Monthly State Let Construction Report For Abilene District As Of Nov 10, 2024 Page 1 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayIH 20
FromWEST END OF SANDY DRAW BRIDGE
ToMITCHELL COUNTY (EB LANES)
CSJ0005-06-126
Proj IDC 5-6-126
Work TypeOVERLAY
 
16.0647152987.396261384.1087.5
Work Order07-24-24
Work Began09-09-24
Work Completed
Time Computed08-23-24
Contract Working Days108
Addl Days Granted0
Working Days Charged36
Percent Time Used33
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-126
CHEROKEE SERVICES (0.34)
CONTRACTORS SERVICE, LTD. (0.51)
FLAT LINE, INC. (2.27)
HJC FARMS, INC. (9.36)
INNOVATIVE ROADWAY SOLUTIONS, LLC (4.85)
TEXOP CONSTRUCTION (1.73)
Contract #05243212
Totals7152987.391829068.806261384.1087.5

CountyMITCHELL
HighwayIH 20
From0.40 MILE EAST OF FM 644
ToNEAR CR 424
CSJ0006-01-106
Proj IDF 2025(157)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1243855.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROADWAY SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-01-106
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243222
Totals1243855.770.000.000.0

CountyMITCHELL
HighwayIH 20
FromCOLORADO CITY EAST CITY LIMITS
ToNOLAN COUNTY
CSJ0006-01-107
Proj IDF 2024(169)
Work TypeOVERLAY
 
10261309.2410557725.0999.9
Work Order01-17-24
Work Began06-17-24
Work Completed
Time Computed02-16-24
Contract Working Days88
Addl Days Granted0
Working Days Charged81
Percent Time Used92
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-01-107
CONTRACTORS SERVICE, LTD. (0.36)
DOUBLE A CONTRACTING, L.P. (2.42)
HJC FARMS, INC. (3.55)
PRIMATE CONSTRUCTION, LP (1.55)
TEXOP CONSTRUCTION (2.27)
WEST TEXAS ROCK RESOURCES, LLC (0.38)
Contract #10233206
Totals10261309.24213723.3910557725.0999.9

CountyNOLAN
HighwayIH 20
FromEAST OF CR 111
ToWEST OF LP 170
CSJ0006-02-114
Proj IDC 6-2-114
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
6.290115985812.19101897172.4083.8
CountyNOLAN
HighwayIH 20
FromEAST OF CR 111
ToWEST OF LP 170
CSJ0006-02-123
Proj IDNH 2B20(091)
Work TypeRIGHT OF WAY
 
6.290998587.00998587.0099.9
Work Order09-15-22
Work Began01-03-23
Work Completed
Time Computed11-14-22
Contract Working Days829
Addl Days Granted0
Working Days Charged450
Percent Time Used54
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-114
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.03)
FUSION COMMUNICATIONS, LLC (0.08)
HB FARMER FOUNDATION, LLC (1.85)
JVH4 SERVICES, LLC (0.33)
MICA CORPORATION (1.88)
MICA CORPORATION (1.38)
TORO BRAVO CONSTRUCTION, LLC (0.71)
WILLIS ELECTRIC CO., LP (3.49)
DK CONTRACTING, LLC (0.19)
PINNACLE GRINDING AND GROOVING LLC (0.00)
TEX OP CONSTRUCTION, LP (0.27)
CHOCTAW ERECTORS, INC. (0.45)
SOUTHEAST GRINDING AND GROOVING LLC (0.03)
BARRICADES UNLIMITED (1.38)
CB SERVICES, INC. (0.21)
CRANE SERVICES, INC. (0.27)
DALLAS LITE AND BARRICADE, INC. (0.44)
DUSTIN ALLEN, INC. (0.27)
TORO BRAVO CONSTRUCTION, LLC (0.08)
BRUNDAGE-BONE (0.16)
NOBLES ROAD CONSTRUCTION, INC. (14.70)
BLACKWELL WATER WELL SERVICE INC. (0.06)
H&P BORING SERVICES, LLC (0.11)
MAKIN" IT MOVE TRANSPORT,LLC (2.33)
TS CONSTRUCTION (0.02)
TRP CONSTRUCTION GROUP, LLC (0.37)
C.B. SERVICES, INC. (0.21)
J. H. ODEN CONTRACTING COMPANY (0.16)
TORO BRAVO CONSTRUCTION, LLC (0.01)
Contract #08223202
Totals116984399.197397133.31102895759.4084.0

