Monthly Local Let Maintenance Report For Wichita Falls District As Of Jan 10, 2023 Page 1 Of 3

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWICHITA
HighwayIH0044
FromWICHITA FALLS TRAVEL
ToINFORMATION CENTER
CSJ6176-60-001
Proj IDSUP - 617660001
Work TypeGROUNDS MAINTENANCE
 
0.00120489.0412417.6060.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-08
Work Began02-01-08
Work Completed
Time Computed02-01-08
Contract Working Days730
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6176-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02080331
Totals20489.040.0012417.6060.6

CountyWICHITA
HighwayIH0044
FromWICHITA FALLS TRAVEL
ToINFORMATION CENTER
CSJ6176-61-001
Proj IDSUP - 617661001
Work TypeJANITORIAL MAINTENANCE
 
0.00179828.5675390.2794.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-08
Work Began02-01-08
Work Completed
Time Computed02-01-08
Contract Working Days730
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6176-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02080332
Totals79828.560.0075390.2794.4

CountyYOUNG
HighwaySH0016
FromVARIOUS LOCATIONS IN
ToYOUNG COUNTY
CSJ6205-61-001
Proj IDRMC - 620561001
Work TypeROW MOWING
 
0.00137807.2818843.9649.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-10
Work Began06-21-10
Work Completed
Time Computed06-21-10
Contract Working Days26
Addl Days Granted0
Working Days Charged11
Percent Time Used42
Contractor(s)
K & D CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6205-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01100305
Totals37807.280.0018843.9649.8

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATION IN WICHITA
ToARCHER & CLAY COUNTIES
CSJ6205-69-001
Proj IDRMC - 620569001
Work TypeROW MOWING
 
0.00142940.801177.892.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-10
Work Began06-01-10
Work Completed
Time Computed06-08-10
Contract Working Days29
Addl Days Granted0
Working Days Charged1
Percent Time Used3
Contractor(s)
QUALITY TRACTOR SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6205-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01100313
Totals42940.800.001177.892.7

CountyWICHITA
HighwayIH0044
FromGROUNDS MAINT. AT
ToWF TRAVEL INFORMATION CENTER
CSJ6206-43-001
Proj IDSUP - 620643001
Work TypeGROUNDS MAINTENANCE
 
0.00121302.1616460.7677.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-10
Work Began02-01-10
Work Completed
Time Computed02-01-10
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6206-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02100331
Totals21302.160.0016460.7677.2

CountyWICHITA
HighwayIH0044
FromJANITORIAL SERVICES FOR
ToWF TRAVEL INFORMATION CENTER
CSJ6206-44-001
Proj IDSUP - 620644001
Work TypeJANITORIAL MAINTENANCE
 
0.00184882.0078918.4492.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-10
Work Began02-01-10
Work Completed
Time Computed02-01-10
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6206-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02100332
Totals84882.000.0078918.4492.9

CountyWICHITA
HighwayUS0082
FromVARIOUS ROADWAYS IN ARCHER
ToCLAY AND WICHITA COUNTIES
CSJ6213-52-001
Proj IDRMC - 621352001
Work TypeRIGHT OF WAY MOWING
 
0.00131200.002068.757.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-05-10
Work Began08-06-10
Work Completed
Time Computed08-12-10
Contract Working Days20
Addl Days Granted0
Working Days Charged2
Percent Time Used10
Contractor(s)
K & D CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6213-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07100301
Totals31200.000.002068.757.6

CountyCOOKE
HighwayIH0035
FromVARIOUS ROADS IN COOKE, CLAY,ARCHER
ToMONTAGUE,YOUNG,BAYLOR,THROCKMORTON CO.
CSJ6214-17-001
Proj IDRMC - 621417001
Work TypeROUTINE STREET SWEEPING
 
0.00171776.9543008.8659.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-11
Work Began03-08-11
Work Completed
Time Computed03-15-11
Contract Working Days365
Addl Days Granted0
Working Days Charged292
Percent Time Used80
Contractor(s)
CNR GROUND SOLUTIONS
SUBCONTRACTOR(S) FOR CCSJ: 6214-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11100301
Totals71776.950.0043008.8659.9

CountyWICHITA
HighwayUS0082
FromVARIOUS ROADWAYS IN
ToWICHITA COUNTY
CSJ6216-93-001
Proj IDRMC - 621693001
Work TypeRIGHT-OF-WAY MOWING
 
0.00117280.0011330.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-29-10
Work Began11-01-10
Work Completed
Time Computed11-05-10
Contract Working Days10
Addl Days Granted0
Working Days Charged24
Percent Time Used240
Contractor(s)
RED LINE LANDSCAPING & CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6216-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09100301
Totals17280.000.0011330.0099.9

CountyCOOKE
HighwayIH0035
FromGROUNDS MAINTENANCE AT
ToGAINESVILLE TRAVEL INFO CENTER
CSJ6230-54-001
Proj IDSUP - 623054001
Work TypeGROUNDS MAINTENANCE
 
0.00186460.0037990.0043.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-11
Work Began08-01-11
Work Completed
Time Computed08-01-11
Contract Working Days731
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6230-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08110331
Totals86460.000.0037990.0043.9

