Monthly State Let Construction Report For Wichita Falls District As Of Jul 13, 2021 Page 1 Of 3

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTAGUE ETC
HighwayUS 81 ETC
FromRED RIVER
ToSL 19 (LANES ONLY)
CSJ0013-02-023
Proj IDSTP 2B20(301)
Work TypeSEAL COAT
 
198.7027507421.97498129.356.6
Work Order12-11-20
Work Began06-14-21
Work Completed
Time Computed05-21-21
Contract Working Days50
Addl Days Granted0
Working Days Charged14
Percent Time Used28
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-02-023
BARRICADES PLUS, LLC (2.12)
CDM HOLDINGS, LLC (67.54)
Contract #11203210
Totals7507421.97498129.35498129.356.6

CountyMONTAGUE
HighwayUS 81
FromFM 174
ToFM 3043
CSJ0013-05-062
Proj IDSTP 2021(252)
Work TypeOVERLAY
 
775964.42763576.2398.4
CountyMONTAGUE
HighwaySH 59
FromMILL STREET
ToUS 81
CSJ0239-02-038
Proj IDSTP 2021(252)
Work TypeOVERLAY
 
0.001720121.70782843.5599.9
CountyMONTAGUE
HighwaySH 59
FromUS 81
ToWICHITA STREET
CSJ0239-05-034
Proj IDSTP 2021(252)
Work TypeOVERLAY
 
132071.40149061.8399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-05-21
Work Began04-26-21
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged28
Percent Time Used41
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-062
TEXAS TRAFFIC AND BARRICADE, LLC (0.24)
DUSTROL, INC. (3.85)
INNOVATIVE ROADWAY SOLUTIONS, LLC (1.44)
STRIPE-A-ZONE, INC. (3.68)
Contract #01213213
Totals1628157.52201304.281695481.6199.9

CountyWILBARGER ETC
HighwayUS 70 ETC
FromUS 287
ToLAURIE STREET
CSJ0043-05-110
Proj IDSTP 1902(143)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
54.1048701328.894676669.9253.7
Work Order09-25-19
Work Began05-28-20
Work Completed
Time Computed10-25-19
Contract Working Days263
Addl Days Granted0
Working Days Charged208
Percent Time Used79
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-110
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.50)
TOTAL HIGHWAY MAINTENANCE, LLC (0.60)
FABER TECHNOLOGIES USA, INC. (1.28)
Contract #08193007
Totals8701328.89147368.114676669.9253.7

CountyWILBARGER
HighwayUS 70
From0.75 MILES NORTH OF FM 433
ToUS 287
CSJ0043-06-096
Proj IDF 2021(448)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
142790.000.000.0
CountyWILBARGER
HighwayUS 287
FromUS 70
To0.75 MILES SOUTH OF US 70
CSJ0043-07-121
Proj IDF 2021(448)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
530.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-06-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04213023
Totals143320.000.000.000.0

CountyWILBARGER
HighwayUS 287
FromOKLAUNION
ToHARROLD
CSJ0043-07-119
Proj IDF 2021(700)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5165943.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days136
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-07-119
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213215
Totals5165943.810.000.000.0

CountyWICHITA
HighwayUS 287
From.
ToSB AND NB REST AREAS NEAR IOWA PARK
CSJ0043-08-084
Proj IDNH 2020(165)
Work TypeSAFETY REST AREA
 
0.7635141357.004025790.6778.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-19
Work Began01-20-20
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted18
Working Days Charged311
Percent Time Used97
Contractor(s)
ANTHONY INMAN CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-08-084
BUTLER & BUTLER CONSTRUCTION LLC (9.17)
WILSON CONTRACTING (8.12)
DALLAS LITE AND BARRICADE, INC. (0.13)
BREEGLE BUILDING PRODUCTS, INC. (4.08)
FERGUSON-VERESH, INC. (9.03)
ARMORED ROOFING COMPANY, INC. (2.51)
RHS STEEL CONSTRUCTORS, LLC (2.08)
SORGE CONTRACTING INC. (0.17)
WICHITA FALLS COMPLETE LAWN SERVICE, LLC (2.62)
BNR CONCRETE POLISHING, LLC (0.21)
CHENEY ELECTRIC, LLC (4.53)
COMMERCIAL & INDUSTRIAL ELECTRONICS, INC. (2.89)
B & R SERVICES (0.01)
Contract #10193028
Totals5141357.00361005.114025790.6778.3