CountyNOLAN
HighwayIH 20
FromSFR EB EXIT TO HOPKINS RD INTERSECTION
ToNFR WB EXIT
CSJ0006-02-130
Proj IDC 6-2-130
Work TypeREHABILITATION OF EXISTING ROAD
 
0.4446255551.502709738.8543.3
Work Order06-19-24
Work Began09-05-24
Work Completed
Time Computed08-18-24
Contract Working Days66
Addl Days Granted0
Working Days Charged37
Percent Time Used56
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-130
CONTRACTORS SERVICE, LTD. (1.08)
Contract #05243216
Totals6255551.50941232.052709738.8543.3

CountyNOLAN
HighwayIH 20
FromFROM 0.7 MILES EAST OF CR 226
To1.9 MILES EAST OF CR 226
CSJ0006-03-121
Proj IDSTP 2000(401)TP
Work TypeSAFETY REST AREA
 
1.34034593730.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days324
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-03-121
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243205
Totals34593730.020.000.000.0

CountyTAYLOR
HighwayIH 20
FromNOLAN COUNTY LINE
ToNEAR WELLS LANE (WB)
CSJ0006-04-080
Proj IDF 2024(063)
Work TypeOVERLAY
 
13.4356846269.337059882.2999.9
CountyTAYLOR
HighwayIH 20
FromNOLAN COUNTY LINE
ToNEAR WELLS LANE
CSJ0006-04-084
Proj IDF 2024(063)
Work TypeOVERLAY
 
5259462.465456013.6399.9
Work Order10-23-23
Work Began02-22-24
Work Completed
Time Computed11-22-23
Contract Working Days142
Addl Days Granted14
Working Days Charged155
Percent Time Used99
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-04-080
MAR-ZAP CONSTRUCTION, LLC (3.75)
LINEAR TRAFFIC MARKINGS LLC (0.12)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.13)
MURRAY CONSTRUCTION (0.44)
STRAIGHT LINE SAWING & SEALING, INC. (0.70)
WEST TEXAS ROCK RESOURCES, LLC (0.12)
Contract #09233209
Totals12105731.79976772.8012515895.9299.9

CountyTAYLOR
HighwayFM 18
FromSH 36
ToCALLAHAN CO LINE
CSJ0006-10-011
Proj IDF 2B24(019)
Work TypeOVERLAY
 
3.8204570547.0015000.000.3
Work Order07-16-24
Work Began00-00-00
Work Completed
Time Computed09-14-24
Contract Working Days110
Addl Days Granted0
Working Days Charged10
Percent Time Used9
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-10-011
CONTRACTORS SERVICE, LTD. (0.35)
PINNACLE GRINDING AND GROOVING LLC (0.46)
FLAT LINE, INC. (2.60)
HJC FARMS, INC. (5.97)
Contract #05243021
Totals4570547.0015000.0015000.000.3

CountyNOLAN
HighwaySH 70
FromSH 70
ToBI 20 BRIDGE REPLACEMENT
CSJ0006-15-038
Proj IDBR 2024(662)
Work TypeBRIDGE REPLACEMENT
 
8441703.00522000.006.1
Work Order07-18-24
Work Began10-21-24
Work Completed
Time Computed09-16-24
Contract Working Days166
Addl Days Granted0
Working Days Charged5
Percent Time Used3
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-15-038
NOBLES ROAD CONSTRUCTION, INC. (5.18)
Contract #06243019
Totals8441703.00522000.00522000.006.1

