Monthly State Let Maintenance Report For Waco District As Of Jan 10, 2023 Page 1 Of 4

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFALLS
HighwaySH0014
FromVARIOUS ROADWAYS IN
ToFALLS COUNTY
CSJ6270-61-001
Proj IDRMC - 627061001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010670190.00658724.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-14
Work Began10-17-14
Work Completed12-31-14
Time Computed09-15-14
Contract Working Days60
Addl Days Granted0
Working Days Charged40
Percent Time Used66
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06144002
Totals670190.000.00658724.00100.0

CountyFALLS
HighwayFM0147
FromVARIOUS ROADWAYS IN
ToFALLS COUNTY
CSJ6341-72-001
Proj IDRMC - 634172001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010507127.80512748.70100.0
Work Order02-03-20
Work Began04-07-20
Work Completed06-04-20
Time Computed02-04-20
Contract Working Days67
Addl Days Granted0
Working Days Charged12
Percent Time Used17
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6341-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194221
Totals507127.800.00512748.70100.0

CountyMCLENNAN
HighwayFM1858
FromVAR RDWYS IN BELL, CORYELL, FALLS, HILL,
ToLIMESTONE AND MCLENNAN COUNTIES
CSJ6347-55-001
Proj IDRMC - 634755001
Work TypeSEAL COAT
 
0.0101537362.721733040.97100.0
Work Order00-00-00
Work Began06-08-20
Work Completed06-26-20
Time Computed03-02-20
Contract Working Days26
Addl Days Granted0
Working Days Charged16
Percent Time Used61
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6347-55-001
FLASHER EQUIPMENT COMPANY (1.43)
STRIPE-A-ZONE, INC. (16.58)
BRYDL CONTRACTING, INC. (1.21)
Contract #09194018
Totals1537362.7217605.401733040.97100.0

CountyMCLENNAN
HighwayIH0035
FromMM
ToMM
CSJ6351-58-001
Proj IDRMC - 635158001
Work TypeROUTINE MAINTENANCE OF IH - 35 CORRIDOR
 
0.01026575153.0020816939.6878.3
Work Order08-26-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days1,095
Addl Days Granted0
Working Days Charged846
Percent Time Used77
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6351-58-001
BIG CREEK CONSTRUCTION, LTD. (0.00)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00)
Contract #05204226
Totals26575153.00604054.5720816939.6878.3

CountyFALLS
HighwaySH0006
FromVARIOUS RDWYS
ToIN FALLS COUNTY
CSJ6356-85-001
Proj IDMMC - 635685001
Work TypeHOT MIX-MATERIAL ONLY
 
0.0101108250.001871059.22100.0
Work Order07-07-20
Work Began07-07-20
Work Completed06-25-21
Time Computed06-01-20
Contract Working Days120
Addl Days Granted240
Working Days Charged329
Percent Time Used91
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6356-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03204015
Totals1108250.00174686.521871059.22100.0

CountyHILL
HighwayFM0310
FromVARIOUS ROADWAYS IN HILL, FALLS AND
ToLIMESTONE COUNTIES
CSJ6362-77-001
Proj IDRMC - 636277001
Work TypeTREE TRIM, BRUSH REM, DRIFTWOOD & DEBRIS
 
0.010362572.00643202.46100.0
Work Order00-00-00
Work Began12-01-20
Work Completed09-01-21
Time Computed11-01-20
Contract Working Days365
Addl Days Granted0
Working Days Charged274
Percent Time Used75
Contractor(s)
PATHFIELD INVESTMENTS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6362-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07204016
Totals362572.000.00643202.46100.0

CountyBELL
HighwaySH0317
FromRDWYS IN BELL, BOSQUE, CORYELL, FALLS
ToHILL, HAMILTON, LIMESTONE & MCLENNAN
CSJ6364-94-001
Proj IDRMC - 636494001
Work TypeDISTRICT WIDE PAVEMENT MARKINGS
 
0.0101435500.001666751.28100.0
Work Order00-00-00
Work Began03-02-21
Work Completed02-28-22
Time Computed02-10-21
Contract Working Days365
Addl Days Granted0
Working Days Charged362
Percent Time Used99
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6364-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204025
Totals1435500.00126544.921666751.28100.0

CountyBELL
HighwayUS0190
From_AT VARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6364-95-001
Proj IDRMC - 636495001
Work TypeLARGE SIGN MAINTENANCE-DISTRICT WIDE
 
0.010274900.00161176.7158.6
Work Order00-00-00
Work Began01-04-21
Work Completed
Time Computed11-30-20
Contract Working Days365
Addl Days Granted365
Working Days Charged721
Percent Time Used98
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6364-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204210
Totals274900.000.00161176.7158.6

CountyMCLENNAN
HighwaySH0006
FromWACO DISTRICT - FALLS, HILL, LIMESTONE,
ToAND MCLENNAN COUNTIES
CSJ6365-05-001
Proj IDRMC - 636505001
Work TypeMBGF,BRIDGE RAIL,CABLE BARRIER REPR&INST
 
0.010887302.001521186.0099.9
Work Order12-07-20
Work Began12-15-20
Work Completed
Time Computed11-01-20
Contract Working Days365
Addl Days Granted365
Working Days Charged726
Percent Time Used99
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6365-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09204212
Totals887302.0033400.001521186.0099.9