CountyWICHITA
HighwayUS 287
FromBU 287H
To0.5 MI W OF JOHNSON RD
CSJ0043-08-085
Proj IDF 2021(514)
Work TypeREHABILITATION OF EXISTING ROAD
 
2590826.340.000.0
CountyWICHITA
HighwayUS 287
From0.5MI W OF JOHNSON RD
ToBELL RD
CSJ0043-09-143
Proj IDF 2021(514)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.001550271.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-08-085
HJC FARMS, INC. (12.44)
DUSTROL, INC. (5.23)
TOTAL HIGHWAY MAINTENANCE, LLC (1.91)
W. S. CONSTRUCTION COMPANY (0.79)
PINNACLE GRINDING AND GROOVING LLC (0.34)
TEXAS TRAFFIC AND BARRICADE, LLC (0.26)
LANCO TURF & SEEDING, INC. (0.21)
Contract #05213212
Totals3141097.740.000.000.0

CountyWICHITA
HighwaySL 11
FromUS 287
ToFM 367
CSJ0043-14-026
Proj IDNH 2B20(225)
Work TypeOVERLAY
 
2.1501360148.320.000.0
Work Order12-04-20
Work Began00-00-00
Work Completed
Time Computed01-03-21
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-14-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11203027
Totals1360148.320.000.000.0

CountyMONTAGUE
HighwayUS 82
FromSH 175 / MONTAGUE STREET
ToNEAR FM 1816
CSJ0044-04-047
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
6.10027683391.050.000.0
CountyMONTAGUE
HighwayUS 82
From0.5 MI EAST OF US 81
ToNEAR FM 1816
CSJ0044-04-049
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
5.82920779023.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days719
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213001
Totals48462414.090.000.000.0

CountyCOOKE
HighwayFM 1199
FromFM 3108
ToUS 82
CSJ0044-09-067
Proj IDF 2021(705)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1043643.150.000.0
CountyCOOKE
HighwayFM 3108
FromFM 1199
ToFM 1630
CSJ3192-01-007
Proj IDF 2021(705)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2775494.460.000.0
CountyCOOKE
HighwayFM 3108
FromFM 3108
ToAT ELM FORK TRINITY RIVER
CSJ3192-01-008
Proj IDBR 2021(706)
Work TypeBRIDGE REPLACEMENT
 
1208335.370.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days238
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-09-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213211
Totals5027472.980.000.000.0

CountyWILBARGER
HighwayUS 183
From0.992 MI S OF FM 1763
ToBAYLOR COUNTY LINE
CSJ0124-04-038
Proj IDSTP 2B20(074)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.68010036994.001343734.6413.3
CountyBAYLOR
HighwayUS 183
FromWILBARGER CL
To5.737 MI N OF US 82
CSJ0124-05-025
Proj IDSTP 2B20(074)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.2505079547.73691452.2013.6
Work Order11-19-20
Work Began01-21-21
Work Completed
Time Computed12-19-20
Contract Working Days359
Addl Days Granted0
Working Days Charged75
Percent Time Used20
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0124-04-038
BARRICADES UNLIMITED (1.89)
FC TRAFFIC CONTROL, INC. (0.22)
MARCOM"S MOWING SERVICE, LLC (0.28)
W. S. CONSTRUCTION COMPANY (9.26)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.41)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
ZACK BURKETT CO. (36.83)
Contract #10203205
Totals15116541.73221390.082035186.8413.4

CountyBAYLOR
HighwaySH 114
FromBU 183B
ToUS 183
CSJ0133-05-030
Proj IDF 2021(515)
Work TypeOVERLAY
 
208298.760.000.0
CountyBAYLOR
HighwayBU 183B
FromSH 114
ToUS 82
CSJ0156-06-061
Proj IDF 2021(515)
Work TypeOVERLAY
 
182211.360.000.0
CountyBAYLOR
HighwayUS 82
FromBU 183B
ToUS 183
CSJ0156-06-062
Proj IDF 2021(515)
Work TypeOVERLAY
 
450401.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0133-05-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213029
Totals840911.260.000.000.0

