Monthly Local Let Maintenance Report For Waco District As Of Jul 13, 2021 Page 1 Of 3

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHILL
HighwaySH0171
FromSTATE MAINTAINED ROADWAYS
ToHILL COUNTY
CSJ6250-54-001
Proj IDRMC - 625054001
Work TypeMOWING ROW & LITTER PICKUP AND DISPOSAL
 
221.740209531.30214580.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-13
Work Began06-18-13
Work Completed
Time Computed06-18-13
Contract Working Days124
Addl Days Granted0
Working Days Charged68
Percent Time Used54
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6250-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12120904
Totals209531.300.00214580.6099.9

CountyFALLS
HighwaySH0007
FromVARIOUS ROADWAYS IN FALLS, LIMESTONE &
ToHILL COUNTIES
CSJ6288-93-001
Proj IDRMC - 628893001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01046527.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days77
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150903
Totals46527.660.000.000.0

CountyHAMILTON
HighwaySH0006
FromVARIOUS ROADWAYS IN BOSQUE, CORYELL,
ToAND HAMILTON COUNTIES
CSJ6288-94-001
Proj IDRMC - 628894001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01047693.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days89
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150901
Totals47693.000.000.000.0

CountyMCLENNAN
HighwaySH0006
FromVAR RDWYS IN BELL, BOSQUE, FALLS, HIILL,
ToCORYELL, HAMILTON, LIMESTONE, MCLENNAN
CSJ6297-29-001
Proj IDRMC - 629729001
Work TypeLARGE SIGN MAINTENANCE (DISTRICT WIDE)
 
0.010176300.00591674.05100.0
Work Order05-13-16
Work Began10-05-16
Work Completed09-01-18
Time Computed05-23-16
Contract Working Days365
Addl Days Granted335
Working Days Charged700
Percent Time Used100
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160903
Totals176300.000.00591674.05100.0

CountyCORYELL
HighwaySH0009
FromINTERSECTION OF SH 9 AND
ToFM 116
CSJ6300-02-001
Proj IDRMC - 630002001
Work TypeTRAFFIC SIGNAL INSTALLATION
 
0.100196235.20200754.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-16
Work Began09-08-16
Work Completed
Time Computed05-31-16
Contract Working Days50
Addl Days Granted0
Working Days Charged46
Percent Time Used92
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160902
Totals196235.200.00200754.0499.9

CountyFALLS
HighwaySH0007
FromVARIOUS ROADWAYS IN FALLS, HILL AND
ToLIMESTONE COUNTIES
CSJ6306-36-001
Proj IDRMC - 630636001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01046343.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-05-18
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170902
Totals46343.100.000.000.0

CountyHAMILTON
HighwaySH0036
FromVARIOUS ROADWAYS IN BOSQUE,CORYELL,
To& HAMILTON COUNTIES
CSJ6306-37-001
Proj IDRMC - 630637001
Work TypeCLEANING & SWEEPING
 
0.01085083.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days148
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170903
Totals85083.680.000.000.0

CountyCORYELL
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6307-12-001
Proj IDSUP - 630712001
Work TypePICNIC AREA MAINTENANCE
 
0.01047770.0039845.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
WORKQUEST
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160942
Totals47770.000.0039845.00100.0

CountyHAMILTON
HighwayUS0281
FromVARIOUS
ToVARIOUS
CSJ6307-13-001
Proj IDSUP - 630713001
Work TypePICNIC AREA MAINTENANCE
 
0.01044370.0032375.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
WORKQUEST
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160943
Totals44370.000.0032375.00100.0

CountyLIMESTONE
HighwayUS0084
FromVARIOUS ROADWAYS IN
ToLIMESTONE COUNTY
CSJ6323-45-001
Proj IDRMC - 632345001
Work TypeTREE TRIMMING AND REMOVAL
 
0.010137009.2692425.28100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-08-18
Work Began01-08-18
Work Completed03-26-19
Time Computed01-08-18
Contract Working Days70
Addl Days Granted0
Working Days Charged58
Percent Time Used82
Contractor(s)
C.E.S. CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 6323-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11170901
Totals137009.260.0092425.28100.0

CountyBELL
HighwaySH0317
FromBELL,BOSQUE,CORYELL,FALLS,HAMILTON
ToHILL,LIMESTONE & MCLENNAN COUNTIES
CSJ6324-16-001
Proj IDRMC - 632416001
Work TypeMEASURING RETROREFLECTIVITY DISTRICTWIDE
 
0.10035445.7523285.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-24-18
Work Completed12-25-18
Time Computed04-24-18
Contract Working Days30
Addl Days Granted0
Working Days Charged21
Percent Time Used70
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02180902
Totals35445.750.0023285.00100.0

CountyBELL
HighwayFM0439
FromVARIOUS LOCATIONS IN
ToBELL COUNTY
CSJ6347-26-001
Proj IDRMC - 634726001
Work TypeTREE TRIM.BRUSH,DRIFTWOOD& DEBRIS REMOVE
 
