Monthly State Let Construction Report For Wichita Falls District As Of Jan 10, 2023 Page 1 Of 2

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWILBARGER ETC
HighwayUS 70 ETC
FromUS 287
ToLAURIE STREET
CSJ0043-05-110
Proj IDSTP 1902(143)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
54.1048701328.898640869.0299.7
Work Order09-25-19
Work Began05-28-20
Work Completed
Time Computed10-25-19
Contract Working Days263
Addl Days Granted15
Working Days Charged309
Percent Time Used111
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-110
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.50)
TOTAL HIGHWAY MAINTENANCE, LLC (0.60)
FABER TECHNOLOGIES USA, INC. (1.28)
H D COOK"S ROCK SOLID INC (0.54)
Contract #08193007
Totals8701328.890.008640869.0299.7

CountyWICHITA
HighwayUS 287
From.
ToSB AND NB REST AREAS NEAR IOWA PARK
CSJ0043-08-084
Proj IDNH 2020(165)
Work TypeSAFETY REST AREA
 
0.7635141357.005427784.5899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-19
Work Began01-20-20
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted249
Working Days Charged549
Percent Time Used100
Contractor(s)
ANTHONY INMAN CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-08-084
BUTLER & BUTLER CONSTRUCTION LLC (9.17)
WILSON CONTRACTING (8.12)
DALLAS LITE AND BARRICADE, INC. (0.13)
BREEGLE BUILDING PRODUCTS, INC. (4.08)
FERGUSON-VERESH, INC. (9.03)
ARMORED ROOFING COMPANY, INC. (2.51)
RHS STEEL CONSTRUCTORS, LLC (2.08)
SORGE CONTRACTING INC. (0.17)
WICHITA FALLS COMPLETE LAWN SERVICE, LLC (2.62)
BNR CONCRETE POLISHING, LLC (0.21)
CHENEY ELECTRIC, LLC (4.53)
COMMERCIAL & INDUSTRIAL ELECTRONICS, INC. (2.89)
B & R SERVICES (0.01)
Contract #10193028
Totals5141357.000.005427784.5899.9

CountyMONTAGUE
HighwayUS 82
FromSH 175 / MONTAGUE STREET
ToNEAR FM 1816
CSJ0044-04-047
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
6.10027683391.0515453451.2655.8
CountyMONTAGUE
HighwayUS 82
From0.5 MI EAST OF US 81
ToNEAR FM 1816
CSJ0044-04-049
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
5.82920779023.048687168.5241.8
Work Order08-19-21
Work Began10-25-21
Work Completed
Time Computed09-20-21
Contract Working Days719
Addl Days Granted0
Working Days Charged268
Percent Time Used37
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-047
STRAIGHT LINE SAWING & SEALING, INC. (0.24)
PINNACLE GRINDING AND GROOVING LLC (0.03)
JR WEST TEXAS CONCRETE LLC (3.18)
AREA WIDE PROTECTIVE, INC. (0.25)
DUSTY ALLEN, INC. (0.28)
DUSTROL, INC. (0.25)
HAMMETT EXCAVATION, INC. (24.22)
STRIPING TECHNOLOGY, L.P. (0.97)
TEXAS SHAFTS, INC. (0.86)
L&H ELECTRICAL, LLC (0.70)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.84)
WITHERS CONSTRUCTION, LLC (0.86)
HERMANOS STEEL, LLC (0.03)
TORO BRAVO CONSTRUCTION, LLC (0.15)
FARR FOUNDATION, INC. (0.25)
Contract #07213001
Totals48462414.09456710.9324140619.7849.8

CountyCOOKE
HighwayFM 1199
FromFM 3108
ToUS 82
CSJ0044-09-067
Proj IDF 2021(705)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1043643.15988809.9394.7
CountyCOOKE
HighwayFM 3108
FromFM 1199
ToFM 1630
CSJ3192-01-007
Proj IDF 2021(705)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2775494.461832346.4866.0
CountyCOOKE
HighwayFM 3108
FromFM 3108
ToAT ELM FORK TRINITY RIVER
CSJ3192-01-008
Proj IDBR 2021(706)
Work TypeBRIDGE REPLACEMENT
 
1208335.37273721.5322.6
Work Order08-18-21
Work Began12-07-21
Work Completed
Time Computed09-17-21
Contract Working Days238
Addl Days Granted5
Working Days Charged209
Percent Time Used86
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-09-067
JOE"S TREE SERVICE (0.76)
DUSTROL, INC. (1.29)
TEXAS SHAFTS, INC. (1.73)
BARRICADES UNLIMITED (2.23)
SOUTHERN CROSS CONTRACTORS, LLC (2.33)
RAMBO CONTRACTING, INC. (6.03)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.46)
PINNACLE GRINDING AND GROOVING LLC (0.13)
BRENDA PRICE TRUCKING (1.36)
GARRET SHIELDS INFRASTRUCTURE (2.70)
Contract #07213211
Totals5027472.9897771.853094877.9461.5