CountyCALLAHAN
HighwayIH 20
FromAPPROX 0.3 MI EAST OF MEXIA CREEK
ToEASTLAND CO LINE
CSJ0007-02-051
Proj IDC 7-2-51
Work TypeOVERLAY
 
10411766.900.000.0
Work Order07-16-24
Work Began00-00-00
Work Completed
Time Computed09-14-24
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-02-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05243016
Totals10411766.900.000.000.0

CountySTONEWALL
HighwayUS 83
FromKING COUNTY LINE
ToUS 380
CSJ0032-07-029
Proj IDSTP 1302(057)
Work TypeSUPER-2 HIGHWAY
 
17.54319299562.0617583941.6491.1
Work Order02-16-22
Work Began04-14-22
Work Completed
Time Computed04-14-22
Contract Working Days432
Addl Days Granted10
Working Days Charged461
Percent Time Used104
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0032-07-029
4-WAY HAULERS, LLC (3.81)
BARRICADES UNLIMITED (2.19)
TRP CONSTRUCTION GROUP, LLC (1.63)
NICKEL ROCK, LLC (2.59)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (0.88)
J. H. ODEN CONTRACTING COMPANY (0.33)
WEST TEXAS ROCK RESOURCES, LLC (0.01)
Contract #01223201
Totals19299562.062556.0817583941.6491.1

CountySTONEWALL
HighwayUS 83
FromUS 380
ToFISHER COUNTY LINE
CSJ0033-01-038
Proj IDSTP 1302(058)
Work TypeSUPER-2 HIGHWAY
 
18.38914492854.1114300909.9898.6
Work Order02-16-22
Work Began04-28-22
Work Completed
Time Computed04-28-22
Contract Working Days396
Addl Days Granted19
Working Days Charged414
Percent Time Used99
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-01-038
DIIBS SPECIALISTS, LLC (2.90)
PINNACLE GRINDING AND GROOVING LLC (0.21)
FLAT LINE, INC. (1.64)
CONTRACTORS SERVICE, LTD. (0.36)
HJC FARMS, INC. (0.73)
PROFESSIONAL TRAFFIC CONTROL LLC (0.21)
Contract #01223001
Totals14492854.11160875.8014300909.9898.6

CountyJONES
HighwayUS 83
From1.0 MILES NORTH OF FM 3034
ToTAYLOR COUNTY LINE
CSJ0033-05-089
Proj IDF 2B24(277)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
4.12939496850.500.000.0
Work Order08-14-24
Work Began00-00-00
Work Completed
Time Computed10-13-24
Contract Working Days528
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-05-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243005
Totals39496850.500.000.000.0

CountyJONES
HighwayUS 83
FromFM 707
To0.25 MI NORTH OF FM 3034
CSJ0033-05-096
Proj IDSTP 2023(911)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3628354.034012699.6199.9
CountyTAYLOR
HighwayUS 83
FromBUS 83 INTERCHANGE
To1300' NORTH OF AMBLER AVE
CSJ0033-06-123
Proj IDSTP 2023(911)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2056618.30560655.2927.2
CountyJONES
HighwayUS 277
From0.25 MI SOUTH OF BUS 277-G
ToUS 83
CSJ0157-05-065
Proj IDSTP 2023(911)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2092536.241803745.3986.1
CountyTAYLOR
HighwaySL 322
FromN 10TH ST
ToLYTLE CREEK
CSJ2398-01-056
Proj IDSTP 2023(911)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2440353.3120133.750.8
Work Order07-19-23
Work Began10-02-23
Work Completed
Time Computed08-18-23
Contract Working Days250
Addl Days Granted0
Working Days Charged157
Percent Time Used62
Contractor(s)
ROADWAY SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-05-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06233212
Totals10217861.88547335.516397234.0462.6

