Monthly State Let Construction Report For Dallas District As Of Oct 10, 2024 Page 8 Of 8
Last Update: Thursday, October 10, 2024
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | NAVARRO |
Highway | FM 3041 |
From | CHAMBERS CREEK |
To | FM 1129 |
CSJ | 3090-01-012 |
Proj ID | F 2023(609) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 2.918 | 6473924.21 | | 6108902.05 | 94.3 |
Work Order | 05-17-23 |
Work Began | 07-10-23 |
Work Completed | |
Time Computed | 07-10-23 |
Contract Working Days | 247 |
Addl Days Granted | 0 |
Working Days Charged | 244 |
Percent Time Used | 98 |
Contractor(s) |
KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 3090-01-012 TEXAS TRAFFIC AND BARRICADE, LLC (0.32) FORTSON CONTRACTING, INC. (1.40) WITHERS CONSTRUCTION, LLC (1.00) J & M CONTRACTING, COMPANY (20.94) WEST TEXAS ROCK RESOURCES, LLC (0.10) D. I. J. CONSTRUCTION, INC. (0.60) A. E. MOORE CONSTRUCTION, INC. (3.70) PROFESSIONAL TRAFFIC CONTROL LLC (0.00)
|
Contract # | 04233209 |
| Totals | 6473924.21 | 160679.86 | 6108902.05 | 94.3 |
|