CountyWILBARGER
HighwayUS 283
FromRED RIVER
ToFM 924
CSJ0124-02-033
Proj IDF 2023(092)
Work TypeOVERLAY
 
6216761.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days61
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0124-02-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09223026
Totals6216761.980.000.000.0

CountyWILBARGER
HighwayUS 183
From0.992 MI S OF FM 1763
ToBAYLOR COUNTY LINE
CSJ0124-04-038
Proj IDSTP 2B20(074)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.68010036994.009985178.9699.9
CountyBAYLOR
HighwayUS 183
FromWILBARGER CL
To5.737 MI N OF US 82
CSJ0124-05-025
Proj IDSTP 2B20(074)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.2505079547.734328881.3885.2
Work Order11-19-20
Work Began01-21-21
Work Completed
Time Computed12-19-20
Contract Working Days359
Addl Days Granted9
Working Days Charged407
Percent Time Used110
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0124-04-038
BARRICADES UNLIMITED (1.89)
FC TRAFFIC CONTROL, INC. (0.22)
MARCOM"S MOWING SERVICE, LLC (0.28)
W. S. CONSTRUCTION COMPANY (9.26)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.41)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
ZACK BURKETT CO. (36.83)
Contract #10203205
Totals15116541.73104976.6714314060.3495.0

CountyBAYLOR
HighwayUS 183
FromUS 277
ToTHROCKMORTON CL
CSJ0125-01-034
Proj IDF 2023(090)
Work TypeREHABILITATION OF EXISTING ROAD
 
7724536.690.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days210
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0125-01-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09223234
Totals7724536.690.000.000.0

CountyBAYLOR
HighwayUS 82
FromKNOX COUNTY LINE
ToBU 183B
CSJ0133-04-042
Proj IDF 2022(303)
Work TypeSUPER-2 HIGHWAY
 
12.57915938381.263317714.6120.8
Work Order01-05-22
Work Began03-21-22
Work Completed
Time Computed02-04-22
Contract Working Days377
Addl Days Granted0
Working Days Charged173
Percent Time Used45
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-04-042
DUSTIN ALLEN, INC. (0.42)
MARCOM"S MOWING SERVICE, LLC (0.75)
TRP CONSTRUCTION GROUP, LLC (1.11)
W. S. CONSTRUCTION COMPANY (12.80)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.49)
CONTRACTORS SERVICE, LTD. (0.56)
Contract #12213023
Totals15938381.26578434.433317714.6120.8

CountyYOUNG
HighwayUS 380
From.350 MI E OF FM 926
ToFM 1769
CSJ0134-02-059
Proj IDSTP 2021(868)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.4914045567.023868282.9795.7
Work Order09-16-21
Work Began12-01-21
Work Completed
Time Computed10-16-21
Contract Working Days165
Addl Days Granted14
Working Days Charged184
Percent Time Used102
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0134-02-059
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.39)
W. S. CONSTRUCTION COMPANY (6.96)
CONTRACTORS SERVICE, LTD. (1.02)
BARRICADES UNLIMITED (0.93)
TOTAL HIGHWAY MAINTENANCE, LLC (1.71)
DUSTROL, INC. (0.44)
STOUT EXCAVATING GROUP TEXAS, LLC (2.13)
Contract #08213229
Totals4045567.02836519.853868282.9795.7

CountyYOUNG
HighwayUS 380
FromFM 926
ToNEWCASTLE EAST CITY LIMITS
CSJ0134-02-060
Proj IDF 2022(135)
Work TypeOVERLAY
 
9.4362285264.982421951.2899.9
Work Order11-17-21
Work Began06-27-22
Work Completed
Time Computed12-17-21
Contract Working Days46
Addl Days Granted0
Working Days Charged41
Percent Time Used89
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0134-02-060
W. S. CONSTRUCTION COMPANY (1.67)
DIIBS SPECIALISTS, LLC (1.67)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.31)
CHEROKEE CONSTRUCTION SERVICES (0.33)
TOTAL HIGHWAY MAINTENANCE, LLC (3.79)
DALLAS LITE AND BARRICADE, INC. (0.37)
Contract #10213024
Totals2285264.9855260.482421951.2899.9

