Monthly Local Let Maintenance Report For Bryan District As Of Nov 10, 2024 Page 1 Of 5

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWASHINGTON
HighwayMR0688
FromAT BRENHAM STATE SCHOOL
ToAT BRENHAM STATE SCHOOL
CSJ6250-83-001
Proj IDRMC - 625083001
Work TypeSURFACE TREAT PARKING LOTS
 
0.00139379.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days4
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6250-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03131701
Totals39379.850.000.000.0

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6315-09-001
Proj IDRMC - 631509001
Work TypePICNIC AREA MAINTENANCE
 
0.00125570.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TWO SISTER'S CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6315-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171703
Totals25570.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6319-89-001
Proj IDRMC - 631989001
Work TypeROADSIDE MOWING
 
225.457207044.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JMT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6319-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181709
Totals207044.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6373-13-001
Proj IDMMC - 637313001
Work TypeTYPE II BRINE SALT(MATERIALS ONLY)
 
0.00123600.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAHAN FOUNDATION & CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6373-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11201701
Totals23600.000.000.000.0

CountyWALKER
HighwayFM0247
FromFM 247 & FM 2821
ToFM 247 & FM 2821
CSJ6376-21-001
Proj IDSUP - 637621001
Work TypeSTATE USE PROJECT
 
0.01010067.6819203.9999.9
Work Order03-10-21
Work Began03-01-21
Work Completed
Time Computed03-10-21
Contract Working Days730
Addl Days Granted730
Working Days Charged1,341
Percent Time Used91
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-21-001
RUCON, INC. (0.00)
Contract #01211730
Totals10067.68544.5619203.9999.9

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6385-74-001
Proj IDSUP - 638574001
Work TypeJANITORIAL MAINTENANCE
 
0.01067227.3453371.5679.3
Work Order08-01-21
Work Began08-01-21
Work Completed
Time Computed08-01-21
Contract Working Days730
Addl Days Granted730
Working Days Charged1,188
Percent Time Used81
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6385-74-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #06211730
Totals67227.341217.2053371.5679.3

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6423-36-001
Proj IDRMC - 642336001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01089129.0055134.5061.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-04-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged667
Percent Time Used91
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6423-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11221706
Totals89129.000.0055134.5061.8

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6423-99-001
Proj IDRMC - 642399001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010239906.96339541.9299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-05-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged666
Percent Time Used91
Contractor(s)
WELLMANN ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6423-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11221701
Totals239906.968135.28339541.9299.9

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6424-02-001
Proj IDRMC - 642402001
Work TypeTREE REMOVAL
 
0.010187400.00122053.5065.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-02-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged638
Percent Time Used87
Contractor(s)
J&H EXCAVATION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6424-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221723
Totals187400.000.00122053.5065.1

CountyMILAM
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6424-06-001
Proj IDRMC - 642406001
Work TypeTREE REMOVAL
 
0.010279000.00240090.0086.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-30-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged672
Percent Time Used92
Contractor(s)
GV LANDSCAPE AND CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6424-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11221704
Totals279000.000.00240090.0086.0

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6427-53-001
Proj IDMMC - 642753001
Work TypeWINTER WEATHER MATERIAL
 
0.010201794.849040.914.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-10-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged357
Percent Time Used48
Contractor(s)
UNITED SALT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6427-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231701
Totals201794.840.009040.914.4

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6427-55-001
Proj IDMMC - 642755001
Work TypeWINTER WEATHER MATERIAL
 
0.010306608.8818235.975.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-27-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged401
Percent Time Used54
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6427-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231701
Totals306608.880.0018235.975.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6430-18-001
Proj IDRMC - 643018001
Work TypeILLUMINATION MAINTENANCE
 
0.010166278.5092969.1355.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-31-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged581
Percent Time Used79
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6430-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231701
Totals166278.500.0092969.1355.9

CountyROBERTSON
HighwayFM0485
FromVARIOUS
ToVARIOUS
CSJ6430-91-001
Proj IDRMC - 643091001
Work TypeBRIDGE SCOUR REPAIR
 
0.010222416.50188271.90100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-05-23
Work Completed09-16-24
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged23
Percent Time Used88
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6430-91-001
AREA WIDE PROTECTIVE, INC. (0.00)
AWP SAFETY (0.00)
Contract #06231704
Totals222416.5017970.90188271.90100.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6432-48-001
Proj IDMMC - 643248001
Work TypeCUTBACK
 
0.010148920.00442810.2799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-25-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged495
Percent Time Used91
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6432-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231702
Totals148920.0025811.50442810.2799.9

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6432-50-001
Proj IDMMC - 643250001
Work TypeCUTBACK
 
0.010199560.00393297.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-25-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged495
Percent Time Used91
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6432-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231703
Totals199560.000.00393297.6099.9

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6434-26-001
Proj IDSUP - 643426001
Work TypeJANITORIAL MAINTENANCE
 
0.01041668.0033476.9680.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6434-26-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #01231730
Totals41668.001340.9233476.9680.3

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6434-30-001
Proj IDSUP - 643430001
Work TypeJANITORIAL MAINTENANCE
 
0.01024699.2420335.1482.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6434-30-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #01231731
Totals24699.24998.1920335.1482.3

CountyMILAM
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6436-60-001
Proj IDSUP - 643660001
Work TypeJANITORIAL MAINTENANCE
 
0.01025943.4413936.5153.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged519
Percent Time Used71
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6436-60-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #02231730
Totals25943.44852.0913936.5153.7

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6438-25-001
Proj IDSUP - 643825001
Work TypeJANITORIAL MAINTENANCE
 
0.01049278.1633017.7067.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged580
Percent Time Used79
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6438-25-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #03231730
Totals49278.161562.8533017.7067.0

page 1 | page 2 | page 3 | page 4 | page 5