Monthly State Let Maintenance Report For Wichita Falls District As Of Nov 10, 2023 Page 1 Of 2

Last Update: Friday, November 10, 2023
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyARCHER
HighwaySH0079
FromVARIOUS LOCATIONS IN
ToARCHER, COOKE, AND WILBARGER COUNTIES
CSJ6377-32-001
Proj IDBPM - 637732001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010758085.691378703.17100.0
Work Order00-00-00
Work Began10-04-21
Work Completed08-31-23
Time Computed10-04-21
Contract Working Days137
Addl Days Granted72
Working Days Charged273
Percent Time Used130
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6377-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214016
Totals758085.690.001378703.17100.0

CountyWICHITA
HighwayUS0082
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6383-35-001
Proj IDRMC - 638335001
Work TypePAVEMENT MARKINGS
 
0.010717366.001825805.28100.0
Work Order00-00-00
Work Began09-01-21
Work Completed10-25-23
Time Computed09-01-21
Contract Working Days365
Addl Days Granted386
Working Days Charged751
Percent Time Used100
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6383-35-001
STRIPE-A-ZONE, LLC (3.79)
Contract #07214216
Totals717366.0012810.001825805.28100.0

CountyMONTAGUE
HighwayUS0082
FromVARIOUS LOCATION IN
ToMONTAGUE COUNTY
CSJ6395-29-001
Proj IDRMC - 639529001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010310778.00348924.4999.9
Work Order00-00-00
Work Began04-27-22
Work Completed
Time Computed04-27-22
Contract Working Days365
Addl Days Granted365
Working Days Charged553
Percent Time Used75
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6395-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224021
Totals310778.000.00348924.4999.9

CountyCOOKE
HighwayIH0035
FromVARIOUS LOCATIONS
ToTHROUGHOUT COOKE COUNTY
CSJ6395-77-001
Proj IDRMC - 639577001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010304478.00449948.5099.9
Work Order00-00-00
Work Began04-27-22
Work Completed
Time Computed04-27-22
Contract Working Days365
Addl Days Granted365
Working Days Charged553
Percent Time Used75
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6395-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224026
Totals304478.000.00449948.5099.9

CountyCLAY
HighwayUS0082
FromBPM AT VARIOUS PLACES
ToTHROUGHOUT THE DISTRICT
CSJ6401-97-001
Proj IDBPM - 640197001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.0101243840.00879936.5770.8
Work Order00-00-00
Work Began10-24-22
Work Completed
Time Computed10-24-22
Contract Working Days182
Addl Days Granted0
Working Days Charged184
Percent Time Used101
Contractor(s)
TALBRAN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6401-97-001
GARRET SHIELDS INFRASTRUCTURE (0.00)
Contract #06224618
Totals1243840.0028018.80879936.5770.8

CountyWICHITA
HighwayUS0287
FromWICHITA COUNTY
ToVARIOUS ROADWAYS
CSJ6421-33-001
Proj IDRMC - 642133001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010298575.0078791.0026.3
Work Order00-00-00
Work Began05-16-23
Work Completed
Time Computed05-16-23
Contract Working Days85
Addl Days Granted0
Working Days Charged81
Percent Time Used95
Contractor(s)
MTS BRUSH HOGGING DOZER AND LAWN LLC
SUBCONTRACTOR(S) FOR CCSJ: 6421-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234211
Totals298575.0011052.0078791.0026.3

CountyCOOKE
HighwayFM3164
FromVARIOUS ROADWAYS
ToTHROUGHOUT THE DISTRICT
CSJ6425-80-001
Proj IDRMC - 642580001
Work TypeSEAL COAT
 
0.0102382691.002480452.1499.9
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days36
Addl Days Granted0
Working Days Charged39
Percent Time Used108
Contractor(s)
NORTHEASTERN PAVERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6425-80-001
BARRICADES PLUS, LLC (2.24)
CENTERLINE TECHNOLOGIES, LLC (20.70)
Contract #12224224
Totals2382691.0015750.002480452.1499.9

CountyWICHITA
HighwayUS0082
FromDEBRIS REMOVAL IN WICHITA, CLAY
ToCOOKE, MONTAGUE & WILBARGER COUNTIES
CSJ6428-36-001
Proj IDRMC - 642836001
Work TypeDEBRIS REMOVAL
 
0.010531600.00396300.0074.5
Work Order00-00-00
Work Began04-03-23
Work Completed
Time Computed04-03-23
Contract Working Days275
Addl Days Granted0
Working Days Charged212
Percent Time Used77
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6428-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234026
Totals531600.0033480.00396300.0074.5

CountyWICHITA
HighwayIH0044
FromVARIOUS ROADWAYS THROUGHOUT
ToTHE WICHITA FALLS DISTRICT
CSJ6428-38-001
Proj IDRMC - 642838001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010482000.0040100.408.3
Work Order09-01-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6428-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234430
Totals482000.0032454.0040100.408.3

CountyWICHITA
HighwayUS0287
FromVARIOUS ROADWAYS THROUGHOUT
ToTHE WICHITA FALLS DISTRICT
CSJ6428-40-001
Proj IDRMC - 642840001
Work TypePAVEMENT MARKINGS
 
