Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNUECES
HighwayCS
FromON GOLLIHAR RD FROM MUSTANG TRAIL
ToPENNINGTON DRIVE
CSJ0916-35-239
Proj IDSTP 2B23(211)HESG
Work TypeTRAFFIC CONTROL DEVICES
 
1.848302655.0039635.8013.0
Work Order11-08-23
Work Began00-00-00
Work Completed
Time Computed10-01-23
Contract Working Days134
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-35-239
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08233245
Totals302655.000.0039635.8013.0

CountyNUECES
HighwayCS
FromON SOUTH PORT AVE AT TARLTON AVE
ToSARITA STREET
CSJ0916-35-243
Proj IDSTP 2022(545)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.19267469.4059694.4088.4
CountyNUECES
HighwayCS
FromON TEXAN TRAIL ST FROM S STAPLES STREET
ToBUCCANEER DRIVE
CSJ0916-35-247
Proj IDSTP 2022(546)HESG
Work TypeTRAFFIC CONTROL DEVICES
 
45492.0042983.3494.4
CountyNUECES
HighwayCS
FromON TEXAN TRAIL FROM BUCCANEER DRIVE
ToSWANTNER DRIVE
CSJ0916-35-248
Proj IDSTP 2022(546)HESG
Work TypeTRAFFIC CONTROL DEVICES
 
40616.0038066.0093.7
Work Order10-31-22
Work Began06-28-23
Work Completed
Time Computed01-01-23
Contract Working Days68
Addl Days Granted0
Working Days Charged44
Percent Time Used64
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-35-243
IPQ CONSTRUCTION LLC (16.20)
Contract #08223263
Totals153577.4039473.68140743.7491.6

CountyJIM WELLS
HighwayCR
FromSTR. (AA0292001) TRANQUITAS CREEK
ToAPPROX. .15 MI W OF CR 465
CSJ0916-37-036
Proj IDBR 2024(963)
Work TypeBRIDGE REPLACEMENT
 
590058.080.000.0
CountyJIM WELLS
HighwayCR
FromSTR. (AA0292002) SAN ANDREAS CREEK
ToAPPROX. 1.5 MI W OF CR 465
CSJ0916-37-037
Proj IDBR 2024(978)
Work TypeBRIDGE REPLACEMENT
 
821038.390.000.0
Work Order10-02-24
Work Began00-00-00
Work Completed
Time Computed08-01-24
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-37-036
TEXAS ICON CONSTRUCTION, LLC (1.11)
HIGHWAY BARRICADES AND SERVICES, LLC (0.77)
AVILA AND SON"S L.L.C. (5.20)
Contract #06243047
Totals1411096.470.000.000.0

CountyBEE
HighwayFM 623
FromON FM 623 FROM .5 MI N OF FM883
To.5 MI S OF FM 883
CSJ0988-01-025
Proj IDC 988-1-25
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.6471284612.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed12-01-24
Contract Working Days96
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LCR TOTAL TRANSPORT LLC
SUBCONTRACTOR(S) FOR CCSJ: 0988-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243223
Totals1284612.000.000.000.0

CountyNUECES
HighwayFM 624
FromJIM WELLS COUNTY LINE
ToFM 666
CSJ0989-02-054
Proj IDF 2022(932)
Work TypeOVERLAY
 
6.1235788737.565698054.9499.9
CountyNUECES
HighwayFM 624
FromWEST LAKE DRIVE
ToFM 666
CSJ0989-02-056
Proj IDSTP 2022(933)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.9774327855.883916303.6190.4
Work Order09-21-22
Work Began12-05-22
Work Completed
Time Computed10-03-22
Contract Working Days255
Addl Days Granted34
Working Days Charged404
Percent Time Used139
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0989-02-054
HIGHWAY BARRICADES AND SERVICES, LLC (4.05)
COLD CREEK CONSTRUCTION, LTD (1.09)
LONE STAR EROSION CONTROL (3.49)
ANDERSON COLUMBIA CO., INC. (33.08)
BROOKE PAVING AND CONSTRUCTION LLC (0.07)
K. L. DURHAM CONSTRUCTION, L.L.C. (1.15)
WEST TEXAS ROCK RESOURCES, LLC (0.13)
Contract #08223010
Totals10116593.4473499.379614358.5596.4

