Monthly State Let Construction Report For Yoakum District As Of Jan 10, 2023 Page 1 Of 8

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGONZALES ETC
HighwayUA 90 ETC
FromSH 80
To0.25 MI E OF CR 143
CSJ0025-05-024
Proj IDF 2023(225)
Work TypeSEAL COAT
 
309.85718739124.790.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-05-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11223205
Totals18739124.790.000.000.0

CountyFAYETTE
HighwayUS 90
From0.12 MILES WEST OF SH 95
ToELM ST IN CITY OF FLATONIA
CSJ0026-02-034
Proj IDSTP 2021(586)
Work TypeRESTORATION
 
0.8072724321.522705035.0298.8
Work Order11-04-21
Work Began12-27-21
Work Completed
Time Computed02-02-22
Contract Working Days175
Addl Days Granted0
Working Days Charged163
Percent Time Used93
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-02-034
BATTERSON, LLP (1.17)
INTERSTATE BARRICADES & MARKINGS, INC. (3.09)
RUCOBA & MAYA CONSTRUCTION, LLC (5.35)
Contract #06213018
Totals2724321.524804.502705035.0298.8

CountyFAYETTE ETC
HighwayUS 90 ETC
FromMARKET STREET(IN FLATONIA)
To0.4 MI E OF ELM STREET
CSJ0026-02-037
Proj IDF 2021(544)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
4.8362774624.510.000.0
Work Order01-20-22
Work Began00-00-00
Work Completed
Time Computed04-21-22
Contract Working Days210
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0026-02-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12213211
Totals2774624.510.000.000.0

CountyFAYETTE
HighwayUS 90
FromAT MIDDLE CREEK
ToSTR # 0026-03-028
CSJ0026-03-042
Proj IDBR 2017(318)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.288831842.19814791.3299.9
Work Order01-10-17
Work Began03-03-17
Work Completed
Time Computed04-10-17
Contract Working Days60
Addl Days Granted0
Working Days Charged121
Percent Time Used201
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-042
DELGADO"S CONSTRUCTION (60.07)
EGGEMEYER LAND CLEARING, LLC (2.87)
ROADWAY SPECIALTIES, INC. (3.88)
FLASHER EQUIPMENT COMPANY (0.39)
PAVEMENT MARKINGS INC. (0.94)
Contract #12163022
Totals831842.190.00814791.3299.9

CountyCOLORADO ETC
HighwayUS 90 ETC
FromAT BS 71-F IN COLUMBUS
To.
CSJ0026-06-032
Proj IDF 2022(609)
Work TypeTRAFFIC CONTROL DEVICES
 
0.2022805099.5090428.003.2
Work Order09-28-22
Work Began00-00-00
Work Completed
Time Computed12-27-22
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-032
FLASHER EQUIPMENT COMPANY (2.74)
Contract #06223225
Totals2805099.5090428.0090428.003.2

CountyCOLORADO
HighwayUS 90
FromFM 806
ToFRONT STREET
CSJ0026-06-034
Proj IDF 2022(489)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.503779897.200.000.0
CountyMATAGORDA
HighwaySH 35
FromBAYOU DRIVE
To12 TH STREET
CSJ0179-04-100
Proj IDF 2022(490)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
4.4002077545.80225209.1010.8
Work Order06-09-22
Work Began00-00-00
Work Completed
Time Computed09-07-22
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-034
PBJ CONSTRUCTION (5.82)
HIGHWAY 1 LLC (1.73)
LONESTAR TRAFFIC SAFETY, LLC (0.60)
Contract #05223008
Totals2857443.000.00225209.107.8

CountyCOLORADO ETC
HighwayUS 90 ETC
FromFM 806
To0.056 MI W OF FRONT ST.
CSJ0026-06-035
Proj IDF 2022(093)
Work TypeSEAL COAT
 
314.60116624783.2014845548.1589.2
Work Order12-16-21
Work Began05-03-22
Work Completed
Time Computed06-01-22
Contract Working Days75
Addl Days Granted0
Working Days Charged72
Percent Time Used96
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-035
INTERSTATE BARRICADES & MARKINGS, INC. (1.23)
CENTERLINE TECHNOLOGIES, LLC (14.48)
LINEAR TRAFFIC MARKINGS LLC (1.13)
Contract #11213201
Totals16624783.200.0014845548.1589.2