0.010100425.0072950.00100.0
Work Order00-00-00
Work Began10-29-19
Work Completed10-27-20
Time Computed10-29-19
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
LYELLCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6347-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08190902
Totals100425.000.0072950.00100.0

CountyBELL
HighwaySH0317
FromVAR RDWYS IN BELL, BOSQUE, CORYELL,FALLS
ToHAMILTON, HILL, LIMESTONE & MCLENNAN
CSJ6352-37-001
Proj IDRMC - 635237001
Work TypeNON SITE SPEC MEAS OF RETROREFLECTIVITY
 
0.01027461.5915645.8956.9
Work Order00-00-00
Work Began04-06-20
Work Completed
Time Computed06-01-20
Contract Working Days30
Addl Days Granted0
Working Days Charged11
Percent Time Used36
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6352-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01200901
Totals27461.5915645.8915645.8956.9

CountyBOSQUE
HighwaySH0006
From_VARIOUS ROADWAYS IN
To_BOSQUE COUNTY
CSJ6352-96-001
Proj IDRMC - 635296001
Work TypeMOWING AND LITTER REMOVAL
 
0.010246990.60226881.60100.0
Work Order00-00-00
Work Began06-01-20
Work Completed12-29-20
Time Computed06-01-20
Contract Working Days106
Addl Days Granted0
Working Days Charged82
Percent Time Used77
Contractor(s)
BAR NONE AG SUPPLY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6352-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12190902
Totals246990.600.00226881.60100.0

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN FALLS, HILL,
ToLIMESTONE AND MCLENNAN COUNTIES
CSJ6354-19-001
Proj IDRMC - 635419001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010215763.7233582.7915.5
Work Order00-00-00
Work Began01-28-21
Work Completed
Time Computed11-09-20
Contract Working Days365
Addl Days Granted0
Working Days Charged198
Percent Time Used54
Contractor(s)
STAR SWEEPING USA INC.
SUBCONTRACTOR(S) FOR CCSJ: 6354-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02200901
Totals215763.725511.2133582.7915.5

CountyMCLENNAN
HighwaySS0299
FromWACO DISTRICTG
ToCOMPLEX
CSJ6354-83-001
Proj IDSUP - 635483001
Work TypeJANITOIRLA
 
0.01059039.8040490.78100.0
Work Order12-19-19
Work Began01-01-20
Work Completed08-31-20
Time Computed01-01-20
Contract Working Days234
Addl Days Granted0
Working Days Charged243
Percent Time Used103
Contractor(s)
WORKQUEST
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6354-83-001
RELIEF ENTERPRISES (100.00)
Contract #12190930
Totals59039.805150.2540490.78100.0

CountyMCLENNAN
HighwaySH0006
FromVARIOUS LOCATIONS IN
ToMCLENNAN AND HAMILTON COUNTY.
CSJ6357-28-001
Proj IDRMC - 635728001
Work TypeDITCH & CULVERT CLEANING(NON-SITE SPEC.)
 
0.010124850.0015459.0012.3
Work Order10-28-20
Work Began00-00-00
Work Completed
Time Computed09-01-20
Contract Working Days365
Addl Days Granted0
Working Days Charged201
Percent Time Used55
Contractor(s)
BPP HOLDINGS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6357-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05200908
Totals124850.000.0015459.0012.3

CountyBELL
HighwayFM0487
From_VARIOUS ROADWAYS IN
To_BELL COUNTY
CSJ6362-79-001
Proj IDRMC - 636279001
Work TypeTREE TRIM,BRUSH,DRIFTWOOD & DEBRIS REMOV
 
0.01082959.000.000.0
Work Order12-14-20
Work Began00-00-00
Work Completed
Time Computed12-15-20
Contract Working Days365
Addl Days Granted0
Working Days Charged176
Percent Time Used48
Contractor(s)
BPP HOLDINGS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6362-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08200902
Totals82959.000.000.000.0

CountyBOSQUE
HighwaySH0006
From_BOSQUE COUNTY
To_MAINTENANCE OFFICE
CSJ6365-06-001
Proj IDSUP - 636506001
Work TypeLAWN AND GROUNDS MAINTENANCE
 
0.01024195.004700.0019.4
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days427
Addl Days Granted0
Working Days Charged365
Percent Time Used85
Contractor(s)
WORKQUEST
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6365-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06200930
Totals24195.00790.004700.0019.4

CountyMCLENNAN
HighwayUS0084
FromBELL, BOSQUE, CORYELL, FALLS, HAMILTON
ToHILL, LIMESTONE, MCLENNAN
CSJ6365-54-001
Proj IDMMC - 636554001
Work TypeDE-ICING/ANTI-ICING MATERIAL
 
0.010236630.83281775.9399.9
Work Order01-08-21
Work Began00-00-00
Work Completed
Time Computed01-11-21
Contract Working Days120
Addl Days Granted120
Working Days Charged166
Percent Time Used69
Contractor(s)
UNITED SALT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6365-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08200951
Totals236630.830.00281775.9399.9

page 1 | page 2 | page 3