CountySAN PATRICIO ETC
HighwayFM 666 ETC
FromCR 1441
ToCR 1740
CSJ1052-03-030
Proj IDSTP 2024(047)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.413854238.39858258.6699.9
Work Order10-23-23
Work Began05-15-24
Work Completed
Time Computed04-01-24
Contract Working Days119
Addl Days Granted0
Working Days Charged73
Percent Time Used61
Contractor(s)
MALDONADO-BURKETT, LLP
SUBCONTRACTOR(S) FOR CCSJ: 1052-03-030
SAFETY FIRST TRAFFIC SOLUTIONS, LLC (2.44)
Contract #09233026
Totals854238.3983178.29858258.6699.9

CountyJIM WELLS
HighwayFM 738
FromON FM738 FROM .8 MI S OF CR303
ToSOYARS AVE.
CSJ1087-01-018
Proj IDSTP 2B24(258)HRR
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.8181403302.29200280.7014.2
CountyJIM WELLS
HighwayFM 738
From0.5 MILES WEST OF SH 359
To1.3 MILES WEST OF SH 359
CSJ1087-02-011
Proj IDSTP 2B24(149)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
589719.2614825.802.5
Work Order08-01-24
Work Began10-14-24
Work Completed
Time Computed08-01-24
Contract Working Days136
Addl Days Granted0
Working Days Charged11
Percent Time Used8
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1087-01-018
SOIL TECH ADVANCE INC. (0.45)
STAFF CONCRETE CONSTRUCTION (20.60)
MURRAY CONSTRUCTION (2.26)
HIGHWAY BARRICADES AND SERVICES, LLC (2.10)
MALDONADO-BURKETT, LLP (7.23)
H J HENKE, LLC (1.25)
Contract #06243246
Totals1993021.55215106.50215106.5010.7

CountyKARNES
HighwayFM 743
FromON FM743 FROM US 181
To.815 MI E OF FM 623
CSJ1095-03-017
Proj IDSTP 2B23(261)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.8812555558.852725935.1699.9
Work Order09-07-23
Work Began10-25-23
Work Completed
Time Computed10-01-23
Contract Working Days127
Addl Days Granted13
Working Days Charged97
Percent Time Used69
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1095-03-017
HIGHWAY BARRICADES AND SERVICES, LLC (3.27)
MURRAY CONSTRUCTION (1.76)
BEAVER BOYS SERVICES LLC (0.58)
A K FUQUAY CONSTRUCTION (0.38)
Contract #08233238
Totals2555558.8538607.302725935.1699.9

CountyKARNES
HighwayFM 791
FromON FM 791
To@DRAW;SANANTONIORIVER;&SCAREDDOG CREEK
CSJ1122-01-033
Proj IDBR 2B23(118)
Work TypeBRIDGE MAINTENANCE
 
165558.00145065.4587.6
Work Order11-16-23
Work Began12-11-23
Work Completed
Time Computed12-01-23
Contract Working Days46
Addl Days Granted0
Working Days Charged21
Percent Time Used45
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1122-01-033
BARRICADES UNLIMITED (2.54)
Contract #10233230
Totals165558.003000.00145065.4587.6

CountyKARNES
HighwayFM 887
FromSH 123
ToFM 2724
CSJ1122-02-042
Proj IDF 2024(048)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.2237291794.136546577.0289.7
Work Order10-12-23
Work Began01-08-24
Work Completed
Time Computed11-01-23
Contract Working Days199
Addl Days Granted0
Working Days Charged181
Percent Time Used90
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1122-02-042
STAFF CONCRETE CONSTRUCTION (17.77)
INTERSTATE BARRICADES & MARKINGS, INC. (0.34)
PAVEMENT MARKINGS INC. (1.44)
MURRAY CONSTRUCTION (0.72)
LONE STAR EROSION CONTROL (4.95)
EGGEMEYER LAND CLEARING, LLC (0.50)
THE LEVY COMPANY, INC. (0.36)
LONE STAR PAVING COMPANY (41.08)
Contract #09233012
Totals7291794.13698300.136546577.0289.7

CountyKARNES
HighwayFM 887
FromSH 123
ToUS 181
CSJ1122-02-044
Proj IDC 1122-2-44
Work TypeREHABILITATION OF EXISTING ROAD
 
7.50413339130.792878865.3621.5
CountyKARNES
HighwayFM 887
FromINTERSECTION OF FM 791 AND CR 206
ToINTERSECTION OF US 181 AND FM 887 BYPASS
CSJ1122-05-006
Proj IDC 1122-5-6
Work TypeWIDEN NON-FREEWAY
 