CountyCOLORADO
HighwayUS 90
FromAT COLORADO RIVER BRIDGE
ToSTR # 0027-01-001
CSJ0027-01-044
Proj IDBR 2019(850)
Work TypeBRIDGE REPLACEMENT
 
0.3648244674.8810913983.4099.9
Work Order06-13-19
Work Began08-05-19
Work Completed
Time Computed08-05-19
Contract Working Days405
Addl Days Granted0
Working Days Charged360
Percent Time Used88
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0027-01-044
SEMPER STRIPING LLC (0.02)
HB FARMER FOUNDATION, LLC (12.51)
MCL CONTRACTING, LLC (0.81)
DORAN STEEL, INC. (0.93)
A1 EROSION CONTROL (0.37)
CHOCTAW ERECTORS, INC. (8.27)
WILLOW CITY SIGN & RAIL, INC. (1.56)
GMJ PAVING CO. (2.99)
DORAN STEEL, INC. (0.54)
EAST - TEX PIPE AND FAB LLC (0.56)
PRIMATE CONSTRUCTION, LP (0.09)
JB PINNACLE GROUP, LLC (0.79)
PEREZ CONSTRUCTION CO. (0.48)
BATTERSON, LLP (0.63)
CRAIG & HEIDT, INC. (1.58)
Contract #05193010
Totals8244674.8872210.0010913983.4099.9

CountyCOLORADO
HighwayUS 90A
FromFM 102 IN EAGLE LAKE
ToWHARTON COUNTY LINE
CSJ0027-03-071
Proj IDSTP 1702(426)
Work TypeCONSTRUCT SUPER 2 LANES
 
5.0284487326.994851429.9999.9
Work Order08-11-17
Work Began10-25-17
Work Completed
Time Computed11-09-17
Contract Working Days160
Addl Days Granted0
Working Days Charged159
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0027-03-071
AREA WIDE PROTECTIVE, INC. (0.26)
D. I. J. CONSTRUCTION, INC. (1.88)
D&S TEXAS ICON CONSTRUCTION (0.35)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.27)
RIOS TRUCKING CO. (1.40)
STRIPE-A-ZONE, INC. (0.27)
Contract #06173243
Totals4487326.990.004851429.9999.9

CountyCOLORADO ETC
HighwayFM 102 ETC
FromDOWNTOWN EAGLE LAKE
ToUS 90A
CSJ0027-03-073
Proj IDSTP 2020(052)
Work TypeOVERLAY
 
12.3403987940.974006810.6699.9
Work Order04-07-20
Work Began07-06-20
Work Completed
Time Computed04-23-20
Contract Working Days120
Addl Days Granted0
Working Days Charged108
Percent Time Used90
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0027-03-073
STRIPE LINES, INC. (4.36)
CAPSTONE TRUCKING (0.00)
A.J.J.A . TRUCKING, INC. (0.00)
Contract #09193006
Totals3987940.970.004006810.6699.9

CountyWHARTON
HighwayUA 90
From2.58 MI W OF FM 1164
ToSH 60
CSJ0027-04-041
Proj IDSTP 1902(164)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7.341496857.15640136.3199.9
CountyWHARTON
HighwayFM 640
FromFM 1161
ToFM 102
CSJ1260-03-013
Proj IDSTP 1902(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.014527561.27460838.6187.3
CountyWHARTON
HighwayFM 1161
FromFM 102
ToSH 60
CSJ1303-01-018
Proj IDSTP 1902(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.3991138794.901073003.7394.2
CountyMATAGORDA
HighwayFM 2540
FromSH 35
ToFM 457
CSJ2525-01-017
Proj IDSTP 1902(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.301448295.64373640.1883.3
Work Order10-21-19
Work Began11-20-19
Work Completed
Time Computed01-19-20
Contract Working Days210
Addl Days Granted0
Working Days Charged291
Percent Time Used138
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0027-04-041
A K FUQUAY CONSTRUCTION (2.24)
AREA WIDE PROTECTIVE, INC. (0.98)
RUCOBA & MAYA CONSTRUCTION, LLC (62.13)
TRAFFIC SIGNS & LINES, LLC (1.76)
Contract #09193204
Totals2611508.960.002547618.8399.9