CountyWICHITA
HighwaySH 240
FromIH 44
ToNEAR ROBINSON ROAD
CSJ0156-02-033
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
701607.84493439.0070.3
CountyWICHITA
HighwaySH 240
FromNEAR ROBINSON ROAD
To2ND STREET
CSJ0156-03-049
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1128031.00717238.5063.5
Work Order08-25-21
Work Began07-11-22
Work Completed
Time Computed09-24-21
Contract Working Days152
Addl Days Granted0
Working Days Charged101
Percent Time Used66
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0156-02-033
GARRET SHIELDS INFRASTRUCTURE (102.75)
WEST TEXAS ROCK RESOURCES, LLC (0.72)
WG ENGINEERING & CONSTRUCTION, LLC (16.02)
STRIPE-A-ZONE, LLC (6.13)
MEDELLIN HDD LLC (0.39)
ARBOR RESOURCES, LLC (1.55)
Contract #07213019
Totals1829638.84217279.001210677.5066.1

CountyARCHER
HighwayUS 82
From2.2 MI WEST OF FM 2846
To1.95 MI EAST OF FM 2846
CSJ0156-05-063
Proj IDF 2022(136)
Work TypeOVERLAY
 
4.9504706206.174583554.6297.3
Work Order11-17-21
Work Began04-12-22
Work Completed
Time Computed12-17-21
Contract Working Days62
Addl Days Granted0
Working Days Charged62
Percent Time Used100
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-063
TEXAS TRAFFIC AND BARRICADE, LLC (0.20)
TOTAL HIGHWAY MAINTENANCE, LLC (2.57)
DUSTROL, INC. (1.10)
Contract #10213025
Totals4706206.172.004583554.6297.3

CountyCOOKE
HighwayIH 35
From1.4 MI SOUTH OF SPRING CREEK ROAD
To0.2 MI SOUTH OF US 82
CSJ0195-01-119
Proj IDNH 2021(327)
Work TypeWIDEN FREEWAY
 
7.900208432431.1481235156.5038.9
CountyCOOKE
HighwayIH 35
From1.4 MI SOUTH OF SPRING CREEK ROAD
To0.2 MI SOUTH OF US 82
CSJ0195-01-120
Proj IDROW 0195-1-120
Work TypeRIGHT OF WAY
 
7.9001566682.221552235.6899.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-18-21
Work Began06-21-21
Work Completed
Time Computed00-00-00
Contract Working Days1,395
Addl Days Granted0
Working Days Charged446
Percent Time Used31
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0195-01-119
DOUBLE EE CONTRACTORS, LLC (0.01)
BARRICADES UNLIMITED (0.67)
ANTIGO CONSTRUCTION, INC. (0.24)
SOUTHERN CROSS CONTRACTORS, LLC (0.05)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.10)
FORTSON CONTRACTING, INC. (0.58)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.43)
SCOTT DERR PAINTING CO, LLC (0.06)
W.O.E. CONSTRUCTION, INC. (2.24)
TEXAS SHAFTS, INC. (0.67)
OSCAR ORDUNO, INC. (1.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.27)
MONARREZ TRUCKING LLC. (0.00)
DALE BROWN, INC. (0.13)
TIME STRIPING, INC. (0.05)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.17)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
WITHERS CONSTRUCTION, LLC (0.00)
FREIGHT OPERATION SERVICES, LLC, DBA FOS BROKERAGE SERVICES (0.00)
VENUS CONSTRUCTION COMPANY (0.78)
RAY"S THREADING AND FAB SHOP (0.62)
SKAGGS ROAD BORING, INC. (0.15)
HERMANOS STEEL, LLC (0.04)
ZACHRY CONSTRUCTION CORPORATION (0.00)
KHONSU ENTERPRISE LLC (0.36)
H & H CONCRETE ON DEMAND INC (0.56)
TORO BRAVO CONSTRUCTION, LLC (2.69)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21)
POTERE CONSTRUCTION LLC (0.68)
A.E.A. TRANSPORTATION (0.00)
TIM ANTHONY SERVICES, LLC (0.00)
MCRYAN HAULING, INC. (0.00)
Contract #02213201
Totals209999113.361997274.9982787392.1839.3

CountyCLAY
HighwayUS 287
FromNEAR US 82
ToSH 148
CSJ0224-01-061
Proj IDC 224-1-61
Work TypeOVERLAY
 
1.5312016366.652139536.9399.9
Work Order02-15-22
Work Began08-24-22
Work Completed
Time Computed03-17-22
Contract Working Days85
Addl Days Granted0
Working Days Charged44
Percent Time Used51
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0224-01-061
XROADS, L.P. (0.60)
DUSTROL, INC. (8.51)
LOLLAR CONSTRUCTION GROUP LLC (12.29)
PRIMATE CONSTRUCTION, LP (0.80)
SOUTHERN CROSS CONTRACTORS, LLC (4.33)
STRIPING TECHNOLOGY, L.P. (2.59)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.40)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.54)
Contract #01223015
Totals2016366.65174328.372139536.9399.9

