Monthly State Let Construction Report For Childress District As Of Nov 10, 2024 Page 2 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCHILDRESS
HighwayVA
FromDISTRICT WIDE
To.
CSJ0925-00-095
Proj IDC 925-00-95
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1197204.50881393.5073.6
Work Order04-18-24
Work Began06-17-24
Work Completed
Time Computed03-29-24
Contract Working Days185
Addl Days Granted0
Working Days Charged98
Percent Time Used52
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243226
Totals1197204.5062078.00881393.5073.6

CountyCHILDRESS
HighwayVA
FromDISTRICT WIDE
To.
CSJ0925-00-096
Proj IDC 925-00-96
Work TypeTRANSPORTATION NON-ROADWAY
 
1519265.560.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days142
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CENTERLINE TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243025
Totals1519265.560.000.000.0

CountyCHILDRESS
HighwayVA
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ0925-00-100
Proj IDSTP 2B24(244)FRS
Work TypeMISCELLANEOUS CONSTRUCTION
 
122600.000.000.0
Work Order08-01-24
Work Began00-00-00
Work Completed
Time Computed08-01-24
Contract Working Days39
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SYNERGY SIGNS & SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243258
Totals122600.000.000.000.0

CountyHALL
HighwayCR
FromCR 24 @ PARKER CREEK
To.
CSJ0925-09-036
Proj IDBR 2B23(251)
Work TypeBRIDGE REPLACEMENT
 
879885.40854749.8097.1
Work Order07-17-24
Work Began08-19-24
Work Completed
Time Computed07-17-24
Contract Working Days65
Addl Days Granted0
Working Days Charged53
Percent Time Used81
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-09-036
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.06)
FC TRAFFIC CONTROL, INC. (0.59)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.85)
HODGES AND SON CONSTRUCTION COMPANY, INC. (15.27)
TORO BRAVO CONSTRUCTION, LLC (0.75)
Contract #06243051
Totals879885.40147571.00854749.8097.1

CountyDICKENS
HighwayCR
From@ DUCK CREEK
To.
CSJ0925-15-014
Proj IDBR 2021(898)
Work TypeBRIDGE REPLACEMENT
 
1446464.001007052.0069.6
Work Order07-26-23
Work Began05-03-24
Work Completed
Time Computed08-26-23
Contract Working Days119
Addl Days Granted0
Working Days Charged90
Percent Time Used75
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0925-15-014
TEXAS SHAFTS, INC. (6.21)
FC TRAFFIC CONTROL, INC. (0.54)
LANCO TURF & SEEDING, INC. (0.55)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.78)
PENHALL COMPANY (0.29)
HERMANOS STEEL, LLC (5.91)
Contract #06233035
Totals1446464.00385514.361007052.0069.6

CountyFOARD
HighwayCR
From@ BEAVER CREEK
To.
CSJ0925-21-009
Proj IDBR 2020(321)
Work TypeBRIDGE REPLACEMENT
 
699120.000.000.0
Work Order09-26-24
Work Began00-00-00
Work Completed
Time Computed09-26-24
Contract Working Days101
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SKYLINE BRIDGE LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-21-009
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.24)
Contract #07243025
Totals699120.000.000.000.0

CountyWHEELER
HighwayFM 2473
FromON FM 2473, FROM SH 152, SOUTH
ToTEXAS AVENUE
CSJ2051-01-014
Proj IDSTP 2023(335)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
691555.0059900.008.6
Work Order09-26-24
Work Began10-28-24
Work Completed
Time Computed09-26-24
Contract Working Days101
Addl Days Granted0
Working Days Charged4
Percent Time Used3
Contractor(s)
STX CIVIL
SUBCONTRACTOR(S) FOR CCSJ: 2051-01-014
BARRICADES UNLIMITED (1.14)
Contract #08243040
Totals691555.0059900.0059900.008.6

page 1 | page 2