CountyYOUNG
HighwaySH 251
FromSH 79
ToFM 926
CSJ0134-01-025
Proj IDSTP 2B20(075)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
11.3001754989.60892023.0450.8
CountyYOUNG
HighwaySH 16
FromCOUNTRY MEADOWS DR.
To0.7 MI E OF FM 1191
CSJ0362-01-052
Proj IDSTP 2B20(075)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.687277545.503885.001.3
CountyTHROCKMORTON
HighwaySH 222
FromCABIN RD
To0.8 MI N OF OTTS ROAD
CSJ0982-03-016
Proj IDSTP 2B20(075)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.741266693.9029991.0011.2
Work Order09-16-20
Work Began11-09-20
Work Completed
Time Computed01-16-22
Contract Working Days253
Addl Days Granted40
Working Days Charged114
Percent Time Used38
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0134-01-025
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.77)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.00)
PEACHTREE CONSTRUCTION, LTD. (3.96)
STRIPING TECHNOLOGY, L.P. (0.80)
PINNACLE GRINDING AND GROOVING LLC (0.10)
FC TRAFFIC CONTROL, INC. (0.60)
TOTAL HIGHWAY MAINTENANCE, LLC (6.39)
MARCOM"S MOWING SERVICE, LLC (0.69)
W. S. CONSTRUCTION COMPANY (4.09)
Contract #08203029
Totals2299229.0094352.50925899.0440.2

CountyARCHER
HighwaySH 25
From1.05 MI E OF FM 2581
To1.687 MI W OF US 281
CSJ0137-07-025
Proj IDSTP 2B20(086)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
131050.00123775.9094.4
CountyYOUNG
HighwayFM 61
FromFM 3003
ToFM 67
CSJ0529-01-024
Proj IDSTP 2B20(086)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.001459467.60363639.6079.1
Work Order09-18-20
Work Began11-10-20
Work Completed
Time Computed10-18-20
Contract Working Days51
Addl Days Granted0
Working Days Charged50
Percent Time Used98
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0137-07-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08203050
Totals590517.6030525.90487415.5082.5

CountyWICHITA
HighwaySH 240
FromIH 44
ToNEAR ROBINSON ROAD
CSJ0156-02-033
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
701607.840.000.0
CountyWICHITA
HighwaySH 240
FromNEAR ROBINSON ROAD
To2ND STREET
CSJ0156-03-049
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1128031.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days152
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0156-02-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213019
Totals1829638.840.000.000.0

CountyWICHITA
HighwayUS 82
FromARCHER COUNTY LINE
ToBEGIN 4 LANE UNDIVIDED
CSJ0156-04-125
Proj IDF 2021(418)
Work TypeOVERLAY
 
363896.750.000.0
CountyARCHER
HighwayUS 82
From1.95 MI E OF FM 2846
ToBU 82F (IN SECTIONS)
CSJ0156-05-062
Proj IDF 2021(418)
Work TypeOVERLAY
 
4362424.550.000.0
CountyARCHER
HighwayUS 82
FromBU 82F
ToWICHITA COUNTY LINE
CSJ0156-17-030
Proj IDF 2021(418)
Work TypeOVERLAY
 
3.1002333112.550.000.0
Work Order04-08-21
Work Began00-00-00
Work Completed
Time Computed05-08-21
Contract Working Days102
Addl Days Granted0
Working Days Charged16
Percent Time Used15
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-04-125
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03213205
Totals7059433.850.000.000.0

CountyARCHER ETC
HighwayUS 82 ETC
FromBAYLOR COUNTY LINE
ToBU 82F
CSJ0156-05-061
Proj IDSTP 1902(036)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
46.6847252069.494500720.9462.0
Work Order09-25-19
Work Began03-11-20
Work Completed
Time Computed10-25-19
Contract Working Days346
Addl Days Granted0
Working Days Charged229
Percent Time Used66
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-061
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.50)
CONTRACTORS SERVICE COMPANY (0.65)
Contract #08193212
Totals7252069.49139622.084500720.9462.0

CountyCOOKE
HighwayIH 35
From1.4 MI SOUTH OF SPRING CREEK ROAD
To0.2 MI SOUTH OF US 82
CSJ0195-01-119
Proj IDNH 2021(327)
Work TypeWIDEN FREEWAY
 