CountyCOOKE
HighwayIH0035
FromJANITORIAL SERVICES AT
ToGAINESVILLE TRAVEL INFO CENTER
CSJ6230-62-001
Proj IDSUP - 623062001
Work TypeJANITORIAL SERVICES
 
0.001240015.60239304.8199.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-11
Work Began08-01-11
Work Completed
Time Computed08-01-11
Contract Working Days731
Addl Days Granted31
Working Days Charged792
Percent Time Used103
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6230-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08110332
Totals240015.600.00239304.8199.7

CountyCOOKE
HighwayIH0035
FromVARIOUS
To-
CSJ6263-90-001
Proj IDSUP - 626390001
Work TypeJANITORIAL, GROUNDS, LANDSCAPING
 
0.001126800.96105491.16100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-13
Work Began10-01-13
Work Completed08-31-14
Time Computed10-01-13
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6263-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08130332
Totals126800.960.00105491.16100.0

CountyBAYLOR
HighwayUS0082
FromVARIOUS ROADWAYS
ToIN BAYLOR COUNTY
CSJ6377-17-001
Proj IDRMC - 637717001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001147131.50284192.00100.0
Work Order00-00-00
Work Began06-07-21
Work Completed01-02-23
Time Computed06-01-21
Contract Working Days58
Addl Days Granted58
Working Days Charged95
Percent Time Used81
Contractor(s)
TRIPLE T MAINTENANCE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03210301
Totals147131.5072020.00284192.00100.0

CountyYOUNG
HighwayUS0380
FromTXDOT MAINTENANCE OFFICES IN
ToGRAHAM, THROCKMORTON & OLNEY
CSJ6384-98-001
Proj IDSUP - 638498001
Work TypeJANITORIAL MAINTENANCE
 
0.01062050.0039687.1163.9
Work Order00-00-00
Work Began08-03-21
Work Completed
Time Computed08-03-21
Contract Working Days730
Addl Days Granted0
Working Days Charged516
Percent Time Used70
Contractor(s)
WORKQUEST
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6384-98-001
WORK SERVICES CORPORATION (0.00)
Contract #07210330
Totals62050.002160.0039687.1163.9

CountyWICHITA
HighwayFM0369
FromWICHITA FALLS TXDOT DISTRICT HEADQUARTER
ToLOCATED AT 1601 SOUTHWEST PKWY.
CSJ6386-23-001
Proj IDSUP - 638623001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.010113052.0065890.8958.2
Work Order09-01-21
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days731
Addl Days Granted0
Working Days Charged487
Percent Time Used66
Contractor(s)
WORKQUEST
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6386-23-001
WORK SERVICES CORPORATION (0.00)
Contract #09210330
Totals113052.003206.2865890.8958.2

CountyMONTAGUE
HighwayUS0081
FromBOWIE AND NOCONA
ToMAINTENANCE OFFICES
CSJ6391-44-001
Proj IDSUP - 639144001
Work TypeJANITORIAL MAINTENANCE
 
0.01059936.0038629.3864.4
Work Order09-20-21
Work Began09-20-21
Work Completed
Time Computed09-20-21
Contract Working Days731
Addl Days Granted0
Working Days Charged468
Percent Time Used64
Contractor(s)
WORKQUEST
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6391-44-001
FRESH START OF MONROE INC. (0.00)
Contract #09210334
Totals59936.002422.0038629.3864.4

CountyARCHER
HighwaySH0079
FromVARIOUS LOCATIONS IN
ToARCHER COUNTY
CSJ6395-27-001
Proj IDRMC - 639527001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010226267.98217197.9895.9
Work Order00-00-00
Work Began04-27-22
Work Completed
Time Computed04-27-22
Contract Working Days365
Addl Days Granted365
Working Days Charged249
Percent Time Used34
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220304
Totals226267.980.00217197.9895.9

CountyCLAY
HighwayUS0287
FromVARIOUS LOCATION IN
ToCLAY COUNTY
CSJ6395-28-001
Proj IDRMC - 639528001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010288002.44167301.7058.0
Work Order00-00-00
Work Began04-27-22
Work Completed
Time Computed04-27-22
Contract Working Days365
Addl Days Granted365
Working Days Charged249
Percent Time Used34
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220305
Totals288002.440.00167301.7058.0

CountyTHROCKMORTON
HighwayUS0183
FromVARIOUS LOCATIONS IN
ToTHROCKMORTON COUNTY
CSJ6395-30-001
Proj IDRMC - 639530001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.01098992.0017980.0018.1
Work Order05-01-22
Work Began04-27-22
Work Completed
Time Computed04-27-22
Contract Working Days365
Addl Days Granted0
Working Days Charged218
Percent Time Used59
Contractor(s)
NOMAD MEDIAN SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6395-30-001
MARLANE CONSTRUCTION, LLC (41.69)
Contract #02220302
Totals98992.000.0017980.0018.1

CountyWILBARGER
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToWILBARGER COUNTY
CSJ6395-31-001
Proj IDRMC - 639531001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010253280.50247036.5097.5
Work Order00-00-00
Work Began04-27-22
Work Completed
Time Computed04-27-22
Contract Working Days365
Addl Days Granted365
Working Days Charged249
Percent Time Used34
Contractor(s)
TRIPLE T MAINTENANCE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220303
Totals253280.5044485.00247036.5097.5

page 1 | page 2 | page 3