Monthly State Let Maintenance Report For Atlanta District As Of Nov 10, 2024 Page 2 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6462-18-001
Proj IDRMC - 646218001
Work TypeCABLE BARRIER REPAIR
 
0.010667815.0096708.9714.4
Work Order00-00-00
Work Began05-06-24
Work Completed
Time Computed05-06-24
Contract Working Days612
Addl Days Granted0
Working Days Charged148
Percent Time Used24
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-18-001
ELITE CASTLE RESOURCES LLC (90.11)
TIMBERTEX, INC. (2.02)
Contract #02244228
Totals667815.0037263.0096708.9714.4

CountyHARRISON
HighwayIH0020
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6462-19-001
Proj IDRMC - 646219001
Work TypeCABLE BARRIER REPAIR
 
0.010478435.00186108.5038.8
Work Order00-00-00
Work Began05-06-24
Work Completed
Time Computed05-06-24
Contract Working Days612
Addl Days Granted0
Working Days Charged151
Percent Time Used24
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-19-001
ELITE CASTLE RESOURCES LLC (90.20)
TIMBERTEX, INC. (2.82)
Contract #02244229
Totals478435.0010939.00186108.5038.8

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6464-42-001
Proj IDMMC - 646442001
Work TypeEMULSION
 
0.010325400.001231615.3899.9
Work Order00-00-00
Work Began05-16-24
Work Completed
Time Computed05-16-24
Contract Working Days120
Addl Days Granted120
Working Days Charged169
Percent Time Used70
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6464-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244028
Totals325400.00228983.851231615.3899.9

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6467-34-001
Proj IDRMC - 646734001
Work TypeRAISED PAVEMENT MARKERS
 
0.010858521.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP INFRASTRUCTURE SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6467-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08244207
Totals858521.000.000.000.0

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6467-35-001
Proj IDRMC - 646735001
Work TypeLARGE SIGN REPLACEMENT
 
0.010864875.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RISE UP CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6467-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07244203
Totals864875.000.000.000.0

CountyBOWIE
HighwayIH0030
From.
To.
CSJ6470-10-001
Proj IDMMC - 647010001
Work TypeLIMESTONE ROCK ASPHALT
 
0.0102893160.000.000.0
Work Order00-00-00
Work Began10-01-24
Work Completed
Time Computed10-01-24
Contract Working Days180
Addl Days Granted0
Working Days Charged31
Percent Time Used17
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6470-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08244034
Totals2893160.000.000.000.0