CountyARCHER
HighwayUS 281
FromLAKE CREEK ROAD
To1000 FT NORTH OF LITTLE WICHITA RIVER
CSJ0249-03-053
Proj IDC 249-3-53
Work TypeRESTORATION
 
4.1404616373.184462606.3396.6
Work Order12-15-20
Work Began02-02-21
Work Completed
Time Computed01-14-21
Contract Working Days204
Addl Days Granted0
Working Days Charged193
Percent Time Used94
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0249-03-053
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.47)
TOTAL HIGHWAY MAINTENANCE, LLC (2.03)
MARCOM"S MOWING SERVICE, LLC (0.27)
W. S. CONSTRUCTION COMPANY (6.65)
ZACK BURKETT CO. (34.23)
Contract #11203218
Totals4616373.180.004462606.3396.6

CountyARCHER ETC
HighwayUS 281 ETC
FromFM 174
ToST MARY'S ST
CSJ0249-03-055
Proj IDF 2023(183)
Work TypeSEAL COAT
 
9.21910600584.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0249-03-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11223211
Totals10600584.040.000.000.0

CountyCOOKE
HighwayFM 51
FromAT ELM FORK TRINITY RIVER
To.
CSJ0312-01-076
Proj IDBR 2022(425)
Work TypeBRIDGE REPLACEMENT
 
0.1104761917.351995148.3141.8
Work Order05-12-22
Work Began09-06-22
Work Completed
Time Computed06-13-22
Contract Working Days285
Addl Days Granted0
Working Days Charged69
Percent Time Used24
Contractor(s)
INDUS ROAD & BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-076
4-WAY HAULERS, LLC (0.66)
HERMANOS STEEL, LLC (6.40)
MASSEY CONTRACTORS, LLC (3.02)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.34)
FC TRAFFIC CONTROL, INC. (1.01)
STRIPING TECHNOLOGY, L.P. (0.77)
WYLIE DRILLING & DRAINAGE, INC. (3.92)
TEXOP CONSTRUCTION (0.44)
MICA CORPORATION (1.09)
DFW REBAR, INC. (0.20)
Contract #04223009
Totals4761917.35300201.061995148.3141.8

CountyCLAY
HighwaySH 148
FromFM 1883
ToRUSSELL CREEK
CSJ0391-04-030
Proj IDSTP 2022(627)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5543432425.5046156.211.3
CountyZERO COUNTIES
Highway
From
To
CSJ0391-05-021
Proj ID
Work Type
 
0.00322434.480.0
CountyZERO COUNTIES
Highway
From
To
CSJ0391-05-022
Proj ID
Work Type
 
0.0053064.250.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-22
Work Began10-04-22
Work Completed
Time Computed00-00-00
Contract Working Days181
Addl Days Granted0
Working Days Charged35
Percent Time Used19
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0391-04-030
W. S. CONSTRUCTION COMPANY (11.64)
HJC FARMS, INC. (5.12)
TOTAL HIGHWAY MAINTENANCE, LLC (0.38)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.28)
TRP CONSTRUCTION GROUP, LLC (1.61)
Contract #06223218
Totals3432425.50290341.19421654.9412.2

CountyYOUNG
HighwaySH 114
FromSH 79
To0.8 MI WEST OF FM 1769
CSJ0444-01-044
Proj IDF 2023(055)
Work TypeSUPER-2 HIGHWAY
 
10524957.680.000.0
CountyYOUNG
HighwaySH 114
FromSH 114 AT SALT CREEK
To.
CSJ0444-01-046
Proj IDF 2023(207)
Work TypeBRIDGE MAINTENANCE
 
87937.500.000.0
Work Order10-06-22
Work Began00-00-00
Work Completed
Time Computed12-20-22
Contract Working Days275
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0444-01-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09223021
Totals10612895.180.000.000.0

CountyYOUNG
HighwayFM 701
FromFM 701
ToAT CLEAR FORK OF THE BRAZOS RIVER
CSJ0570-03-019
Proj IDBR 2023(333)
Work TypeBRIDGE REPLACEMENT
 
0.1143033426.360.000.0
CountyYOUNG
HighwayFM 701
FromFM 701
ToAT CLEAR FORK BRAZOS RIVER
CSJ0570-03-020
Proj IDBR 1802(482)
Work TypeBRIDGE REPLACEMENT
 
0.1052535575.110.000.0
CountyYOUNG
HighwayFM 1974
FromFM 1974
ToAT CLEAR FORK OF THE BRAZOS RIVER
CSJ2217-01-015
Proj IDBR 2023(334)
Work TypeBRIDGE REPLACEMENT
 
0.0872276443.530.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days336
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INDUS ROAD & BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0570-03-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233211
Totals7845445.000.000.000.0

page 1 | page 2