CountyWHARTON ETC
HighwayUS 90A ETC
FromCOLORADO C/L
ToSH 60
CSJ0027-04-042
Proj IDSTP 2021(545)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
30.9503775419.00861456.1422.8
Work Order09-29-21
Work Began03-31-22
Work Completed
Time Computed12-28-21
Contract Working Days300
Addl Days Granted0
Working Days Charged149
Percent Time Used49
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0027-04-042
CONCAN SERVICES LLC (4.01)
GV LANDSCAPE AND CONSTRUCTION LLC (7.38)
Contract #08213232
Totals3775419.0035224.00861456.1422.8

CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-085
Proj IDC 88-5-85
Work TypeCONSTRUCT FRONTAGE ROADS
 
2.76927884764.5033057730.7799.9
CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-099
Proj IDROW 88-5-99
Work TypeUTILITY ONLY
 
3.329708858.20655277.2092.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-19-18
Work Began09-17-18
Work Completed
Time Computed00-00-00
Contract Working Days600
Addl Days Granted172
Working Days Charged783
Percent Time Used101
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-085
AREA WIDE PROTECTIVE, INC. (0.02)
THIRD COAST SERVICES LLC (5.43)
ANGEL BROTHERS HOLDINGS CORP. (28.20)
ADCOCK 4 INVESTMENTS, LLC (4.34)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.59)
TITO"S TRUCKING & SONS, LLC (0.00)
ROADWAY SPECIALTIES, INC. (1.60)
INSITUFORM TECHNOLOGIES, LLC (0.68)
MVA CONSTRUCTION LLC (0.00)
AIMS COMPANIES (0.03)
BORTUNCO (0.22)
FARR FOUNDATION, INC. (0.30)
HIGHWAY BARRICADES AND SERVICES, LLC (0.40)
MONTALVO BRIDGE SYSTEMS, LLC (0.11)
DUSTROL, INC. (1.14)
WEBER-BALKE FOUNDATION COMPANY, INC (0.40)
CURB PLANET INC. (0.05)
AARON CONCRETE CONTRACTORS, L.P. (1.52)
ROYAL REBAR (0.05)
PRIMATE CONSTRUCTION, LP (0.02)
TEXAS MATERIALS GROUP, INC. (0.87)
ROADWAY CONSTRUCTION, LLC (0.63)
WEST TEXAS ROCK RESOURCES, LLC (0.01)
Contract #05183003
Totals28593622.700.0033713007.9799.9

CountyVICTORIA
HighwayUS 59
FromUS 87
ToSH 185
CSJ0088-05-098
Proj IDC 88-5-98
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
1.13613531313.255997117.5144.3
Work Order09-21-21
Work Began04-07-22
Work Completed
Time Computed12-20-21
Contract Working Days360
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-098
BEAVER CONTRACTORS, LLC (7.48)
HB FARMER FOUNDATION, LLC (1.49)
HIGHWAY BARRICADES AND SERVICES, LLC (1.61)
ROADWAY SPECIALTIES, INC. (0.68)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.80)
THIRD COAST SERVICES LLC (8.19)
BARRICADES UNLIMITED (0.18)
ANCORTEX, INC. (1.92)
PBX BRIDGE COMPANY (1.07)
TORO BRAVO CONSTRUCTION, LLC (0.03)
TORO BRAVO CONSTRUCTION, LLC (0.07)
Contract #08213214
Totals13531313.25252519.305997117.5144.3

CountyWHARTON
HighwayUS 59
FromLP 524 N. OF HILLJE (NB LANES ONLY)
To0.130 MI.N.OF FM 647(NB LANES ONLY)
CSJ0089-06-088
Proj IDNH 1702(485)
Work TypeACP OVERLAY
 
17.2038161719.848623991.3499.9
Work Order08-16-17
Work Began01-08-18
Work Completed
Time Computed11-14-17
Contract Working Days84
Addl Days Granted98
Working Days Charged184
Percent Time Used101
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-088
BATTERSON,LLP (3.59)
DEVTEX INC. (2.18)
A BROTHERS MILLING, LLC (1.99)
WEST TEXAS RUMBLE STRIP (0.17)
Contract #07173210
Totals8161719.840.008623991.3499.9

CountyWHARTON
HighwayUS 59
FromBU 59 NORTH OF ELCAMPO
ToSH 71
CSJ0089-07-146
Proj IDNH 2019(437)
Work TypeCONSTRUCT FRONTAGE ROADS
 