CountyMCLENNAN
HighwayFM0185
FromBELL, HAMILTON, HILL, LIMESTONE,
ToAND MCLENNAN COUNTIES
CSJ6366-45-001
Proj IDBPM - 636645001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.010623661.41744117.61100.0
Work Order05-03-21
Work Began06-02-21
Work Completed11-15-22
Time Computed05-10-21
Contract Working Days45
Addl Days Granted30
Working Days Charged74
Percent Time Used98
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6366-45-001
ACME BARRICADES, LLC (1.45)
Contract #12204226
Totals623661.41222432.08744117.61100.0

CountyLIMESTONE
HighwaySH0007
FromVARIOUS ROADWAYS IN
ToLIMESTONE COUNTY
CSJ6369-31-001
Proj IDRMC - 636931001
Work TypeMOWING AND LITTTER
 
0.010260742.20260217.20100.0
Work Order06-14-21
Work Began06-14-21
Work Completed12-01-21
Time Computed02-01-21
Contract Working Days93
Addl Days Granted0
Working Days Charged53
Percent Time Used56
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6369-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11204226
Totals260742.2012064.40260217.20100.0

CountyFALLS
HighwaySH0006
FromVARIOUS ROADWAYS IN
ToFALL COUNTY
CSJ6369-32-001
Proj IDRMC - 636932001
Work TypeMOWING AND LITTER
 
0.010315648.15315583.14100.0
Work Order05-26-21
Work Began00-00-00
Work Completed10-26-21
Time Computed02-01-21
Contract Working Days93
Addl Days Granted0
Working Days Charged40
Percent Time Used43
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6369-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11204225
Totals315648.15157791.57315583.14100.0

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6375-32-001
Proj IDRMC - 637532001
Work TypeTRAFFIC SIGNAL MAINTENANCE_ PROJECT
 
0.010429668.00217885.4050.7
Work Order00-00-00
Work Began05-27-21
Work Completed
Time Computed04-30-21
Contract Working Days365
Addl Days Granted365
Working Days Charged578
Percent Time Used79
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6375-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214018
Totals429668.000.00217885.4050.7

CountyMCLENNAN
HighwayUS0077
FromVARIOUS ROADWAYS
ToIN MCLENNAN COUNTY
CSJ6377-69-001
Proj IDRMC - 637769001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.010136233.0085213.0162.5
Work Order08-30-21
Work Began04-05-22
Work Completed
Time Computed06-15-21
Contract Working Days365
Addl Days Granted365
Working Days Charged481
Percent Time Used65
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6377-69-001
HOLLINGSWORTH CONCRETE CORING (11.01)
Contract #04214217
Totals136233.000.0085213.0162.5

CountyCORYELL
HighwayFM0185
FromVARIOUS ROADWAYS
ToIN THE WACO DISTRICT
CSJ6377-87-001
Proj IDRMC - 637787001
Work TypeCULVERT REPAIR
 
0.010486782.00220108.5045.2
Work Order01-24-22
Work Began03-16-22
Work Completed
Time Computed10-31-21
Contract Working Days365
Addl Days Granted0
Working Days Charged328
Percent Time Used89
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6377-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08214216
Totals486782.0029930.00220108.5045.2

CountyMCLENNAN
HighwayFM1860
FromVARIOUS ROADWAYS
ToIN WACO DISTRICT
CSJ6377-88-001
Proj IDRMC - 637788001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.010386492.0082584.2521.3
Work Order09-20-21
Work Began09-27-21
Work Completed
Time Computed06-15-21
Contract Working Days365
Addl Days Granted0
Working Days Charged150
Percent Time Used41
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6377-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04214216
Totals386492.000.0082584.2521.3

CountyMCLENNAN
HighwayFM1860
FromVARIOUS LOCATIONS
ToIN MCLENNAN COUNTY
CSJ6379-44-001
Proj IDRMC - 637944001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010534686.203144890.20100.0
Work Order00-00-00
Work Began10-04-21
Work Completed10-03-22
Time Computed07-05-21
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6379-44-001
D. I. J. CONSTRUCTION, INC. (2.22)
Contract #05214019
Totals534686.20126991.353144890.20100.0

CountyMCLENNAN
HighwayIH0035
FromSITE SPECIFIC LOCATIONS
ToIN MCLENNAN, BELL, HILL, & FALLS
CSJ6379-47-001
Proj IDRMC - 637947001
Work TypeILLUMINATION MAINTENANCE
 
0.010333611.16280956.0584.2
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed05-02-22
Contract Working Days365
Addl Days Granted0
Working Days Charged59
Percent Time Used16
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6379-47-001
SNOWHILL CONTRACTING LLC (16.40)
Contract #01224021
Totals333611.1653184.61280956.0584.2

CountyLIMESTONE
HighwayUS0084
FromVARIOUS ROADWAYS
ToIN LIMESTONE COUNTY
CSJ6380-23-001
Proj IDMMC - 638023001
Work TypeHOT MIX
 
0.010178000.00307554.55100.0
Work Order00-00-00
Work Began09-20-21
Work Completed11-30-21
Time Computed07-01-21
Contract Working Days120
Addl Days Granted0
Working Days Charged67
Percent Time Used55
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6380-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05214221
Totals178000.0054098.20307554.55100.0

CountyBELL
HighwaySH0317
FromVARIOUS ROADWAYS
ToIN WACO DISTRICT
CSJ6381-22-001
Proj IDRMC - 638122001
Work TypePAVEMENT MARKINGS
 
0.0103150885.002404608.9076.3
Work Order00-00-00
Work Began02-01-22
Work Completed
Time Computed12-20-21
Contract Working Days365
Addl Days Granted0
Working Days Charged328
Percent Time Used89
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6381-22-001
BATTERSON, LLP (0.00)
Contract #10214025
Totals3150885.00269287.302404608.9076.3

page 1 | page 2 | page 3 | page 4