2628481.152783886.7099.9
Work Order03-14-24
Work Began04-15-24
Work Completed
Time Computed04-01-24
Contract Working Days412
Addl Days Granted8
Working Days Charged123
Percent Time Used29
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1122-02-044
HIGHWAY BARRICADES AND SERVICES, LLC (0.08)
MURRAY CONSTRUCTION (0.54)
PAVEMENT MARKINGS INC. (0.94)
EGGEMEYER LAND CLEARING, LLC (0.34)
RELMCO, INC. (15.97)
J. H. ODEN CONTRACTING COMPANY (0.28)
A K FUQUAY CONSTRUCTION (1.93)
ANTS CONTRACTORS LLC (0.31)
Contract #02243208
Totals15967611.94500231.755662752.0635.4

CountyKARNES
HighwayFM 81
FromSH 123
ToUS 181
CSJ1123-01-016
Proj IDF 2024(379)
Work TypeOVERLAY
 
5.1646545352.984801919.0273.7
Work Order12-13-23
Work Began01-09-24
Work Completed
Time Computed01-01-24
Contract Working Days123
Addl Days Granted30
Working Days Charged171
Percent Time Used111
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1123-01-016
ANTS CONTRACTORS LLC (8.64)
MURRAY CONSTRUCTION (1.94)
HIGHWAY BARRICADES AND SERVICES, LLC (2.48)
WEST TEXAS ROCK RESOURCES, LLC (0.17)
A K FUQUAY CONSTRUCTION (2.97)
EGGEMEYER LAND CLEARING, LLC (0.24)
DUSTROL, INC. (0.90)
LISKA CONSTRUCTION COMPANY, INC. (0.19)
MPB, INC. (0.12)
Contract #11233013
Totals6545352.98220813.654801919.0273.7

CountyKARNES
HighwayFM 81
FromSH 80
ToSH 123
CSJ1123-02-016
Proj IDC 1123-2-16
Work TypeREHABILITATION OF EXISTING ROAD
 
6.1208531763.889240054.3199.9
Work Order12-11-20
Work Began01-21-21
Work Completed
Time Computed01-01-21
Contract Working Days415
Addl Days Granted32
Working Days Charged439
Percent Time Used98
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1123-02-016
BEAVER BOYS SERVICES LLC (1.05)
(INACTIVE)DEPENDABLE FENCE & WELDING CO. INC. (2.01)
FLASHER EQUIPMENT COMPANY (1.56)
LONE STAR EROSION CONTROL (1.92)
MURRAY CONSTRUCTION (0.81)
PINNACLE GRINDING AND GROOVING LLC (0.10)
HIGHWAY BARRICADES AND SERVICES, LLC (0.18)
F & W ELECTRICAL CONTRACTORS, INC. (0.46)
Contract #11203029
Totals8531763.888434.759240054.3199.9

CountyNUECES
HighwayFM 43
From4 WAY STOP AT FM 665
ToW OF CR 49
CSJ1557-01-043
Proj IDC 1557-1-43
Work TypeOVERLAY
 
5154966.445571206.7499.9
Work Order07-22-21
Work Began11-16-21
Work Completed
Time Computed08-01-21
Contract Working Days187
Addl Days Granted65
Working Days Charged323
Percent Time Used128
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1557-01-043
TRAF-TEX, INC. (1.32)
HIGHWAY BARRICADES AND SERVICES, LLC (4.27)
SOIL TECH ADVANCE INC. (0.53)
FUQUAY, INC. (4.19)
PERFORMANCE EQUIPMENT SERVICE (0.51)
Contract #06213017
Totals5154966.440.005571206.7499.9

CountyGOLIAD
HighwayFM 1961
FromON FM1961 FROM LASSMAN RD
ToHENCERLING RD
CSJ1843-01-023
Proj IDSTP 2024(125)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.7342869910.681989901.5169.3
Work Order11-16-23
Work Began05-15-24
Work Completed
Time Computed01-01-24
Contract Working Days152
Addl Days Granted0
Working Days Charged108
Percent Time Used71
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1843-01-023
EGGEMEYER LAND CLEARING, LLC (2.11)
HIGHWAY BARRICADES AND SERVICES, LLC (0.62)
PAVEMENT MARKINGS INC. (1.61)
DEPENDABLE FENCE (2.04)
A K FUQUAY CONSTRUCTION (1.54)
MURRAY CONSTRUCTION (1.39)
STAFF CONCRETE CONSTRUCTION (15.51)
Contract #10233212
Totals2869910.68669652.651989901.5169.3

