proj ID | SUP - 647178001 | 
										 
											| Work Type | JANITORIAL MAINTENANCE | 
										 
											|   | 
										 
									  | 0.010 | 17377.44 |  | 2442.52 | 14.0 | 
								
									
										
											| Work Order | 00-00-00 | 
										 
											| Work Began | 09-01-24 | 
										 
											| Work Completed |  | 
										 
											| Time Computed | 09-02-24 | 
										 
											| Contract Working Days | 365 | 
										 
											| Addl Days Granted | 0 | 
										 
											| Working Days Charged | 55 | 
										 
											| Percent Time Used | 15 | 
										 
											| Contractor(s) | 
										 
											WORKQUEST GOODWILL TEMPORARY SERVICES, INC. | 
										 
											SUBCONTRACTOR(S) FOR CCSJ: 6471-78-001 GOODWILL TEMPORARY SERVICES, INC. (100.00)
  | 
										 
											| Contract # | 08240941 | 
										 
									  | Totals | 17377.44 | 1184.21 | 2442.52 | 14.0 | 
								
									
  |