7.900208432431.14974660.520.4
CountyCOOKE
HighwayIH 35
From1.4 MI SOUTH OF SPRING CREEK ROAD
To0.2 MI SOUTH OF US 82
CSJ0195-01-120
Proj IDROW 0195-1-120
Work TypeRIGHT OF WAY
 
7.9001566682.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-18-21
Work Began06-21-21
Work Completed
Time Computed00-00-00
Contract Working Days1,395
Addl Days Granted0
Working Days Charged5
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0195-01-119
DOUBLE EE CONTRACTORS, LLC (0.01)
BARRICADES UNLIMITED (0.67)
ANTIGO CONSTRUCTION, INC. (0.24)
SOUTHERN CROSS CONTRACTORS, LLC (0.05)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.10)
FORTSON CONTRACTING, INC. (0.58)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.43)
SCOTT DERR PAINTING CO, LLC (0.06)
W.O.E. CONSTRUCTION, INC. (2.24)
TEXAS SHAFTS, INC. (0.67)
OSCAR ORDUNO, INC. (1.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.27)
MONARREZ TRUCKING LLC. (0.00)
DALE BROWN, INC. (0.00)
TIME STRIPING, INC. (0.05)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.17)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
WITHERS CONSTRUCTION, LLC (0.00)
FREIGHT OPERATION SERVICES, LLC, DBA FOS BROKERAGE SERVICES (0.00)
VENUS CONSTRUCTION COMPANY (0.78)
RAY"S THREADING AND FAB SHOP (1.40)
Contract #02213201
Totals209999113.36974660.52974660.520.4

CountyCLAY
HighwayUS 287
FromAT EAST FORK LITTLE WICHITA
ToRIVER (NB)
CSJ0224-02-045
Proj IDBR 2020(348)
Work TypeBRIDGE REPLACEMENT
 
0.1501971677.502001719.4899.9
CountyCLAY
HighwayUS 287
FromAT EAST FORK LITTLE WICHITA RIVER
ToRELIEF (NB)
CSJ0224-02-046
Proj IDBR 2020(349)
Work TypeBRIDGE REPLACEMENT
 
0.0941464641.001442812.0898.5
Work Order01-15-20
Work Began02-24-20
Work Completed
Time Computed02-20-19
Contract Working Days142
Addl Days Granted102
Working Days Charged243
Percent Time Used99
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0224-02-045
HODGES AND SON CONSTRUCTION COMPANY, INC. (7.49)
STRIPING TECHNOLOGY, L.P. (0.88)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.88)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.59)
HUNTER DEMOLITION & WRECKING CORPORATION (4.42)
AREA WIDE PROTECTIVE, INC. (0.10)
PRIMATE CONSTRUCTION, LP (0.22)
AARON CONCRETE CONTRACTORS, L.P. (2.43)
TORO BRAVO CONSTRUCTION, LLC (0.41)
FOUTSCO PAVING COMPANY, LLC (2.10)
WEST TEXAS ROCK RESOURCES, LLC (0.14)
Contract #12193216
Totals3436318.501217.453444531.5699.9

CountyCLAY
HighwayUS 287
FromBELLEVUE
ToMONTAGUE COUNTY LINE
CSJ0224-02-049
Proj IDNH 2021(251)
Work TypeOVERLAY
 
1.986770954.05285685.3937.0
CountyMONTAGUE
HighwayUS 287
FromCLAY COUNTY LINE
ToNEAR JACKSON RD
CSJ0224-03-061
Proj IDNH 2021(251)
Work TypeOVERLAY
 
4.4841783518.65155234.498.7
Work Order03-05-21
Work Began05-17-21
Work Completed
Time Computed06-22-21
Contract Working Days70
Addl Days Granted0
Working Days Charged25
Percent Time Used35
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0224-02-049
XROADS, L.P. (3.32)
IBCTX, LLC (3.46)
W.O.E. CONSTRUCTION, INC. (1.72)
DUSTROL, INC. (6.55)
BARRICADES UNLIMITED (3.00)
PRIMATE CONSTRUCTION, LP (0.26)
WEST TEXAS ROCK RESOURCES, LLC (0.27)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (9.33)
Contract #01213009
Totals2554472.70341765.54440919.8817.2

page 1 | page 2 | page 3