CountyKARNES
HighwayFM 2102
FromFM 626
ToFM 99
CSJ2234-02-009
Proj IDC 2234-2-9
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8073872.883395125.0042.0
Work Order06-12-24
Work Began07-01-24
Work Completed
Time Computed07-01-24
Contract Working Days238
Addl Days Granted7
Working Days Charged80
Percent Time Used32
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2234-02-009
BEAVER BOYS SERVICES LLC (0.74)
HIGHWAY BARRICADES AND SERVICES, LLC (1.62)
MURRAY CONSTRUCTION (0.49)
SOIL TECH ADVANCE INC. (1.06)
Contract #05243018
Totals8073872.881125066.513395125.0042.0

CountyNUECES
HighwaySH 361
FromAT FERRY LANDINGS IN PORT ARANSAS
To.
CSJ2263-02-106
Proj IDFT 2263-2-106
Work TypeFERRY BOAT
 
0.08358651776.0011641384.4219.8
Work Order06-07-23
Work Began02-19-24
Work Completed
Time Computed10-02-23
Contract Working Days719
Addl Days Granted0
Working Days Charged136
Percent Time Used18
Contractor(s)
RUSSELL MARINE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2263-02-106
HI-TECH ELECTRIC, INC. (13.38)
ALL-TECH FUEL SYSTEMS, LLC (1.56)
WEBER-BALKE FOUNDATION COMPANY, INC (0.56)
D & C FENCE CO., INC. (0.21)
SAFETY FIRST TRAFFIC SOLUTIONS, LLC (0.04)
LEDESMA TUNCHEZ MARINE LLC (0.03)
RIO CONTROLS & HYDRAULICS INC. (1.37)
MIRAGE INDUSTRIAL GROUP, LLC (2.13)
AFCO 360, LLC (0.00)
PBI INTERNATIONAL, LLC (0.00)
BADGER DAYLIGHTING CORP. (0.31)
APACHE INDUSTRIAL SERVICES, INC. (0.04)
Contract #05233203
Totals58651776.002522242.4811641384.4219.8

CountySAN PATRICIO
HighwayFM 2986
FromAT INTERSECTION OF HEAVY HAUL RD
To.
CSJ3026-01-034
Proj IDCC 3026-1-34
Work TypeTRAFFIC CONTROL DEVICES
 
417141.40441775.8899.9
Work Order11-16-23
Work Began03-18-24
Work Completed
Time Computed12-01-23
Contract Working Days99
Addl Days Granted7
Working Days Charged88
Percent Time Used83
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3026-01-034
PAVEMENT MARKINGS INC. (3.71)
FIBERTEL, LLC (3.85)
HIGHWAY BARRICADES AND SERVICES, LLC (1.81)
WEBER-BALKE FOUNDATION COMPANY, INC (0.79)
ALAMO CRANE SERVICE, INC. (0.03)
TAHOE TRUCKING LLC (0.11)
Contract #10233232
Totals417141.400.00441775.8899.9

CountyGOLIAD
HighwaySH 239
FromUS 183
ToREFUGIO COUNTY LINE
CSJ3075-01-011
Proj IDF 2022(276)
Work TypeREHABILITATION OF EXISTING ROAD
 
14.99714990020.8413309204.5289.0
Work Order01-05-22
Work Began04-19-22
Work Completed
Time Computed02-01-22
Contract Working Days371
Addl Days Granted44
Working Days Charged448
Percent Time Used107
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3075-01-011
HIGHWAY BARRICADES AND SERVICES, LLC (1.64)
TEXAS ICON CONSTRUCTION, LLC (2.60)
ROADWAY SPECIALTIES, INC. (0.36)
H J HENKE, LLC (0.11)
TEXAS GUARDRAIL CONTRACTORS LLC (4.45)
AVILA AND SON"S L.L.C. (0.17)
Contract #12213207
Totals14990020.84285071.1213309204.5289.0

CountyNUECES
HighwaySS 3
FromSH 358
ToEND OF STATE MAINTENANCE
CSJ3596-01-009
Proj IDF 2024(750)
Work TypeOVERLAY
 
3.3576716237.776872452.2399.9
Work Order03-06-24
Work Began07-01-24
Work Completed
Time Computed04-01-24
Contract Working Days75
Addl Days Granted0
Working Days Charged77
Percent Time Used102
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3596-01-009
HIGHWAY BARRICADES AND SERVICES, LLC (2.39)
BROOKE PAVING AND CONSTRUCTION LLC (10.95)
TEXAS ICON CONSTRUCTION, LLC (1.62)
K. L. DURHAM CONSTRUCTION, L.L.C. (4.54)
Contract #02243222
Totals6716237.77367148.506872452.2399.9