Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNAVARRO
HighwayFM 3041
FromCHAMBERS CREEK
ToFM 1129
CSJ3090-01-012
Proj IDF 2023(609)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.9186473924.216108902.0594.3
Work Order05-17-23
Work Began07-10-23
Work Completed
Time Computed07-10-23
Contract Working Days247
Addl Days Granted0
Working Days Charged244
Percent Time Used98
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 3090-01-012
TEXAS TRAFFIC AND BARRICADE, LLC (0.32)
FORTSON CONTRACTING, INC. (1.40)
WITHERS CONSTRUCTION, LLC (1.00)
J & M CONTRACTING, COMPANY (20.94)
WEST TEXAS ROCK RESOURCES, LLC (0.10)
D. I. J. CONSTRUCTION, INC. (0.60)
A. E. MOORE CONSTRUCTION, INC. (3.70)
PROFESSIONAL TRAFFIC CONTROL LLC (0.00)
Contract #04233209
Totals6473924.21160679.866108902.0594.3