0.0101342430.5034622.492.5
Work Order00-00-00
Work Began09-27-23
Work Completed
Time Computed09-27-23
Contract Working Days366
Addl Days Granted0
Working Days Charged35
Percent Time Used9
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6428-40-001
STRIPING TECHNOLOGY, L.P. (93.37)
SURFACE PREPARATION TECHNOLOGIES, LLC (8.80)
Contract #08234047
Totals1342430.5034622.4934622.492.5

CountyWICHITA
HighwayUS0287
FromVARIOUS ROADWAYS
ToTHROUGHOUT WFS DISTRICT
CSJ6428-44-001
Proj IDRMC - 642844001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101681104.00178395.0010.6
Work Order09-01-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6428-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234627
Totals1681104.00117932.00178395.0010.6

CountyARCHER
HighwayFM0368
FromVARIOUS BRIDGES
ToDISTRICTWIDE
CSJ6436-53-001
Proj IDBPM - 643653001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.0101834460.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-06-23
Work Completed
Time Computed11-06-23
Contract Working Days187
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PATHFIELD INVESTMENTS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6436-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234048
Totals1834460.000.000.000.0

CountyWICHITA
HighwayUS0287
FromVARIOUS COUNTIES
ToWICHITA FALLS DISTRICT
CSJ6436-78-001
Proj IDMMC - 643678001
Work TypeAGGREGATE
 
0.010674333.30351240.8652.0
Work Order00-00-00
Work Began05-23-23
Work Completed
Time Computed05-23-23
Contract Working Days180
Addl Days Granted0
Working Days Charged162
Percent Time Used90
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6436-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234022
Totals674333.300.00351240.8652.0

CountyWICHITA
HighwayUS0287
FromVARIOUS COUNTIES
ToWICHITA FALLS DISTRICT
CSJ6437-93-001
Proj IDMMC - 643793001
Work TypeEMULSION
 
0.010886650.00562577.8563.4
Work Order00-00-00
Work Began05-12-23
Work Completed
Time Computed05-12-23
Contract Working Days180
Addl Days Granted0
Working Days Charged173
Percent Time Used96
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6437-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234023
Totals886650.0034802.17562577.8563.4

CountyCLAY
HighwayUS0287
FromVARIOUS LOCATIONS
ToCLAY COUNTY
CSJ6437-99-001
Proj IDMMC - 643799001
Work TypeHOT MIX
 
0.010910150.00440190.6048.3
Work Order00-00-00
Work Began05-30-23
Work Completed
Time Computed05-30-23
Contract Working Days180
Addl Days Granted0
Working Days Charged155
Percent Time Used86
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 6437-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234024
Totals910150.000.00440190.6048.3

CountyCOOKE
HighwayUS0082
FromVARIOUS LOCATIONS
ToCOOKE COUNTY
CSJ6438-03-001
Proj IDMMC - 643803001
Work TypeHOT MIX
 
0.010828900.00476923.2857.5
Work Order00-00-00
Work Began05-30-23
Work Completed
Time Computed05-30-23
Contract Working Days180
Addl Days Granted0
Working Days Charged155
Percent Time Used86
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 6438-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234025
Totals828900.000.00476923.2857.5

CountyMONTAGUE
HighwayUS0082
FromVARIOUS LOCATIONS
ToMONTAGUE COUNTY
CSJ6438-06-001
Proj IDMMC - 643806001
Work TypeHOT MIX
 
0.0101119757.50657802.2858.7
Work Order00-00-00
Work Began05-30-23
Work Completed
Time Computed05-30-23
Contract Working Days180
Addl Days Granted0
Working Days Charged155
Percent Time Used86
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 6438-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234220
Totals1119757.5048255.60657802.2858.7

CountyTHROCKMORTON
HighwayUS0183
FromVARIOUS LOCATIONS
ToTHROCKMORTON COUNTY
CSJ6438-07-001
Proj IDMMC - 643807001
Work TypeHOT MIX
 
0.010429148.50691367.1799.9
Work Order00-00-00
Work Began05-23-23
Work Completed
Time Computed05-23-23
Contract Working Days180
Addl Days Granted0
Working Days Charged162
Percent Time Used90
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6438-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234221
Totals429148.50186824.94691367.1799.9

CountyYOUNG
HighwayUS0380
FromVARIOUS LOCATIONS
ToYOUNG COUNTY
CSJ6438-09-001
Proj IDMMC - 643809001
Work TypeHOT MIX
 
0.010464125.001174617.6399.9
Work Order00-00-00
Work Began05-23-23
Work Completed
Time Computed05-23-23
Contract Working Days180
Addl Days Granted0
Working Days Charged162
Percent Time Used90
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6438-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234222
Totals464125.00251584.351174617.6399.9

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS
ToWICHITA COUNTY
CSJ6441-55-001
Proj IDMMC - 644155001
Work TypeHOT MIX
 
0.010851094.000.000.0
Work Order00-00-00
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days180
Addl Days Granted0
Working Days Charged139
Percent Time Used77
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6441-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234028
Totals851094.000.000.000.0

page 1 | page 2