3.16834757444.7635814896.2599.9
Work Order02-20-19
Work Began06-20-19
Work Completed
Time Computed05-21-19
Contract Working Days450
Addl Days Granted29
Working Days Charged486
Percent Time Used101
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-07-146
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (2.54)
ROADWAY CONSTRUCTION, LLC (0.74)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.34)
ANGEL BROTHERS HOLDINGS CORP. (10.74)
A BROTHERS MILLING, LLC (0.93)
SOUTHERN CRUSHED CONCRETE LLC (0.84)
BATTERSON,LLP (1.28)
JMHP, INC. (0.34)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28)
MESA ROD BUSTERS, INC. (0.05)
MONTALVO BRIDGE SYSTEMS, LLC (0.14)
ROADWAY SPECIALTIES, INC. (0.41)
TITO"S TRUCKING & SONS, LLC (0.00)
CURB PLANET INC. (0.05)
PRIMATE CONSTRUCTION, LP (0.02)
PRV SERVICES, INC. (0.00)
ALLGAYER, INC. (0.00)
SCOTT DERR PAINTING CO, LLC (0.30)
HODGES BROTHERS, INC. (0.00)
AARON CONCRETE CONTRACTORS, L.P. (0.81)
TEXAS MATERIALS GROUP, INC. (10.74)
WEST TEXAS ROCK RESOURCES, LLC (0.01)
Contract #01193002
Totals34757444.7616038.9135814896.2599.9

CountyWHARTON ETC
HighwayUS 59 ETC
FromFM 961
ToBU 59-S
CSJ0089-07-155
Proj IDSTP 2020(849)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
41.5521842177.411913079.2099.9
Work Order07-07-20
Work Began09-02-20
Work Completed
Time Computed10-05-20
Contract Working Days180
Addl Days Granted0
Working Days Charged103
Percent Time Used57
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-07-155
STRIPE LINES, INC. (1.23)
SAFETY COP, LLC (0.00)
Contract #05203016
Totals1842177.410.001913079.2099.9

CountyWHARTON
HighwayUS 59
From0.74 MI NORTH OF FM 960
To0.20 MI SOUTH OF FM 961
CSJ0089-07-159
Proj IDF 2022(237)
Work TypeOVERLAY
 
6.6608528160.866835357.5780.3
Work Order01-10-22
Work Began05-04-22
Work Completed
Time Computed05-02-22
Contract Working Days90
Addl Days Granted0
Working Days Charged105
Percent Time Used116
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-07-159
DUSTROL, INC. (1.85)
BATTERSON, LLP (0.15)
SCR CONSTRUCTION CO., INC. (0.00)
WEST TEXAS ROCK RESOURCES, LLC (0.14)
SCR CIVIL CONSTRUCTION, LLC (0.73)
Contract #11213014
Totals8528160.86759808.786835357.5780.3

CountyWHARTON
HighwayUS 59
FromFORT BEND C/L
To0.83 MILES SOUTH OF SH 60
CSJ0089-08-098
Proj IDNH 2020(496)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
168669295.33101830591.8060.3
Work Order02-21-20
Work Began03-11-20
Work Completed
Time Computed05-21-20
Contract Working Days1,063
Addl Days Granted5
Working Days Charged529
Percent Time Used49
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-08-098
BUYERS BARRICADES, INC. (0.08)
HIGHWAY 1 LLC (0.01)
MESA ROD BUSTERS, INC. (7.12)
SCOTT DERR PAINTING CO, LLC (0.01)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.50)
STRIPE-A-ZONE, INC. (0.01)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18)
QUALITY TURF FARMS, L.C. (0.45)
PROFESSIONAL TRAFFIC CONTROL LLC (0.64)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.06)
LONG LEGACY ENTERPRISES, LLC (0.00)
BUYERS BARRICADES HOUSTON, LLC (0.08)
TEXAS CURB CUT (0.00)
TDH BUILDERS, LLC (0.01)
WALLER COUNTY ELECTRIC, INC. (0.01)
KELLER NORTH AMERICA, INC. (0.04)
TEXAS MATERIALS GROUP, INC. (0.45)
SWEEPING CORPORATION OF AMERICA, LLC (0.08)
Contract #01203201
Totals168669295.331389361.75101830591.8060.3

CountyWHARTON
HighwaySH 60
FromUS 59
ToFM 1301
CSJ0089-10-026
Proj IDF 2023(060)
Work TypeOVERLAY
 
4.8401891288.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-09-22
Work Began00-00-00
Work Completed
Time Computed05-01-23
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-10-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10223208
Totals1891288.420.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8