CountySCURRY ETC
HighwayUS 84 ETC
FromGARZA COUNTY LINE
To.75 MILES S OF FM 1142
CSJ0053-07-043
Proj IDSTP 2023(793)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
11538452.964881358.1242.3
Work Order06-14-23
Work Began11-03-23
Work Completed
Time Computed07-17-23
Contract Working Days361
Addl Days Granted0
Working Days Charged194
Percent Time Used53
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0053-07-043
FC TRAFFIC CONTROL, INC. (0.38)
LINEAR TRAFFIC MARKINGS LLC (0.71)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.80)
JB PINNACLE GROUP, LLC (0.81)
USA AMTECH, INC. (0.53)
Contract #05233008
Totals11538452.96429696.064881358.1242.3

CountySCURRY
HighwayUS 84
FromHERMLEIGH (US 84 WBL ONLY)
ToNEAR FM 1613 (US 84 WBL ONLY)
CSJ0053-10-047
Proj IDC 53-10-47
Work TypeOVERLAY
 
9325296.750.000.0
Work Order08-01-24
Work Began00-00-00
Work Completed
Time Computed09-30-24
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0053-10-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243210
Totals9325296.750.000.000.0

CountySCURRY
HighwayUS 180
FromSH 350
ToSH 208
CSJ0053-17-037
Proj IDC 53-17-37
Work TypeOVERLAY
 
2.6592179456.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-24
Work Began00-00-00
Work Completed
Time Computed12-22-24
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0053-17-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243226
Totals2179456.150.000.000.0

CountyHOWARD
HighwayUS 87
From4 MILES N OF FM 846
To0.6 MILES N OF FM 2230
CSJ0068-08-070
Proj IDC 68-8-70
Work TypeOVERLAY
 
7656688.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0068-08-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243014
Totals7656688.520.000.000.0

CountySTONEWALL
HighwayUS 380
FromSALT FORK BRAZOS RIVER
To.
CSJ0106-04-036
Proj IDBR 2022(829)
Work TypeBRIDGE REPLACEMENT
 
8952032.006927606.6577.3
CountyKENT
HighwaySH 208
FromSALT FORK BRAZOS RIVER
To.
CSJ2011-02-015
Proj IDBR 2022(829)
Work TypeBRIDGE REPLACEMENT
 
5710494.005629194.3398.5
Work Order09-20-22
Work Began01-23-23
Work Completed
Time Computed01-23-23
Contract Working Days506
Addl Days Granted0
Working Days Charged397
Percent Time Used78
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0106-04-036
BARRICADES UNLIMITED (0.28)
CONTRACTORS SERVICE, LTD. (0.30)
LANCO TURF & SEEDING, INC. (0.15)
MARCOM"S MOWING SERVICE, LLC (0.15)
SCOTT DERR PAINTING CO, LLC (0.24)
PINNACLE GRINDING AND GROOVING LLC (0.04)
PRIMATE CONSTRUCTION, LP (0.13)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.94)
TORO BRAVO CONSTRUCTION, LLC (0.31)
TORO BRAVO CONSTRUCTION, LLC (0.08)
TRP CONSTRUCTION GROUP, LLC (0.28)
J. H. STRAIN & SONS, INC. (1.76)
JB PINNACLE GROUP, LLC (0.64)
PROFESSIONAL TRAFFIC CONTROL LLC (0.04)
Contract #08223006
Totals14662526.00460665.8612556800.9885.6

CountyHASKELL ETC
HighwaySH 6 ETC
FromRED PAINT CREEK
To.
CSJ0106-07-030
Proj IDBR 2022(761)
Work TypeBRIDGE MAINTENANCE
 
1729616.691847469.2799.9
Work Order09-15-22
Work Began11-15-22
Work Completed
Time Computed10-14-22
Contract Working Days124
Addl Days Granted100
Working Days Charged296
Percent Time Used132
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0106-07-030
S & S BRIDGE PAINTING, INC. (16.70)
HJC FARMS, INC. (19.40)
TRP CONSTRUCTION GROUP, LLC (2.16)
Contract #08223058
Totals1729616.6928071.121847469.2799.9

page 1 | page 2 | page 3